This document is an amendment to a solicitation for the Marion Job Order Contract (JOC) for the Marion VAMC in Illinois, Solicitation Number 36C25524R0056. The amendment provides answers to contractors' questions received during a site visit, revises the Proposal Submittal Instructions, and provides corrected attachments. The key details are:

The amendment addresses questions related to the Quality Control Plan, Relevant Experience, and Past Performance requirements. It clarifies that projects used for Relevant Experience can also be used for Past Performance, and that projects larger than the $500K threshold will be accepted. The Proposal Submittal Instructions have been revised to align with the requirements in the Statement of Work. Attachment 2 - Performance Relevancy Survey and Attachment 3 - Surety Form have also been revised. All other terms and conditions remain unchanged.

View the file

Other files for this federal contract opportunity

Other files attached to Z2DA--MARION Job Order Contract (JOC), newest first.
File Type Posted
Pre_Bid_Attendance 08152024.pdf PDF
36C25524R0056 0003.docx DOCX document
Attachment 3 - Surety Form Rev. 2.docx DOCX document
PROPOSAL SUBMITTAL INSTRUCTIONS revision 2.docx DOCX document
Attachment 2 - Performance Relevancy Survey rev. 2.docx DOCX document
36C25524R0056 0001.docx DOCX document
Attachment 4- Specification Section 01 35 26- Safety Requirements 05012024.pdf PDF
Attachment 2 - Performance Relevancy Survey.docx DOCX document
36C25524R0056_1.docx DOCX document
Attachment 3-Surety Form.docx DOCX document
Attachment 1 - Past Performance Questionnaire.docx DOCX document
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7.

ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF

PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE

OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERE

D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED

STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF

CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF

SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 08-26-2024 TBD By Task Order 36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway Leavenworth KS 66048 36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway Leavenworth KS 66048 To all Offerors/Bidders

36C25524R0056 08-09-2024

X X

Marion Job Order Contract (JOC) for Marion VAMC, Marion, Illinois.

The above solicitation is hereby amended as follows:

a. To provide answers to contractor's questions received from site visit on 08/25/2024 starting in page 2.

b. To provide a revis ed Proposal Submittal Instruction to reflect minor changes in Factors #2 and #3. The revised Proposal Submittal Instruction is attached and replaces the original Proposal Submittal Instruction in its entirety.

c. To provide a corrected copy of the attachment 2 and 3. Please use the corrected copy as required.

d. All other terms and conditions remain unchanged.

CONTINUATION PAGE

QUESTIONS RECEIVED FROM SITE VISIT DATED 08/15/2024 FOR MARION JOC

QUESTION 1: Subfactor 2 a: Quality Control: Do you want the actual Plan, or a description?

ANSWER 1: The subfactor 2a in the Proposal Submittal Instructions was revised to match the Quality Control Plan section of the Statement of Work in page 49 (page 49 of your copy but page 48 of the CO’s copy) of the originally published solicitation. Please use the revised Proposal Submittal Instruction for factor 2.a as attached. The revised Proposal Submittal Instruction replaces the originally published Proposal Submittal Instruction in its entirety.

QUESTION 2: Subfactor 2a asks for description, but page 49 (page 48 my copy) seems to say put the whole plan in the proposal.

ANSWER 2: No changes on Quality Control Plan section of the Statement of Work but changes were made on subfactor 2a in the Proposal Submittal Instruction to reflect the same requirement from Quality Control section of the Statement of Work.

QUESTION 3: Should sub-factor 2 Technical approach actually say Factor 2 Technical approach?

ANSWER 3: This was corrected in the Amendment 0001 to the solicitation that was posted in SAM.gov to read “Factor 2-Technical Approach”

QUESTION 4: Factor 3. Relevant Experience: Are these projects separate from the projects listed in Factor 4 Past performance?

ANSWER 4: Factors 3 and 4 projects can be the same project if they meet the requirements of factors 3 or 4. The past performance from projects used in factor 3 is acceptable for factor 4. Please read the revised proposal submittal instructions for the timeline used on past performance for these factors.

QUESTION 5: For factor 3 there is a list of project information to be submitted. Are we required to use the Attachment 2 survey for relevant experience?

ANSWER 5: No, you are not required to use attachment 2. You can use your own form but please ensure you are submitting your project information in accordance with factor 3 requirement.

QUESTION 6: We noticed that attachment #2 has a different solicitation number. Could you provide the correct attachment?

ANSWER 6: Attachment 2 solicitation number was corrected from 36C25524R0054 to 36C25524R0056 and is attached. The original attachment 2 is saved in word document. You can also edit and correct one digit of the solicitation number for this JOC solicitation in the attachment 2.

QUESTION 7: There is some conflicting information that is raising some questions. Factor 3 Relevant Experience states projects should have been started and completed in the last 3 years. However, attachment #2 form states projects may be on-going and cannot have been completed any later than 5 years prior to the issuance of this solicitation. Can you please clarify? We feel that if this is in fact started and completed jobs within the last 3 years it is conflicting and appears to be limiting competition or written to favor of the incumbent contractor.

ANSWER 7: Factor 3 Relevant Experience has been revised to match with the attachment 2 requirement. The Proposal Submittal Instruction has been revised to reflect this change. Please use the attached, revised copy of the Proposal Submittal Instruction.

QUESTION 8: The attachment #2 form does not match the instructions in Factor 3. We request that the instructions are revised to match the form.

ANSWER: The attachment 2 has been revised to match with factor 3. Please use the revised attachment 2.

QUESTION 9: Will you accept previously submitted PPQs or CPARS if we have them?

ANSWER 9: Yes, if the PPQ or CPARS were submitted within the last five years.

QUESTION 10: Will you accept projects that are larger in magnitude than $500K under past performance?

ANSWER 10: yes.

QUESTION 11: Factor 4 Past Performance states again projects completed within the last 5 years. Does this mean we can submit different projects from those listed in relevant experience?

ANSWER 11: yes, if projects are similar in scope of work to this project.

A.1 List of Attachments

See attached document: PROPOSAL SUBMITTAL INSTRUCTIONS revision 2.

See attached document: Attachment 2 - Performance Relevancy Survey rev. 2.

See attached document: Attachment 3 - Surety Form Rev. 2.

Amendment 0001 – Solicitation 36C25524R0056

File details come from the government source that posted it. Updated .