This pre-solicitation notice describes an upcoming solicitation for mechanical systems replacement services. The Department of Veterans Affairs seeks to replace mechanical systems in Buildings 18 and 60 at the Jefferson Barracks VA Medical Center for an estimated cost between $2-5 million. The NAICS code is 238220 with a small business size standard of $16.5 million. The project duration is estimated at 426 calendar days. The solicitation will be issued on April 7th via FedBizOpps. The contractor must perform at least 25% of general construction labor. The acquisition will utilize the Best Value Lowest Price Technically Acceptable process and award without discussions. Firms must register in SAM and VetBiz as a Service-Disabled Veteran-Owned Small Business to be eligible for this total SDVOSB set-aside. A pre-solicitation site visit will be scheduled for interested sources.
36C25520R0063 657-19-103JB - Combined Drawings 100PCT_Part2.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25520R0063-014.pdf | ||
| 36C25520R0063-016.pdf | ||
| 36C25520R0063-011.pdf | ||
| 36C25520R0063-006.pdf | ||
| 36C25520R0063-008.pdf | ||
| 36C25520R0063-015.pdf | ||
| 36C25520R0063-009.pdf | ||
| 36C25520R0063-002.docx | DOCX document | |
| 36C25520R0063-013.pdf | ||
| 36C25520R0063-007.pdf | ||
| 36C25520R0063-003.pdf | ||
| 36C25520R0063-010.pdf | ||
| 36C25520R0063-012.pdf | ||
| 36C25520R0063-005.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t o n e e ig h th in c h o n e fo o t
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
Veterans Health
Administration
VA FORM 08-6231
Drawing Title Project Title
Location
Date Checked Drawn
Project Number
Building Number
Drawing Number
CONSULTANTS: 657-19-103JB
VA Health Care System Approval:
Revision: Date:
ARCHITECT/ENGINEER:
750 W HAMPDEN AVE
SUITE 300
ENGLEWOOD, CO 80110
(720) 550-6307
WWW.VALHALLAENGINEERING.COM VEG 19.7
100% CONTRACT DOCUMENT SUBMITTAL DRAWINGS
JEFFERSON BARRACKS
1 JEFFERSON BARRACKS DRIVE - ST. LOUIS, MO 63125
02/10/2020
/1
/2
:1 :0
A
M
00-MG-507
MECHANICAL DETAILS
18 & 60
FCA - REPLACE MECHANICAL
SYSTEMS IN BUILDING 18 & 60
DD ANT Drawing # 20 of 77
NOTES:
1. SEE SHEET M-001 FOR SEISMIC RESTRAINT NOTES AND FACILITY-SPECIFIC SEISMIC
DESIGN BASIS PARAMETERS.
2. FIGURES ARE FROM FEMA E-74 REDUCING THE RISKS OF NONSTRUCTURAL
EARTHQUAKE DAMAGE - A PRACTICAL GUIDE, DECEMBER 2012.
NTS
FIGURE 6.4.1.5-6 CABLE AND RIGID BRACE ATTACHMENTS TO STRUCTURE
NTS
FIGURE 6.4.1.5-7 HANGER ATTACHMENT DETAILS
NTS
FIGURE 6.4.1.6-2 SUSPENDED EQUIPMENT
NTS
FIGURE 6.4.3.1-11 RIGID BRACING - SINGLE PIPE TRANSVERSE
NTS
FIGURE 6.4.3.1-12 CABLE BRACING - SINGLE PIPE TRANSVERSE
th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t o n e e ig h th in c h o n e fo o t
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
Veterans Health
Administration
VA FORM 08-6231
Drawing Title Project Title
Location
Date Checked Drawn
Project Number
Building Number
Drawing Number
CONSULTANTS: 657-19-103JB
VA Health Care System Approval:
Revision: Date:
ARCHITECT/ENGINEER:
750 W HAMPDEN AVE
SUITE 300
ENGLEWOOD, CO 80110
(720) 550-6307
WWW.VALHALLAENGINEERING.COM VEG 19.7
100% CONTRACT DOCUMENT SUBMITTAL DRAWINGS
JEFFERSON BARRACKS
1 JEFFERSON BARRACKS DRIVE - ST. LOUIS, MO 63125
02/10/2020
/1
/2
:1 :0
A
M
00-MG-508
MECHANICAL DETAILS
18 & 60
FCA - REPLACE MECHANICAL
SYSTEMS IN BUILDING 18 & 60
DD ANT Drawing # 21 of 77
NTS
FIGURE 6.4.3.1-13 RIGID BRACING - SINGLE PIPE ALTERNATE TRANSVERSE
NTS
FIGURE 6.4.3.1-14 RIGID BRACING - SINGLE PIPE
LONGITUDINAL
NTS
FIGURE 6.4.3.1-15 RIGID BRACING - TRAPEZE SUPPORTED PIPING
NTS
FIGURE 6.4.3.1-16 CABLE BRACING - TRAPEZE SUPPORTED PIPING
NTS
FIGURE 6.4.6.1-8 SUSPENDED DUCTWORK
NOTES:
1. SEE SHEET M-001 FOR SEISMIC RESTRAINT NOTES AND FACILITY-SPECIFIC SEISMIC
DESIGN BASIS PARAMETERS.
2. FIGURES ARE FROM FEMA E-74 REDUCING THE RISKS OF NONSTRUCTURAL
EARTHQUAKE DAMAGE - A PRACTICAL GUIDE, DECEMBER 2012.
STEAM CONDENSATE PUMP SCHEDULE
MARK LOCATION
SYSTEM
AND/OR
SERVICE
TYPE UNIT
FLOW
EACH
PUMP
HEAD
MIN
RECEIVER
SIZE REMARKS
GPM PSIG GAL
18-CRP-1 BLDG 18 - 002 BLDG 18 STEAM DRIVEN 4.5 40 3.2 1
NOTES:
1. PROVIDE NON-RESETTABLE HOUR METERS TO LOG RUN TIME OF EACH PUMP.
ELECTRIC WATER HEATER SCHEDULE
MARK LOCATION
AREA AND/OR BLDG
SERVED
SYSTEM AND/OR
SERVICE
TYPE
RECOVERY
@ 60 °F RISE
RELIEF VALVE
SETTING NO OF
ELEMENTS
ELECTIRCAL INPUT
REMARKS
GAL/HR PSIG TOTAL kW kW PER
ELEMENT
PHASE VOLT
18-DWH-1 BLDG 18 - 002 BLG 18 DOMESTIC HOT WATER
INSTANTANEOUS
ELECTRIC
369 70 12 54 4.5 3 208 1
NOTES:
1. BASIS OF DESIGN: TANKLESS INC. CE 54KW.
STEAM TO WATER HEAT EXCHANGER SCHEDULE
MARK LOCATION
AREA
AND/OR
BLDG
SERVED
SYSTEM
AND/OR
SERVICE
TYPE
WATER CONDITIONS STEAM PRESSURE
CONTROL VALVE TRAP
REMARKSFLOW EWT LWT WPD
ENT
CONTROL
VALVE
ENT HEAT
EXCHANGER
GPM °F °F FT PSIG PSIG Cv SIZE - IN LBS/HR TRAP #
18-HX-1A
18-HX-1B
BLDG 18 - 002 BLDG 18
HEATING
WATER
SHELL &
TUBE
90 160 180 1.8 15 5 1-1/4" 950 1, 2
NOTES:
1. BASIS OF DESIGN: ARMSTRONG WS-0603-200-1CSSSSNN-20 WITH ARMSTRON 1500 CONTROL VAVLE OR APPROVED EQUAL.
2. SEE CONTROLS SHEET M-601 FOR REDUNDANT HX SEQUENCE.
STEAM PRESSURE RELIEF VALVE SCHEDULE
MARK LOCATION SYSTEM
TEMPERATURE
MINIMUM
CAPACITY
INLET
PRESSURE
SET
PRESSURE REMARKS
°F LBS/HR PSIG PSIG
18-PRV-1A 18-002 PRV STATION 1/3 340 512 105 17 1, 2
18-PRV-1B 18-002 PRV STATION 2/3 340 737 105 17 1, 3
NOTES:
1. PRVS SHALL BE INSTALLED IN A 1/3-2/3 CAPACITY PRV STATION PER DETAIL.
2. BASIS OF DESIGN ARMSTONG INTERNATIONAL GP-2000 1/2" 50%
PORT.
3. BASIS OF DESIGN ARMSTONG INTERNATIONAL GP-2000 3/4" 50% PORT.
GLYCOL FEEDER SCHEDULE
MARK SERVICE
GLYCOL
TYPE
GLYCOL
PERCENTAGE
TANK VOLUME
(GAL)
PUMP CAPACITY
ELECTRICAL DATA
MANUFACTURER AND MODEL REMARKSPOWER
VOLT PHASE RPM HZ
HP
18-GMP-01
HEATING WATER
AND CHILLED
WATER
PROPYLENE 30% 50
2 INDEPENDENT
1.5 GPM AT 70 PSI
1/3 115 1 1750 60
WESSELS DUPLEX GMPD-SERIES
MAKEUP PACKAGE
INCLUDE LOW LEVEL LIGHT AND
AUDIBLE ALARM.
BUILDING 18 - STEAM TRAP SCHEDULE
MARK LOCATION
SYSTEM
AND/OR
SERVICE
CAPACITY AT
MIN DIFF
PRESS
MIN DIFF
PRESS
MIN INLET
PRESS TRAP TYPE
TRAP SIZE
REMARKS
LBS/HR PSI PSI IN
18-TRP-1 002 PRV 1050 85 105 IB 3/4 -
18-TRP-2 002 PRV 735 10 15 F/T 5/16 -
18-TRP-3 002
HEAT
EXCHANGERS
1050 5 7 IB 5/16 SIZE WITH LARGE VENT
18-TRP-4 003 HUMIDIFIER 105 10 15 IB 1/8 -
60-TRP-5 003 MAU 105 10 15 F/T 1/8 -
EXPANSION TANK SCHEDULE
MARK
SYSTEM AND/OR
SERVICE
TYPE
APPROX
SYSTEM
VOLUME
SYSTEM TEMPERATURE
RANGE
INITIAL PRESSURE IN TANK
MAX OPERATING
PRESSURE
FILL PRESSURE AT TANK
MIN VOLUME TANK
MIN ACCEPTANCE
VOLUME
PIPE SIZE TO
TANK
MAKE-UP WATER
FILL SIZE MANUFACTURER AND
MODEL
REMARKS
MIN MAX
RELIEF
VALVE
AT TANK
GAL °F °F PSIG PSIG PSIG PSIG GAL GAL IN IN
18-ET-01 HEATING WATER
VERTICAL
DIAPHRAGM
349 50 180 12 45 50 30 38.4 9.65 1" 1/3
B&G D-80V OR
APPROVED EQUAL
18-ET-02 CHILLED WATER
VERTICAL
DIAPHRAGM
210 42 80 12 20 25 12 20.5 2.1 1/2 1/3
B&G D-40 OR APPROVED
EQUAL
PUMP SCHEDULE
MARK LOCATION
AREA AND/OR
BLDG SERVED
SYSTEM AND/OR
SERVICE
TYPE
CIRCULATING FLUID
MIN % EFF
ELECTRICAL MOTOR
FLUID
FLOW HEAD TEMPERATURE
NOMINAL
POWER PHASE VOLT HZ MAX RPM SPEED CONTROL REMARKS
GPM FT °F HP
18-CHWP-1 CHILLER BLDG 18 CHILLED WATER
DUPLEX BASE
MOUNTED
30% PG CHILLED WATER 157.3 37.6 44 49 5 3 480 60 2940 VSD
PROVIDED BY CHILLER
MANUFACTURER.
18-HHW-P-1 BLDG 18 - 002 BLDG 18 HEATING WATER
INLINE
CIRUCLATOR
30% PG HEATING WATER 90 51 180 65 3 3 480 60 3030 VSD BELL & GOSSET
18-HHW-P-2 BLDG 18 - 002 BLDG 18 HEATING WATER
INLINE
CIRUCLATOR
30% PG HEATING WATER 90 51 180 65 3 3 480 60 3030 VSD BELL & GOSSET
th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t o n e e ig h th in c h o n e fo o t
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
Veterans Health
Administration
VA FORM 08-6231
Drawing Title Project Title
Location
Date Checked Drawn
Project Number
Building Number
Drawing Number
CONSULTANTS: 657-19-103JB
VA Health Care System Approval:
Revision: Date:
ARCHITECT/ENGINEER:
750 W HAMPDEN AVE
SUITE 300
ENGLEWOOD, CO 80110
(720) 550-6307
WWW.VALHALLAENGINEERING.COM VEG 19.7
100% CONTRACT DOCUMENT SUBMITTAL DRAWINGS
JEFFERSON BARRACKS
1 JEFFERSON BARRACKS DRIVE - ST. LOUIS, MO 63125
02/10/2020
/1
/2
:1 :0
A
M
00-MG-601
MECHANICAL EQUIPMENT SCHEDULES
18 & 60
FCA - REPLACE MECHANICAL
SYSTEMS IN BUILDING 18 & 60
DD MR Drawing # 22 of 77
TERMINAL UNIT SCHEDULE
MARK UNIT SIZE EAT LAT
AIR FLOW REHEAT
MANUFACTURER AND
MODELMAX (CFM) MIN (CFM)
HEATING
(CFM)
MAX
TOTAL
APD
EWT LWT GPM MBH
VAV-1-1A 6 60 °F 90 °F 410 410 410 0.19 180.0 °F 141.0 °F 0.7 13.3 TITUS DESV
VAV-1-1B 6 60 °F 90 °F 260 225 230 0.04 180.0 °F 156.7 °F 0.7 7.5 TITUS DESV
VAV-1-1C 6 60 °F 90 °F 425 420 420 0.2 180.0 °F 141.2 °F 0.7 13.7 TITUS DESV
VAV-1-1D 4 60 °F 91 °F 140 120 140 0.01 180.0 °F 148.3 °F 0.3 4.7 TITUS DESV
VAV-1-1E 8 60 °F 90 °F 495 490 490 0.16 180.0 °F 132.4 °F 0.7 15.9 TITUS DESV
VAV-1-2 6 60 °F 90 °F 360 220 250 0.06 180.0 °F 160.0 °F 0.8 8.1 TITUS DESV
VAV-1-3 6 60 °F 90 °F 270 180 200 0.04 180.0 °F 152.3 °F 0.5 6.5 TITUS DESV
VAV-1-4 6 60 °F 90 °F 210 155 170 0.03 180.0 °F 149.7 °F 0.4 5.5 TITUS DESV
VAV-1-5 6 60 °F 90 °F 360 200 275 0.06 180.0 °F 164.0 °F 1.1 8.9 TITUS DESV
VAV-1-6 6 60 °F 90 °F 285 235 270 0.04 180.0 °F 163.2 °F 1.1 8.8 TITUS DESV
VAV-1-7 6 60 °F 90 °F 420 215 250 0.08 180.0 °F 160.0 °F 0.8 8.1 TITUS DESV
VAV-1-8 6 60 °F 90 °F 380 240 275 0.07 180.0 °F 164.0 °F 1.1 8.9 TITUS DESV
VAV-1-9 8 60 °F 90 °F 440 240 275 0.06 180.0 °F 148.8 °F 0.6 8.9 TITUS DESV
VAV-1-10 10 60 °F 90 °F 830 355 580 0.09 180.0 °F 167.7 °F 3.1 18.8 TITUS DESV
VAV-1-11 6 60 °F 90 °F 220 115 175 0.03 180.0 °F 150.2 °F 0.4 5.7 TITUS DESV
VAV-1-12 6 60 °F 96 °F 230 50 110 0.03 180.0 °F 150.9 °F 0.3 4.3 TITUS DESV
VAV-1-13 6 60 °F 90 °F 210 145 165 0.03 180.0 °F 149.2 °F 0.4 5.4 TITUS DESV
VAV-1-14 8 60 °F 90 °F 690 415 445 0.12 180.0 °F 171.7 °F 3.6 14.5 TITUS DESV
VAV-1-15 6 60 °F 90 °F 495 360 405 0.26 180.0 °F 140.9 °F 0.7 13.2 TITUS DESV
VAV-1-16 8 60 °F 90 °F 670 360 415 0.11 180.0 °F 167.9 °F 2.3 13.5 TITUS DESV
VAV-1-17 8 60 °F 90 °F 495 375 425 0.07 180.0 °F 169.2 °F 2.6 13.8 TITUS DESV
VAV-1-18 6 60 °F 93 °F 180 110 130 0.02 180.0 °F 149.1 °F 0.3 4.6 TITUS DESV
VAV-1-19 6 60 °F 91 °F 210 125 140 0.03 180.0 °F 148.3 °F 0.3 4.7 TITUS DESV
VAV-2-1A 6 60 °F 90 °F 425 420 420 0.2 180.0 °F 141.2 °F 0.7 13.7 TITUS DESV
VAV-2-1B 6 60 °F 90 °F 285 210 260 0.04 180.0 °F 161.6 °F 0.9 8.5 TITUS DESV
VAV-2-1C 8 60 °F 90 °F 550 550 550 0.19 180.0 °F 133.5 °F 0.8 17.9 TITUS DESV
VAV-2-1D 10 60 °F 90 °F 645 625 625 0.06 180.0 °F 171.1 °F 4.7 20.3 TITUS DESV
VAV-2-2 8 60 °F 90 °F 635 320 390 0.1 180.0 °F 164.6 °F 1.7 12.7 TITUS DESV
VAV-2-3 6 60 °F 90 °F 245 150 170 0.03 180.0 °F 149.7 °F 0.4 5.5 TITUS DESV
VAV-2-4 6 60 °F 90 °F 340 185 215 0.06 180.0 °F 154.3 °F 0.6 7.0 TITUS DESV
VAV-2-5 8 60 °F 90 °F 490 305 340 0.07 180.0 °F 157.9 °F 1.0 11.1 TITUS DESV
VAV-2-6 6 60 °F 90 °F 420 305 345 0.08 180.0 °F 174.5 °F 4.2 11.2 TITUS DESV
VAV-2-7 6 60 °F 90 °F 420 140 260 0.08 180.0 °F 161.6 °F 0.9 8.5 TITUS DESV
VAV-2-8 6 60 °F 90 °F 385 260 295 0.07 180.0 °F 167.1 °F 1.5 9.6 TITUS DESV
VAV-2-9 6 60 °F 90 °F 400 200 240 0.08 180.0 °F 158.4 °F 0.7 7.8 TITUS DESV
VAV-2-10 6 60 °F 90 °F 365 250 290 0.07 180.0 °F 166.3 °F 1.4 9.4 TITUS DESV
VAV-2-11 6 60 °F 90 °F 425 240 280 0.09 180.0 °F 164.8 °F 1.2 9.1 TITUS DESV
VAV-2-12 6 60 °F 90 °F 405 275 315 0.08 180.0 °F 170.1 °F 2.1 10.2 TITUS DESV
VAV-2-13 8 60 °F 90 °F 680 275 350 0.12 180.0 °F 159.3 °F 1.1 11.4 TITUS DESV
VAV-2-14 6 60 °F 90 °F 370 240 280 0.07 180.0 °F 164.8 °F 1.2 9.1 TITUS DESV
VAV-2-15 6 60 °F 90 °F 245 150 170 0.03 180.0 °F 149.7 °F 0.4 5.5 TITUS DESV
VAV-2-17 8 60 °F 90 °F 435 245 280 0.05 180.0 °F 149.5 °F 0.6 9.1 TITUS DESV
VAV-2-18 6 60 °F 90 °F 370 265 350 0.07 180.0 °F 175.2 °F 4.9 11.4 TITUS DESV
VAV-2-19 6 60 °F 90 °F 430 235 325 0.09 180.0 °F 171.6 °F 2.6 10.6 TITUS DESV
VAV-2-20 6 60 °F 90 °F 380 255 290 0.07 180.0 °F 166.3 °F 1.4 9.4 TITUS DESV
VAV-3-1A 6 60 °F 90 °F 395 390 365 0.18 180.0 °F 140.1 °F 0.6 11.9 TITUS DESV
VAV-3-1B 6 60 °F 90 °F 280 215 255 0.04 180.0 °F 160.8 °F 0.9 8.3 TITUS DESV
VAV-3-1C 8 60 °F 90 °F 550 545 545 0.19 180.0 °F 133.4 °F 0.8 17.7 TITUS DESV
VAV-3-1D 6 60 °F 90 °F 195 190 190 0.02 180.0 °F 151.6 °F 0.4 6.2 TITUS DESV
VAV-3-2 10 60 °F 90 °F 875 590 660 0.09 180.0 °F 173.7 °F 6.9 21.4 TITUS DESV
VAV-3-3 8 60 °F 90 °F 485 310 345 0.07 180.0 °F 158.6 °F 1.1 11.2 TITUS DESV
VAV-3-4 6 60 °F 90 °F 340 245 270 0.06 180.0 °F 163.2 °F 1.1 8.8 TITUS DESV
VAV-3-5 8 60 °F 90 °F 635 340 395 0.1 180.0 °F 165.3 °F 1.8 12.8 TITUS DESV
VAV-3-6 6 60 °F 90 °F 370 235 275 0.07 180.0 °F 164.0 °F 1.1 8.9 TITUS DESV
VAV-3-7 6 60 °F 90 °F 325 260 285 0.05 180.0 °F 165.6 °F 1.3 9.3 TITUS DESV
VAV-3-8 6 60 °F 90 °F 370 240 280 0.07 180.0 °F 164.8 °F 1.2 9.1 TITUS DESV
VAV-3-9 6 60 °F 90 °F 210 115 180 0.03 180.0 °F 150.6 °F 0.4 5.9 TITUS DESV
VAV-3-10 6 60 °F 90 °F 365 245 325 0.07 180.0 °F 171.6 °F 2.6 10.6 TITUS DESV
VAV-3-11 6 60 °F 90 °F 195 190 190 0.02 180.0 °F 140.6 °F 0.7 12.7 TITUS DESV
VAV-3-12 6 60 °F 90 °F 195 190 190 0.02 180.0 °F 146.1 °F 0.5 8.1 TITUS DESV
VAV-3-13 6 60 °F 90 °F 195 190 190 0.02 180.0 °F 166.6 °F 2.0 13.2 TITUS DESV
VAV-3-14 6 60 °F 90 °F 195 190 190 0.02 180.0 °F 153.7 °F 0.8 10.1 TITUS DESV
VAV-3-15 6 60 °F 90 °F 195 190 190 0.02 180.0 °F 165.3 °F 1.8 12.8 TITUS DESV
VAV-3-16 6 60 °F 90 °F 195 190 190 0.02 180.0 °F 152.3 °F 0.7 9.8 TITUS DESV
VAV-3-17 6 60 °F 90 °F 195 190 190 0.02 180.0 °F 170.5 °F 3.0 14.1 TITUS DESV
VAV-3-18 6 60 °F 90 °F 195 190 190 0.02 180.0 °F 159.3 °F 1.1 11.4 TITUS DESV
VAV-B-1A 10 60 °F 90 °F 1015 1015 1015 0.29 180.0 °F 137.0 °F 1.6 33.0 TITUS DESV
VAV-B-1B 4 60 °F 94 °F 125 110 125 0.01 180.0 °F 149.5 °F 0.3 4.5 TITUS DESV
VAV-B-2 8 60 °F 90 °F 685 495 570 0.28 180.0 °F 134.0 °F 0.8 18.5 TITUS DESV
VAV-B-3 6 60 °F 90 °F 310 275 305 0.05 180.0 °F 168.6 °F 1.8 9.9 TITUS DESV
VAV-B-4 6 60 °F 90 °F 265 250 265 0.04 180.0 °F 162.4 °F 1.0 8.6 TITUS DESV
VAV-B-5 6 60 °F 90 °F 365 205 240 0.07 180.0 °F 158.4 °F 0.7 7.8 TITUS DESV
VAV-B-6 6 60 °F 90 °F 420 370 420 0.2 180.0 °F 141.2 °F 0.7 13.7 TITUS DESV
AIR COOLED SCROLL CHILLER SCHEDULE
MARK LOCATION AREA AND/OR
BLDG SERVED TYPE
CAPACITY # OF
COMP kW/TON MIN COP IPLV (BTU/W*H)
EVAPORATOR CONDENSER ELECTRICAL
REMARKSFLOW EWT LWT MAX WPD FOULING
FACTOR
AMBIENT OA TEMP
COMPRESSOR MOTOR CONDENSER FAN MOTORS
# COMP kW PHASE VOLT # FANS kW PHASE VOLT
TONS GPM °F °F FT °F
18-ACCH-1 BLDG 18
EXTERIOR BLDG 18 SCROLL 65.88 6 8.8 0.7 17.16 157.3 54 44 10 0.0001 105 6 83.51 3 460 4 6.72 3 460 1, 2, 3, 4, 5
NOTES:
1. UNIT SHALL BE RATED FOR SEISMIC DESIGN CATEGORY C (SEE SEISMIC NOTE)
2. SEE SPECIFICATIONS FOR OTHER APPLICABLE ENGINEERING REQUIREMENTS.
3. "MAX kW/TON" AND "MIN COP" SPECIFIED ARE AT DESIGN CONDITIONS INDICATED. kW/TON INCLUDES CONDENSER FANS.
4. CHILLED WATER PUMP KIT SHALL BE INCLUDED BY THE CHILLER MANUFACTURER.
5. BASIS OF DESIGN: JCI YLAA0070SE, CARRIER 30RAP070, OR APPROVED EQUAL.
LOUVER SCHEDULE
MARK SYSTEM AND/OR SERVICE TYPE
WIDTH HEIGHT AIR FLOW FREE AREA FREE AREA VELOCITY APD MANUFACTURER AND
MODEL REMARKS
IN IN CFM SQ FT FPM W.G.
18-LVR-01 OUTSIDE AIR INTAKE STATIONARY 90 93 26000 32.24 806 0.07 RUSKIN L375D OR
APPROVED EQUAL
18-LVR-02 RELIEF AIR STATIONARY 90 73 26000 27.07 960 0.10 RUSKIN L375D OR
APPROVED EQUAL
AIR DEVICE SCHEDULE
MARK TYPE MOUNTING
PANEL/FRAME SIZE NECK SIZE
DAMPER FINISH MANUFACTURER AND
MODEL REMARKS
IN x IN IN
CD-1 SQUARE CONE DIFFUSER LAY-IN CEILING 24 x 24 8 NO WHITE PRICE SCD OR
APPROVED EQUAL 1,2,3
CD-2 SQUARE CONE DIFFUSER LAY-IN CEILING 24 x 24 10 NO WHITE PRICE SCD OR
APPROVED EQUAL 1,2,3
CD-3 LINEAR SLOT PLENUM DIFFUSER HARD CEILING 48", 3 SLOTS 8 NO WHITE PRICE SDB100 OR
APPROVED EQUAL 1,2,7
CD-4 LINEAR SLOT PLENUM DIFFUSER HARD CEILING 48", 3 SLOTS 10 NO WHITE PRICE SDB100 OR
APPROVED EQUAL 1,2,7
CD-5 LINEAR SLOT PLENUM DIFFUSER HARD CEILING 48", 3 SLOTS 12 NO WHITE PRICE SDB100 OR
APPROVED EQUAL 1,2,7
EG-1 PERFORATED EXHAUST GRILLE HARD CEILING 12 x 12 6 x 6 YES WHITE PRICE PDDE OR
APPROVED EQUAL 2,7
EG-2 PERFORATED EXHAUST GRILLE SIDE WALL 12 x 6 6 x 6 YES WHITE PRICE PDDE OR
APPROVED EQUAL 2,7
RG-1 PERFORATED RETURN GRILLE LAY-IN CEILING 24 x 24 8 x 6 NO WHITE PRICE PDDR OR
APPROVED EQUAL 2,3
RG-2 PERFORATED RETURN GRILLE LAY-IN CEILING 24 x 24 8 x 8 YES WHITE PRICE PDDR OR
APPROVED EQUAL 2,3
RG-3 RETURN GRILLE HARD CEILING 48 x 6 8 x 6 NO WHITE PRICE 500 APPROVED
EQUAL 5,7
RG-4 RETURN GRILLE HARD CEILING 48 x 6 8 x 8 NO WHITE PRICE 500 APPROVED
EQUAL 5,7
RG-5 RETURN GRILLE HARD CEILING 24 x 6 8 x 8 NO WHITE PRICE 500 APPROVED
EQUAL 5,7
SG-1 SUPPLY GRILLE SIDE WALL 36 x 6 10 NO WHITE PRICE 500 APPROVED
EQUAL 5,7
SG-2 SUPPLY GRILLE SIDE WALL 48 x 6 10 NO WHITE PRICE 500 APPROVED
EQUAL 5,7
SG-3 SUPPLY GRILLE SIDE WALL 30 x 6 10 NO WHITE PRICE 500 APPROVED
EQUAL 5,7
SG-4 SUPPLY GRILLE SIDE WALL 16 x 6 10 NO WHITE PRICE 500 APPROVED
EQUAL 5,7
SG-5 SUPPLY GRILLE SIDE WALL 22 x 6 10 NO WHITE PRICE 500 APPROVED
EQUAL 5,7
NOTES:
1. SEE PLANS FOR THROW DIRECTIONS. DIFFUSERS SHOWN WITH NO ARROWS ARE 4-WAY THROW.
2. WHERE DAMPERS ARE NOT SHOWN ON DRAWINGS, DAMPER SHALL BE FURNISHED WITH AIR DEVICE AND ACCESSIBLE FROM THE ROOM.
3. FRAME STYLE SHALL BE FOR REGULAR T-BAR CEILING GRID. REFER TO ARCHITECTURAL DRAWINGS FOR CEILING SYSTEM.
4. SLOT WIDTH SHALL BE 1 INCH.
5. BLADE DEFLECTION ANGLE SHALL BE 0 DEGREES. BLADE SPACING SHALL BE 3/4".
6. BLADE DEFLECTION ANGLE SHALL BE 45 DEGREES. BLADE SPACING SHALL BE 3/4".
7. MINIMUM SIZE GIVEN. CONTRACTOR MAY UPSIZE TO MATCH EXISTING DRYWALL PENETRATIONS.
SPLIT SYSTEM AIR CONDITIONER SCHEDULE
MARK LOCATION AREA AND/OR
BLDG SERVED TYPE
MAX INDOOR
AIR FLOW
COOLING CAPACITY
REMARKSMIN TOTAL
CAPACITY
MIN SENS
CAPACITY MIN
SEER
EAT OSA
DESIGN
TEMP CONTROL MANUFACTURER AND
MODEL MCA PHASE VOLTDb Wb
CFM MBH MBH °F °F °F
18-ACU-01 EXTERIOR
WALL MOUNT
18-ACU-01A
18-ACU-01B
18-ACU-01C
PACKAGED NA 24 24 16 NA NA 96 CONTROLLER JCI DHM24CMB21S
APPROVED EQUAL 10 1 208 1, 2, 3
18-ACU-01A 1ST FLOOR OIT CLOSET
119 PACKAGED 450 8.5 8.5 16 80 67 NA THERMOSTAT JCI DHY09NWB21S OR
APPROVED EQUAL 0.07 1 115 3
18-ACU-01B 2ND FLOOR OIT CLOSET
213 PACKAGED 450 8.5 8.5 16 80 67 NA THERMOSTAT JCI DHY09NWB21S OR
APPROVED EQUAL 0.07 1 115 3
18-ACU-01C 3RD FLOOR OIT CLOSET
312 PACKAGED 450 8.5 8.5 16 80 67 NA THERMOSTAT JCI DHY09NWB21S OR
APPROVED EQUAL 0.07 1 115 3
NOTES:
1. UNIT SHALL BE RATED FOR SEISMIC DESIGN CATEGORY C (SEE SEISMIC NOTE).
2. UNIT SHALL INCLUDE FIELD SETTINGS AND LOW AMBIENT KIT FOR OPERATION DOWN TO 0F AMBIENT TEMPERATURE.
3. EQUIPMENT SHALL BE COMPATATIBLE AND CONTROLLED BY MANUFACTURER'S CONTROLLER.
HOT WATER UNIT HEATER SCHEDULE
MARK LOCATION AREA AND/OR
BLDG SERVED
BASIS OF DESIGN
(OR APPROVED
EQUAL)
TYPE UNIT
AIR FLOW MIN
CAPACITY
TEMPERATURES
FLOW WPD CONTROL
SEQUENCE
MOTOR
REMARKSEAT EWT POWER
PHASE VOLT RPM
CFM BTUH °F °F GPM FT HP
18-UH-1 003 MECHANICAL
ROOM VULCAN VV-40 HORIZONTAL 595 22.7 60 180 2.34 0.06 00-MG-701 0.03 1 120 1550 -----
TEMPORARY AIR HANDLING UNIT SCHEDULE
MARK
MAX.
LENGTH
(IN.)
MAX.
HEIGHT
(IN.)
MAX.
WIDTH
(IN.)
MIN./MAX.
AIRFLOW (CFM)
AIR FLOW DATA REFRIGERANT CIRCUITS ELECTRIC HEATER REMARKS
AIRFLOW
(CFM)
SUPPLY AIR
CONNECTION
QTY/SIZE
RETURN AIR
CONNECTION
QTY/SIZE
E.S.P.
(IN. W.G.) DRIVE FAN
QTY
MOTOR
HP (EACH) PH Hz V
MOTOR
FLA
(EACH)
NOMINAL
TONS REFRIGERANT REFRIGERANT
CHARGE
AMBIENT
OPERATING
CONDITIONS
# OF
REFRIGERANT
CIRCUITS
# OF
COMPRESSORS PER
CIRCUIT
STAGES WATTAGE (kW) MCA
CLEAN/DIRTY
A.P.D.
(IN. W.G.) 1, 2, 3, 4, 5, 6
18-TEMP-1 156 100 88 4,200 - 17,000 13,650 (3) 20" (4) 20" 4.6 DIRECT 1 30 3 60 460 282.7 80 R410A 60 LBS 0°F - 105°F 2 1 3 162 329 0.25/.5
NOTES:
1. ALL PREFILTERS ARE MERV-8 THROWAWAY TYPE (16" X 25" X 2").
2. AIR HANDLER FAN CONFIGURATION SHALL BE DRAW-THRU.
3. AIR HANDLER SHALL BE SEISMICALLY CERTIFIED FROM THE FACTORY.
4. PERFORMANCE AT 510 FT. ELEVATION.
5. DESIGN OUTDOOR CONDITIONS: SUMMER: 96 °F DB AT 77 °F WB; WINTER: 6 °F DB
6. BASIS OF DESIGN: TRANE RSHX0080 OR APPROVED EQUAL.
AIR HANDLING UNIT SCHEDULE
MARK
MIN OA
(CFM)
MAX.
LENGTH
(IN.)
MAX.
HEIGHT
(IN.)
MAX.
WIDTH
(IN.)
SUPPLY FAN CHILLED WATER COOLING COIL PREFILTER #1 REMARKS
AIRFLOW
(CFM)
T.S.P.
(IN. W.G.)
E.S.P.
(IN. W.G.)
WHEEL
(TYPE) DRIVE VFD FAN
RPM
FAN
QTY
MOTOR
HP (EACH) PH Hz V
MOTOR
FLA
(EACH)
MAX. F.V.
(FT/MIN)
MAX. A.P.D.
(IN.W.G.) EAT-DB (°F) EAT-WB
(°F)
LAT-DB
(°F)
LAT-WB
(°F)
PROPYLENE
GLYCOL
CONTENT
SMBH TMBH
FLOW RATE
(GPM) MERV THICKNESS (IN)
FINAL
A.P.D.
(IN. W.G.)
CLEAN/DIRTY
A.P.D.
(IN. W.G.)
1, 2, 3, 4, 5, 6, 7 18-AHU-SF 6000 278 108 90 26,000 6.1 3 SWSI DIRECT Y 2,361 4 15 3 60 460 17.3 500 1 80 67 55 54 30% 523 755 147 7 2" 0.25 0.25/.5
MARK
MAX.
LENGTH
(IN.)
MAX.
HEIGHT
(IN.)
MAX.
WIDTH
(IN.)
RETURN FAN HEATING COIL PREFILTER #2
AIRFLOW
(CFM)
T.S.P.
(IN. W.G.)
E.S.P.
(IN. W.G.)
WHEEL
(TYPE) DRIVE VFD FAN
RPM
FAN
QTY
MOTOR
HP (EACH) PH Hz V
MOTOR
FLA
(EACH)
HEATING
AIRFLOW
(CFM)
MAX. F.V.
(FT/MIN)
A.P.D.
(IN.W.G.)
EAT-DB
(°F)
LAT-DB
(°F) MBH
PROPYLENE
GLYCOL
CONTENT
EWT
(°F)
LWT
(°F)
FLOW RATE
(GPM) MERV THICKNESS (IN)
FINAL
A.P.D.
(IN. W.G.)
CLEAN/DIRTY
A.P.D.
(IN. W.G.)
18-AHU-RF 144 108 84 26,000 4.47 3 SWSI DIRECT Y 2,604 4 10 3 60 460 11.6 20968 408 0.03 50 81.3 723 30% 180 160 49.5 11 12" 0.34 0.5/1
NOTES:
1. PREFILTER 1 AND PREFILTER 2 SHALL BE LOCATED BACK-TO-BACK.
2. AIR HANDLER FAN CONFIGURATION SHALL BE DRAW-THRU.
3. AIR HANDLER SHALL BE SEISMICALLY CERTIFIED FROM THE FACTORY.
4. DESIGN OUTDOOR CONDITIONS: SUMMER: 96 °F DB AT 77 °F WB; WINTER: 6 °F DB
5. BASIS OF DESIGN: JCI XTI-102x90, CARRIER AERO 39MN SIZE 50W, OR APPROVED EQUAL.
6. INCLUDE 105 LB/HR STEAM DISTRIBUTION MANIFOLD.
7. PERFORMANCE AT 510 FT. ELEVATION.
MAKE-UP AIR HEATING AND VENTILATING UNIT SCHEDULE
MARK LOCATION AREA AND/OR
BLDG SERVED TYPE
MAX CAPACITY MIN AIR
FLOW SUPPLY FAN
CFM
EXHAUST FAN
CFM
PREFILTER
MARK
AFTER
FILTER
MARK
TEMPERATURES
REMARKSEAT LAT
MBH CFM °F °F
60-MAU-1 BLDG 60 ROOF KITCHEN PREHEAT 435 2700 4825 5400 MERV 8 MERV 11 6 75 1,2,3
60-MAU-2 BLDG 60 ROOF KITCHEN PREHEAT 435 2700 4825 5400 MERV 8 MERV 11 6 75 1,2,3
NOTES:
1. UNIT SHALL INCLUDE FREEZE PROOF STEAM COILS & SNOW HOOD.
2. UNIT SHALL INCLUDE MANUFACTURER PROVIDED CONTROLS FOR MAKE-UP AIR UNITS AND KITCHEN HOOD.
3. UNIT SHALL BE RATED FOR SEISMIC DESIGN CATEGORY C (SEE SEISMIC NOTE).
FAN SCHEDULE
MARK LOCATION AREA AND/OR
BLDG SERVED SYSTEM AND/OR SERVICE
AIR FLOW TSP
FAN MOTOR ELECTRICAL
CONTROL
SEQUENCE REMARKS
TYPE WHEEL CLASS ARRANGEMENT, ROTATION,
AND DISCHARGE
DIAMETER
MIN % EFF DRIVE FAN MAX
RPM
NOMINAL POWER
PHASE VOLT RPM SPEED CONTROL
CFM IN IN BHP HP
18-EF-1 TOILET, FEMALE 005 18 TOILET EXHAUST 400 0.5 INLINE SWSI I N/A 9 63% DIRECT 1500 - 0.2 1 115 1100 FSC-CONSTANT 00-MG-702 2
18-EF-2 ELEVATOR MACHINE
ROOM 001 18 ELEVATOR MACHINE ROOM
EXHAUST 610 EXISTING INLINE SWSI I N/A 18 - DIRECT 1550 - 0.05 1 208 1550 CONSTANT 00-MG-702 1
18-EF-3 MECH. ROOM 002 18 MECHANICAL ROOM EXHAUST EXISTING EXISTING INLINE SWSI I N/A 24 - DIRECT - - - 1 208 - CONSTANT 00-MG-702 1
18-EF-4 ATTIC 18 TOILET EXHAUST 2100 0.8 INLINE SWSI I N/A 24 - BELT 1900 - 1 1 208 1725 CONSTANT 00-MG-702 1
NOTES:
1. EXISTING UTILITY EXHAUST FAN INFORMATION IS FOR REFERENCE ONLY.
2. BASIS OF DESIGN COOK GN-622 GEMINI INLINE FAN OR APPROVED EQUAL.
t h r e e i n c h e s o n e f o o t o n e a n d o n e h a l f i n c h e s o n e f o o t o n e i n c h o n e f o o t t h r e e q u a r t e r s i n c h o n e f o o t o n e h a l f i n c h o n e f o o t t h r e e e i g h t h s i n c h o n e f o o t o n e q u a r t e r i n c h o n e f o o t o n e e i g h t h i n c h o n e f o o t
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
Veterans
Health
Administration
VA FORM 08-6231
Drawing Title Project Title
Location
Date Checked Drawn
Project Number
Building Number
Drawing Number
CONSULTANTS:
657-19-103JB
VA Health Care System Approval:
Revision: Date:
ARCHITECT/ENGINEER:
750 W HAMPDEN AVE
SUITE 300
ENGLEWOOD, CO 80110
(720) 550-6307
WWW.VALHALLAENGINEERING.COM
VEG 19.7
100% CONTRACT DOCUMENT SUBMITTAL DRAWINGS
JEFFERSON BARRACKS
1 JEFFERSON BARRACKS DRIVE - ST. LOUIS, MO 63125
02/10/2020
A
M
00-MG-602
MECHANICAL EQUIPMENT SCHEDULES
18 & 60
FCA - REPLACE MECHANICAL
SYSTEMS IN BUILDING 18 & 60
DD MDR
Drawing # 23 of 77
SMOKE DAMPER (N.C.)
SEE SCHEDULE
NOTE:
UPON DETECTION OF SMOKE BY THE SMOKE DETECTOR, THE SMOKE DAMPER SHALL CLOSE & SEND AN
ALARM TO THE ECC.
DUCT TRANSITION
AS REQUIRED
2 POSITION
BINARY POINT
TO FIRE
ALARM CONTROL
PANEL (FACP)
120V
ELECTRICAL
POWER
AIRFLOW
AIR
DUCT
SMOKE PARTITION
PRESSURE SWITCH HIGH (PSH)
TO SHUT DOWN FAN UPON
REACHING HIGH PRESSURE
SETPOINT
DAMPER POSITION
FEEDBACK TO
ECC
PSH
MZS
SD
AD
ROOM TEMPERATURE (°F)
VA
V
AI
R
F
LO
W
REHEAT FLO
W
TEMPERATURE SET POINTS SHALL BE SET AS FOLLOWS:
OCCUPIED COOLING 75°F(ADJ) UNOCCUPIED COOLING 80°F(ADJ)
OCCUPIED HEATING 70°F(ADJ) UNOCCUPIED HEATING 60°F(ADJ)
DEAD BAND OF 5° F BETWEEN HEATING AND COOLING SET POINTS WILL BE MAINTAINED.
UPON FALL IN SPACE TEMPERATURE, THE VAV DAMPER WILL MODULATE TO MINIMUM
POSITION. VAV SHALL BE PRESSURE INDEPENDENT.
UPON FURTHER DROP IN SPACE TEMPERATURE, VALVE V-1 WILL MODULATE TO
MAINTAIN SET POINT + .5° F. THE ADJUSTABLE TOLERANCE OF + .5° F HAS BEEN
SELECTED TO PREVENT VALVE HUNTING.
THE REVERSE SHALL OCCUR ON THE RISE IN SPACE TEMPERATURE.
V-1 SHALL BE A THREE-WAY VALVE AT THE VAV WITH THE LONGEST HOT WATER PIPE
RUN (18-VAV-3-18).
SP
VAV BOX CONTROL SEQUENCE
A
IR
F
LO
W (C
F M
HEATING
MINIMUM
100%
TU
RHC
HWS
HWR
V-1
TE
PC
TE
FE
ROOM THERMOSTAT/SENSOR
WALL MOUNTED 48" AFF.
ATU CONTROLLER
AIR FLOW
AIR TERMINAL UNIT
REHEAT COIL
WITHOUT SUPPLEMENTAL HEATING
CONTROL VALVES (N.C.). SIZE VALVES
IN 1/3 - 2/3 VALVE ARRANGEMENT
HEAT EXCHANGERS
TEMPERATURE
SENSOR (TYP)
PUMP
LPS
PUMP
HWS
V-1
V-2
LPS
V-3
V-4
AMBIENT TEMPERATURE TRANSMITTER WITH SUN
SHIELD
CONTROL VALVES
(N.C.). SIZE VALVES
IN 1/3 - 2/3 VALVE
ARRANGEMENT
O.A.
140°F (MIN.) 180°F (MAX.)
SEQUENCE OF OPERATION:
1. STEAM CONTROL VALVE SHALL MODULATE TO MAINTAIN THE LEAVING HOT WATER TEMPERATURE AT SET
POINT.
2. THE LEAVING HOT WATER TEMPERATURE SHALL BE RESET INVERSELY WITH THE OUTDOOR TEMPERATURE
AS SCHEDULED.
3. THE LEAD AND STANDBY PUMPS AND HEAT EXCHANGERS SHALL BE SEQUENTIAL BY THE OPERATOR
CONTROLS AT THE PRE-DETERMINED INTERVAL (USUALLY 7 DAYS). IN THE EVENT THE PUMP FAILS TO START
WITHIN 30 SECONDS, AN ALARM SHALL BE INITIATED AND THE SECOND PUMP SHALL START AUTOMATICALLY.
HWR
HX-1
HX-2
TYP OSA RESET SCHEDULE
VALVE SEQUENCE:
1. V1 (1/3 CAPACITY) MODULATE FULLY OPEN TO MAINTAIN SET POINT
2 .V2 (2/3 CAPACITY) MODULATE FULLY OPEN TO MAINTAIN SET POINT.
3. BOTH V1 & V2 MODULATE TOGETHER TO MAINTAIN SET POINT.
SST
HS
CS
HWP-2
SST
TT
CS
HS
HWP-1
TT
V1-C
V2-C
TT
TC PC
V3-C
V4-C x
OA
BAST
PRE-FILTERS
STEAM HEATING
COIL
SA
BAST
BAS0
PDS
BAST
FREEZE STAT
M
NC
BAS
LPR
LPS
NO
V F
D
BAS
SUPPLY FAN(S)
BAS
OUTSIDE
AIR TEMP
EA
V F
D
BAS
EXHUAST FAN
BAS
SEQUENCE OF OPERATIONS:
SUPPLY FAN: THE SUPPLY FAN SHALL HAVE A HAND-OFF-AUTO SWITCH IN THE VARIABLE FREQUENCY DRIVE. WHEN IN THE “HAND” POSITION THE FAN SHALL OPERATE. WHEN IN THE “OFF”
POSITION THE FAN SHALL NOT OPERATE. WHEN IN THE "AUTO" POSITION, THE FAN SHALL BE CONTROLLED BY THE BAS AND VFD. AN AUXILIARY CONTACT ON THE VFD SHALL SEND A SIGNAL
TO THE BAS FOR FAN STATUS. PROGRAM BAS TO SIGNAL AN ALARM CONDITION IF THE FAN FAILS TO PROVE STATUS. PROVIDE HARDWIRED INTERLOCKS TO SHUTDOWN FAN IF THE MOTOR
OVERLOADS, SMOKE DETECTOR CONTACTS OPEN, OR FREEZE STAT CONTACTS OPEN. PROGRAM BAS TO OPERATE THE SUPPLY FAN CONTINUOUSLY IN OCCUPIED MODE.
EXHAUST FAN: THE EXHAUST FAN SHALL HAVE A HAND-OFF-AUTO SWITCH IN THE VARIABLE FREQUENCY DRIVE. WHEN IN THE “HAND” POSITION THE FAN SHALL OPERATE. WHEN IN THE “OFF”
POSITION THE FAN SHALL NOT OPERATE. WHEN IN THE "AUTO" POSITION, THE FAN SHALL BE CONTROLLED BY THE BAS AND VFD. AN AUXILIARY CONTACT ON THE VFD SHALL SEND A SIGNAL
TO THE BAS FOR FAN STATUS. PROGRAM BAS TO SIGNAL AN ALARM CONDITION IF THE FAN FAILS TO PROVE STATUS. PROVIDE HARDWIRED INTERLOCKS TO SHUTDOWN FAN IF THE MOTOR
OVERLOADS. PROGRAM BAS TO OPERATE THE EXHAUST FAN CONTINUOUSLY IN OCCUPIED MODE.
STEAM HEATING COIL : MODULATE STEAM CONTROL VALVE THROUGH THE BAS TO MAINTAIN SA TEMPERATURE.
THE ALARMS SHALL BE PROVIDED AS FOLLOWS:
• LOW SUPPLY AIR TEMPERATURE.
• FREEZE STAT ALARM.
• FILTER DIFFERENTIAL PRESSURE ALARM.
th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t o n e e ig h th in c h o n e fo o t
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
Veterans Health
Administration
VA FORM 08-6231
Drawing Title Project Title
Location
Date Checked Drawn
Project Number
Building Number
Drawing Number
CONSULTANTS: 657-19-103JB
VA Health Care System Approval:
Revision: Date:
ARCHITECT/ENGINEER:
750 W HAMPDEN AVE
SUITE 300
ENGLEWOOD, CO 80110
(720) 550-6307
WWW.VALHALLAENGINEERING.COM VEG 19.7
100% CONTRACT DOCUMENT SUBMITTAL DRAWINGS
JEFFERSON BARRACKS
1 JEFFERSON BARRACKS DRIVE - ST. LOUIS, MO 63125
02/10/2020
/1
/2
:1 :0
A
M
00-MG-701
MECHANICAL CONTROLS
18 & 60
FCA - REPLACE MECHANICAL
SYSTEMS IN BUILDING 18 & 60
DD ANT Drawing # 24 of 77
NTS
SMOKE DAMPER CONTROL DIAGRAM
NTS
VARIABLE AIR VOLUME TERMINAL UNIT CONTROLS DIAGRAM
NTS
DUAL HEAT EXCHANGER CONTROLS (HEATING SYSTEM)
NTS
60-MAU-01 AND 60-MAU-02 MAKE UP AIR HANDLING UNIT CONTROLS DIAGRAM AND
SEQUENCE OF OPERATIONS
I/O POINTS LIST BUILDINGS 18 AND 60
QUANTITY GRAPHICS REQUIRED DO AO DI AI READ WRITE TREND BACnet OBJECT
STEAM TO HEATING WATER HEAT EXCHANGER 18-HX-1 AND 18-HX-2
STEAM CONTROL VALVE 2 X X X HARDWIRED
WATER SUPPLY TEMPERATURE 1 X X X HARDWIRED
WATER FLOW DIFFERENTIAL PRESSURE SWITCH 1 X X X HARDWIRED
BTU ENERGY METER 1 X X X HARDWIRED
HEATING WATER PUMPS 18-HWP-1 AND 18-HWP-2
PUMP STATUS 2 X X X HARDWIRED
PUMP START/STOP 2 X X HARDWIRED
PUMP SPEED CONTROL 2 X X X HARDWIRED
SUPPLY WATER TERMPERATURE 1 X X X HARDWIRED
RETURN WATER TERMPERATURE 1 X X X HARDWIRED
WATER DIFFERENTIAL PRESSURE 2 X X X HARDWIRED
WATER FLOW 1 X X X HARDWIRED
DOMESTIC WATER CIRCULATION PUMP (E) 18-DHWP-1
PUMP STATUS 1 X X X HARDWIRED
WATER FLOW 1 X X X HARDWIRED
DOMESTIC WATER HEATER 18-DWH-1
SUPPLY WATER TERMPERATURE 1 X X X HARDWIRED
SUPPLY WATER TEMPERATURE ALARM 1 X X BV
RETURN WATER TERMPERATURE 1 X X X HARDWIRED
DOMETIC WATER METER 2 X X X HARDWIRED
MAKE UP AIR UNITS 60-MAU-1 AND 60-MAU-2
SUPPLY FAN START/STOP 2 X X HARDWIRED
SUPPLY FAN SPEED CONTROL 2 X X X HARDWIRED
SUPPLY FAN STATUS 2 X X X HARDWIRED
SUPPLY FAN VFD OUTPUT FREQUENCY 2 X X X AV
SUPPLY FAN VFD OUTPUT CURRENT 2 X X AV
SUPPLY FAN VFD OUTPUT VOLTAGE 2 X X AV
SUPPLY FAN VFD ALARM 2 X X BV
SUPPLY AIR STATIC PRESSURE 2 X X X HARDWIRED
SUPPLY AIR PRESSURE HIGH LIMIT 2 X X HARDWIRED
SUPPLY AIRFLOW 2 X X X HARDWIRED
SUPPLY AIR TEMPERATURE 2 X X X HARDWIRED
FILTER AIR PRESSURE HIGH LIMIT 2 X X HARDWIRED
STEAM VALVE CONTROL 2 X X X HARDWIRED
SMOKE DETECTOR ALARM 2 X X HARDWIRED
EXHAUST FAN START/STOP 2 X X HARDWIRED
EXHAUST FAN SPEED CONTROL 2 X X X HARDWIRED
EXHAUST FAN VFD OUTPUT FREQUENCY 2 X X X AV
EXHAUST FAN VFD OUTPUT CURRENT 2 X X AV
EXHAUST FAN VFD OUTPUT VOLTAGE 2 X X AV
EXHAUST FAN VFD ALARM 2 X X BV
EXHAUST FAN STATUS 2 X X X HARDWIRED
OUTSIDE AIR TEMPERATURE 2 X X X HARDWIRED
I/O POINTS LIST BUILDING 18
QUANTITY GRAPHICS REQUIRED DO AO DI AI READ WRITE TREND BACnet OBJECT
AIR HANDLING UNIT 18-AHU-1
SUPPLY FAN ARRAY START/STOP 1 X X HARDWIRED
SUPPLY FAN ARRAYSPEED CONTROL 1 X X X HARDWIRED
SUPPLY FAN ARRAY STATUS 1 X X X HARDWIRED
SUPPLY FAN ARRAY VFD OUTPUT FREQUENCY 1 X X X AV
SUPPLY FAN ARRAY VFD OUTPUT CURRENT 1 X X AV
SUPPLY FAN ARRAY VFD OUTPUT VOLTAGE 1 X X AV
SUPPLY FAN ARRAY VFD ALARM 1 X X BV
SUPPLY AIR STATIC PRESSURE 2 X X X HARDWIRED
SUPPLY AIR PRESSURE HIGH LIMIT 1 X X HARDWIRED
SUPPLY AIRFLOW 1 X X X HARDWIRED
SUPPLY AIR TEMPERATURE 1 X X X HARDWIRED
FILTER AIR PRESSURE HIGH LIMIT 2 X X HARDWIRED
HEATING WATER COIL VALVE CONTROL 1 X X X HARDWIRED
CHILLED WATER COIL VALVE CONTROL 1 X X X HARDWIRED
CHILLED WATER BTU METER 1 X X X HARDWIRED
SMOKE DETECTOR ALARM 1 X X HARDWIRED
FREEZESTAT 1 X X HARDWIRED
MIXED AIR TEMPERATURE 1 X X X HARDWIRED
MIXED & EXHAUST AIR DAMPER CONTROL 1 X X HARDWIRED
RETURN FAN ARRAY START/STOP 1 X X HARDWIRED
RETURN FAN ARRAY SPEED CONTROL 1 X X X HARDWIRED
RETURN FAN ARRAY VFD OUTPUT FREQUENCY 1 X X X AV
RETURN FAN ARRAY VFD OUTPUT CURRENT 1 X X AV
RETURN FAN ARRAY VFD OUTPUT VOLTAGE 1 X X AV
RETURN FAN ARRAY VFD ALARM 1 X X BV
RETURN FAN ARRAY STATUS 1 X X X HARDWIRED
RETURN AIRFLOW 1 X X X HARDWIRED
RETURN AIR TEMPERATURE 1 X X X HARDWIRED
OUTSIDE AIRFLOW 1 X X X HARDWIRED
OUTSIDE AIR TEMPERATURE 1 X X X HARDWIRED
OUTSIDE AIR HUMIDITY 1 X X X HARDWIRED
RETURN AIR HUMIDITY 1 X X X HARDWIRED
SUPPLY AIR HUMIDITY HIGH LIMIT 1 X X HARDWIRED
HUMIDIFIER CONTROL VALVE 1 X X HARDWIRED
SMOKE DETECTOR ALARM 1 X X HARDWIRED
CHILLER UNIT 18-ACCH-1
SCROLL COMPRESSOR ENABLE 3 X X HARDWIRED
DIGITAL COMPRESSOR CONTROL 1 X X HARDWIRED
CIRCUIT FAIL ALARM 2 X X HARDWIRED
AIRFLOW PROVING 2 X X HARDWIRED
VAV BOX
VAV BOX DAMPER POSITION 73 X X X HARDWIRED
VAV BOX INLET PRESSURE TRANSDUCER (FLOW) 73 X X X HARDWIRED
VAV BOX HEATING WATER CONTROL VALVE 73 X X X HARDWIRED
VAV BOX TEMPERATURE SET POINT 73 X X X HARDWIRED
VAV BOX SUPPLY AIR TEMPERATURE SENSOR 73 X X X HARDWIRED
SPACE TEMPERATURE SENSOR 73 X X X HARDWIRED
EXHAUST FAN 18-EF-01 AND 18-EF-04 (E)
EXHAUST FAN START/STOP 2 X X HARDWIRED
EXHAUST FAN SPEED CONTROL 2 X X X HARDWIRED
EXHAUST FAN STATUS 2 X X X HARDWIRED
SPLIT AIR CONDITIONER 18-ACU-1, 18-ACU-1A, 18-ACU-1B, 18-ACU-1C
ON/OFF COMMAND 4 X X HARDWIRED
STATUS 4 X X X HARDWIRED
ALARM 4 X X HARDWIRED
SUPPLY FAN ARRAY START/STOP CONTROL: THE SUPPLY FAN(S) SHALL HAVE A HAND-OFF-AUTO SWITCH IN THE VARIABLE FREQUENCY DRIVE. WHEN IN THE “HAND” POSITION THE FAN(S) SHALL OPERATE. WHEN IN THE “OFF” POSITION THE FAN(S) SHALL NOT OPERATE. WHEN IN THE "AUTO" POSITION, THE FAN(S) SHALL BE CONTROLLED BY THE BAS AND VFD.
SUPPLY FAN PRESSURE TRANSMITTER SHALL MODULATE THE FAN(S) AND VARIABLE FREQUENCY DRIVE TO MAINTAIN PROPER DUCT STATIC SET POINT. AN AUXILIARY CONTACT ON THE VFD SHALL SEND A SIGNAL TO THE BAS FOR FAN STATUS. PROGRAM BAS TO SIGNAL AN ALARM CONDITION IF THE FAN FAILS TO PROVE STATUS. PROVIDE HARDWIRED INTERLOCKS TO SHUTDOWN FAN(S) IF THE MOTOR OVERLOADS, SUPPLY AIR PRESSURE HIGH LIMIT IS REACHED, SMOKE DETECTOR CONTACTS OPEN, OR FREEZE STAT CONTACTS
OPEN. PROGRAM BAS TO OPERATE THE SUPPLY FAN(S) CONTINUOUSLY IN OCCUPIED MODE.
SUPPLY AIR PRESSURE HIGH LIMIT: WHEN THE SUPPLY SIDE OF THE AIR HANDLER REACHES SET DUCT STATIC PRESSURE (ADJ.), MANUAL RESET HIGH PRESSURE SWITCH SHALL
SHUT DOWN THE AIR HANDLER.
HEATING WATER COIL CONTROL: THE HEATING WATER COIL SHALL MODULATE TO MAINTAIN SUPPLY AIR SETPOINT TEMPERATURE.
CHILLED WATER COIL AND CHILLER CONTROL: THE CHILLED WATER COIL SHALL MODULATE TO MAINTAIN SUPPLY AIR SETPOINT TEMPERATURE. THE DDC SYSTEM SHALL START/STOP THE AIR COOLED CHILLER. AIR COOLED CHILLER SHALL BE PROVIDED WITH MANUFACTURER'S INTERNAL CONTROLS. THE CHILLER SHALL CONTROL THE CHILLED WATER PUMP. DDC SYSTEM SHALL MONITOR CHILLER STATUS, CHILLED WATER FLOW SWITCH AND CHILLED WATER SUPPLY TEMPERATURE.
SUPPLY AIR TEMPERATURE RESET SCHEDULE: THE BAS SHALL RESET THE SUPPLY AIR TEMPERATURE BASED ON THE VAV BOX REQUIRING THE MOST AIRFLOW (CRITICAL VAV). THE SUPPLY AIR RESET TEMPERATURE SHALL BE BETWEEN 55°F AND 65°F AS THE CRITICAL VAV DAMPER MODULATES FROM 95% TO 65%, WITH A STRAIGHT LINE RELATIONSHIP
BETWEEN. DISCHARGE TEMPERATURE SHALL BE RESETTABLE IN THE SOFTWARE.
RETURN FAN ARRAY START/STOP CONTROL: THE RETURN FAN(S) SHALL HAVE A HAND-OFF-AUTO SWITCH IN THE VARIABLE FREQUENCY DRIVE. WHEN IN THE “HAND” POSITION THE FAN(S) SHALL OPERATE. WHEN IN THE “OFF” POSITION, THE FAN(S) SHALL NOT OPERATE. WHEN IN THE "AUTO" POSITION, THE FAN(S) SHALL BE CONTROLLED BY THE BAS AND VFD.
AN AUXILIARY CONTACT ON THE VFD SHALL SEND A SIGNAL TO THE BAS FOR FAN STATUS. PROGRAM BAS TO SIGNAL AN ALARM CONDITION IF THE FAN FAILS TO PROVE STATUS.
PROVIDE HARDWIRE INTERLOCKS TO SHUTDOWN FAN(S) IF THE MOTOR OVERLOADS, SMOKE DETECTOR, OR FREEZE STAT CONTACTS OPEN. PROGRAM BAS TO START RETURN
FAN(S) AFTER PROOF OF SUPPLY FAN STATUS.
RETURN FAN ARRAY SPEED CONTROL: RETURN FAN(S) SHALL BE MODULATED TO MAINTAIN A FIXED CFM DIFFERENTIAL BETWEEN SUPPLY AIRFLOW AND RETURN AIRFLOW. TEST
AND BALANCE CONTRACTOR SHALL DETERMINE FIXED DIFFERENTIAL CFM.
MINIMUM OUTSIDE AIR: THE OUTSIDE AIR DAMPER SHALL MODULATE TO MAINTAIN THE SCHEDULED MINIMUM OUTSIDE AIR FLOW SETPOINT WITH A MIXED AIR TEMPERATURE OF 55°F (ADJ.). SIGNAL AN ALARM CONDITION IF MIXED AIR TEMPERATURE IS LESS THAN 40°F. RAD, EAD, AND OAD POSITIONS SHALL ALWAYS SUM TO 100 AND THE BUILDING SHALL REMAIN
POSITIVELY PRESSURIZED.
HUMIDITY CONTROL: HUMIDITY SHALL BE MONITORED BY THE RETURN AIR HUMIDITY SENSOR. MODULATE HUMIDIFIER CONTROL VALVE TO MAINTAIN MINIMUM HUMIDITY REQUIREMENTS. SUPPLY AIR HIGH HUMIDITY LIMIT SHALL KEEP SUPPLY AIR HUMIDITY BELOW 80%RH.
ECONOMIZER CONTROL: OUTSIDE AIR AND RETURN AIR SECTIONS OF THE AIR HANDLING UNITS SHALL HAVE ENTHALPY SENSORS, VAISALA HMX8XH OR VA COR APPROVED
EQUIVALENT.
• WHEN OUTSIDE AIR ENTHALPY IS ABOVE RETURN AIR ENTHALPY, ECONOMIZER IS DISABLED AND MIXING DAMPERS ARE AT MINIMUM POSITION.
• WHEN OUTSIDE AIR ENTHALPY IS BELOW RETURN AIR ENTHALPY, ECONOMIZER IS ENABLED AND OUTSIDE AIR TEMPERATURE IS 55°F OR ABOVE, MIXING DAMPERS ARE 100%
OPEN TO OUTSIDE AIR.
• WHEN OUTSIDE AIR ENTHALPY IS BELOW RETURN AIR ENTHALPY AND OUTSIDE AIR TEMPERATURE IS BELOW 55°F, ECONOMIZER IS ENABLED AND MIXING DAMPERS MODULATE
TO MAINTAIN MIXED AIR TEMPERATURE AT SETPOINT. MIXED AIR TEMPERATURE SETPOINT IS EQUAL TO SUPPLY AIR TEMPERATURE SETPOINT MINUS 2°F TO COMPENSATE FOR
FAN HEAT.
THE ECONOMIZER SHALL CLOSE WHENEVER ONE (1) OF THE FOLLOWING CONDITIONS ARE MET:
• SUPPLY FAN(S) OR RETURN FAN(S) IS OFF.
• MIXED AIR TEMPERATURE IS LESS THAN 40°F.
• OA DEW POINT IS BELOW 35°F (ADJ).
• LOSS OF FAN STATUS.
• SUPPLY AIR TEMPERATURE SENSOR HAS FAILED.
UNOCCUPIED MODE: THE AHU SET TO UNOCCUPIED MODE ON A USER DEFINABLE SCHEDULE VIA THE BAS WITH MANUAL OVERRIDE, AS REQUIRED, FROM THE VA ACCESSIBLE FRONT END. THE BAS SHALL ENABLE THE ASSOCIATED VAV BOXES TO OPERATE IN THEIR UNOCCUPIED MODE SETPOINTS. DURING UNOCCUPIED MODE, THE MINIMUM OUTSIDE AIR DAMPER SHALL BE ALLOWED TO CLOSE COMPLETELY IF ECONOMIZER CONDITIONS AREN'T MET. THE SUPPLY FAN(S) IS OFF WHENEVER SPACE TEMPERATURE IS BETWEEN THE UNOCCUPIED HEATING AND COOLING SETPOINTS. BUILDING IS OCCUPIED FROM 7:30 AM UNTIL 6:00 PM (ADJ). BUILDING SHALL BEGIN START UP 90 MINUTES (ADJ) PRIOR TO
OCCUPANCY AND SHALL START UNOCCUPIED MODE 30 MINUTES (ADJ) AFTER OCCUPANCY ENDS.
MORNING WARM-UP/COOL-DOWN MODE: THE AHU IS SCHEDULED TO ENTER WARMUP/COOLDOWN MODE 1 HOUR (ADJ) PRIOR TO OCCUPIED MODE AS SET ON A USER DEFINABLE SCHEDULE VIA THE BAS WITH MANUAL OVERRIDE, AS REQUIRED, FROM THE VA ACCESSIBLE FRONT END. THE BAS SHALL KEEP OUTDOOR AIR DAMPERS CLOSED IF ECONOMIZER CONDITIONS AREN'T MET. THE BAS SHALL ENABLE THE ASSOCIATED VAV BOXES TO OPERATE IN THEIR OCCUPIED MODE SETPOINTS. AS THE SPACE TEMPERATURE APPROACHES WITHIN 2°F OF SPACE SETPOINT TEMPERATURE, OUTSIDE AIR DAMPER SHALL MODULATE TO THE SCHEDULED MINIMUM OUTSIDE AIR.
THE ALARMS SHALL BE PROVIDED AS FOLLOWS:
• HIGH MIXED AIR TEMPERATURE: 5° F HIGHER THAN SETPOINT.
• LOW MIXED AIR TEMPERATURE: 5° F LOWER THAN SETPOINT.
• HIGH OR LOW SUPPLY AIR TEMPERATURE.
• FILTER DIFFERENTIAL PRESSURE ALARM: PER DIRTY FILTER PRESSURE DROP AS SHOWN IN AHU SCHEDULE.
18-EF-01: EXHAUST FAN SHALL BE INTERLOCKED WITH AHU. THE FAN SPEED IS ADJUSTED DURING TAB THROUGH THE BAS. WHEN STATUS IS LOST, AN ALARM SHALL BE SENT TO THE
BAS.
18-EF-02 (E): EXHAUST FAN SHALL BE INTERLOCKED WITH AHU. THE FAN SPEED IS ADJUSTED DURING TAB THROUGH THE BAS. WHEN STATUS IS LOST, AN ALARM SHALL BE SENT TO
THE BAS.
18-ACCH-1: THE PACKAGED SYSTEM CONSISTS OF 1 AIR COOLED CHILLER AND 2 CHILLED WATER PUMPS. CHILLER CONTROLS SHALL CONSIST OF BAC NET PROTOCOL BASED FACTORY PACKAGED TOUCHPAD SYSTEM CAPABLE OF RECEIVING AND OBEYING HARDWIRED CONTROL POINTS INDICATED. ALL INFORMATION WITHING THE CHILLER CONTROL (I.E.
RUNTIMES, CYCLE COUNTRS, KW, KWH, TONNAGE, REFRIGERANT PRESSURES, ETC) SHALL BE COMMUNICATED TO THE BAS FRONT END TO PERMIT ENERGY MANAGEMENT.
CHILLED WATER PRODUCTION: THE AIR COOLED CHILLER SHALL RUN WHENEVER THE SYSTEM HAS BEEN MANUALLY SWITCHED OVER TO COOLING MODE AND THE OUTSIDE AIR TEMPERATURE IS ABOVE 60°F. IF THE CHILLED WATER RETURN TEMPERATURE IS GREATER THAN THE CHILLER CHILLER MANUFACTUER'S MAXIMUM ALLOWABLE EVAPORATOR ENTERING WATER TEMPERATURE, WAIT TO START THE CHILLER UNTIL WATER COOLS BELOW MAXIMUM TEMPERATURE LIMIT. CHILLER SHALL MODULATE ITS CAPACITY BASED ON FACTORY PROVIDED CONTROLS TO PROVIDE CHILLED WATER SUPPLY AT SETPOINT. INTERNAL CONTROLS SHALL SEQUENCE PRIMARY AND SECONDARY CHILLED WATER PUMPS TO
MAINTAIN WATER FLOW RATE.
18-FCU-1, 18-FCU-2, 18-FCU-3, AND 18-CU-1: UNITS SHALL OPERATE CONTINUOUSLY VIA INTERNAL CONTROLS TO MAINTAIN ROOM SETPOINT TEMPERATURE OF 80°F (ADJ.). WHEN STATUS IS LOST OR UNIT SIGNALS A HIGH ROOM TEMPERATURE ALARM, AN ALARM SHALL BE SENT TO THE BAS.
EXHAUST FAN CONTROL SEQUENCES:
SPLIT AIR CONDITIONER SEQUENCES:
18-AHU-1 CONTROL SEQUENCE:
AIR COOLED CHILLER SEQUENCES:
EA
RA
OA
BAST
PRE-FILTERS
HEATING
WATER COIL
CHILLED WATER
COOLING COIL
SD
TO FIRE ALARM
PANEL
TO CONTROL PANEL
V F
D
BAS
RA
SD TO FIRE ALARM
PANEL
TO CONTROL PANEL
SA
BASTBAS
T
BAS
BAS0
PDS
BAST
FREEZE STAT
M
NC
BAS
M
NO
BAS
BAS
PT
BAS
PDSSTEAM
HUMIDIFIER
LPS
V-3
PSHAFTER-FILTER
M
NC
BAS
MT
BAS
T
MT
HWR
HWS
NO
AFMD
BAS
AFMD BAS
BAS
PT
PLACE SENSOR 2/3 WAY
DOWN FURTHEST SUPPLY
DUCT (SEE 18-MH-131)
V F
D
BAS
SUPPLY FAN(S)
BAS
RETURN FAN(S)
BAS
AFMD
BAS
PLACE SENSOR 2/3 WAY
DOWN FURTHEST SUPPLY
DUCT (SEE 18-MH-131)
MIXED
AIR TEMP
CHR
CHS
NO
th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t o n e e ig h th in c h o n e fo o t
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
Veterans Health
Administration
VA FORM 08-6231
Drawing Title Project Title
Location
Date Checked Drawn
Project Number
Building Number
Drawing Number
CONSULTANTS: 657-19-103JB
VA Health Care System Approval:
Revision: Date:
ARCHITECT/ENGINEER:
750 W HAMPDEN AVE
SUITE 300
ENGLEWOOD, CO 80110
(720) 550-6307
WWW.VALHALLAENGINEERING.COM VEG 19.7
100% CONTRACT DOCUMENT SUBMITTAL DRAWINGS
JEFFERSON BARRACKS
1 JEFFERSON BARRACKS DRIVE - ST. LOUIS, MO 63125
02/10/2020
/1
/2
:1 :0
A
M
00-MG-702
MECHANICAL CONTROLS
18 & 60
FCA - REPLACE MECHANICAL
SYSTEMS IN BUILDING 18 & 60
DD ANT Drawing # 25 of 77
NTS
18-AHU-01 VARIABLE AIR VOLUME AIR HANDLING UNIT WITH
MINIMUM OUTSIDE AIR CONTROLS DIAGRAM
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
FAP
FAP
FAP
FAP
RAD
RAD
RAD
RADRAD
RADRAD
RADRADRAD
RAD
RAD
RADRAD
RADRADRADRAD
RAD
RADRAD
RAD
RAD
RAD RAD
RAD RAD RAD
RAD
RAD RAD
RAD
RAD
RAD
RAD
RAD
OFFICE
OFFICE
OFFICE
FILE RM.
OFFICE
OFFICE
WORK RM.
STORAGE
TOILET, MALE
ELEVATOR LOBBY
100 TOILET, FEMALE
STAIRWELL NO. 2
S102
CORRIDOR
H102
CORRIDOR
H103
OI&T
OFFICE
CORRIDOR
H101
OFFICE
OFFICE
OFFICE
OFFICE
OFFICE
OFFICE
LIBRARY
CORRIDOR
H104
CONFERENCE RM.
OFFICE
OFFICE
OFFICE
OFFICE
OFFICE
OFFICE
OFFICE
114A
OFFICE
BREAK RM.
115A
OFFICE, OPEN
OFFICE
OFFICE, CHIEF
113A
OFFICE
OFFICE
OFFICE
CORRIDOR
H105
ELEVATOR
E1
STAIRWELL NO. 3
S103
RECEPTION
STAIRWELL NO. 1
S101
"x
"x
40"x19"
50"x19"
"x
"x
18-TEMP-01
Plan North True North KEYPLAN th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t o n e e ig h th in c h o n e fo o t
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
Veterans Health
Administration
VA FORM 08-6231
Drawing Title Project Title
Location
Date Checked Drawn
Project Number
Building Number
Drawing Number
CONSULTANTS: 657-19-103JB
VA Health Care System Approval:
Revision: Date:
ARCHITECT/ENGINEER:
750 W HAMPDEN AVE
SUITE 300
ENGLEWOOD, CO 80110
(720) 550-6307
WWW.VALHALLAENGINEERING.COM VEG 19.7
100% CONTRACT DOCUMENT SUBMITTAL DRAWINGS
JEFFERSON BARRACKS
1 JEFFERSON BARRACKS DRIVE - ST. LOUIS, MO 63125
02/10/2020
/1
/2
:1 :3
A
M
18-MG-801
MECHANICAL PHASING PLAN
FCA - REPLACE MECHANICAL
SYSTEMS IN BUILDING 18 & 60
DD RT Drawing # 26 of 77
PHASE 0:
1. INSTALL NEW HOT WATER HEAT EXCHANGER WITH TEMPORARY CONNECTION TO
EXISTING LOW PRESSURE STEAM MAIN.
2. INSTALL NEW PRESSURE REDUCING VALVE, PUMPS, AND DOMESTIC WATER
HEATER.
3. INSTALL DIRECT DIGITAL CONTROLS INFRASTRUCTURE. PREPARE CONNECTIONS
FOR ALL NEW MECHANICAL EQUIPMENT.
4. DEMOLISH EXISTING SUPPLY DUCT WORK IN MAIN CHASE. INSTALL NEW SUPPLY
DUCT WORK AND VERTICAL PIPING RISERS IN MAIN CHASE. MINIMUM 5 DAYS
DOWNTIME. COORDINATE WITH OUTSIDE AIR TEMPERATURE < 55°F.
5. INSTALL TEMPORARY PACKAGED AIR CONDITIONER AND CONNECT TO RETURN
AND SUPPLY MAINS. SEE PLAN BELOW FOR CONNECTION DETAILS.
6. DEMOLISH EXISTING AIR HANDLING UNIT, RETURN FAN, AND ALL ASSOCIATED
DUCTWORK. SEE 18-MD-102 FOR LIMITS OF DEMOLITION.
7. DEMOLISH EXISTING DX UNIT, CONCRETE PAD, AND ASSOCIATED PIPING.
8. INSTALL NEW CHILLER, CONCRETE PAD, ASSOCIATED PIPING, BUFFER TANK, AND
FENCING.
9. INSTALL NEW AIR HANDLING UNIT, RETURN FAN, AND ASSOCIATED DUCT WORK.
10. PERFORM INITIAL START UP OF SUPPLY AND RETURN FAN.
11. REMOVE TEMPORARY PACKAGED AIR CONDITIONER AND TRANSITION SYSTEM
OVER TO NEW UNITS.
PHASE I - VII:
1. REMOVE DROP CEILING IN CORRIDOR(S) AND OTHER LOCATIONS NOTED ON
PLAN SHEETS.
2. DEMOLISH ALL SUPPLY DUCT WORK, SUPPLY DIFFUSERS, AND OTHER HVAC
EQUIPMENT IN WORK AREA. SEE PLAN SHEETS FOR LIMITS OF DEMOLITION.
3. INSTALL NEW SUPPLY DUCTWORK, SUPPLY DIFFUSERS, VAV UNITS, AND
HEATING WATER PIPING BACK TO MAIN.
4. REINSTALL DROP CEILING IN CORRIDOR(S) AND OTHER LOCATIONS NOTED ON
PLAN SHEETS.
5. PERFORM TEST AND BALANCING, AS REQUIRED, FOR NEW WORK.
PHASE VIII:
1. DEMOLISH ALL EXISTING LOW PRESSURE STEAM PIPING IN MECH. RM. 002 AND
SUB-BASEMENT. SEE 18-MD-101 FOR LIMITS OF DEMOLITION.
2. DEMOLISH AND REPLACE STEAM AND CONDENSATE MAINS IN SUB-BASEMENT.
SEE 18-MD-101 AND 18-MP-100 FOR LIMITS OF DEMOLITION AND NEW
CONSTRUCTION.
3. DEMOLISH ALL STEAM CONVECTOR STEMS AND INSTALL NEW PANEL COVERS TO
EACH UNIT.
4. DEMOLISH ALL PNEUMATIC CONTROLS. PNEUMATIC CONTROLS AND TUBING CAN
BE REMOVED WITH ASSOCIATED EQUIPMENT DURING PHASES I THROUGH VII;
HOWEVER ENSURE PNEUMATIC CONTROL SYSTEM REMAINS FUNCTIONAL FOR
THE REST OF THE BUILDING.
BUILDING 18:
1. ALL RETURN DUCT WORK IS TO BE CLEANED AND REUSED UNLESS
OTHERWISE NOTED. ANY NONCONFORMING DUCT IS TO BE REMOVED
AND REPLACED. SAMPLING AND TESTING OF THE RETURN DUCTWORK
IS TO BE CONDUCTED BEFORE AND AFTER THE CLEANING PROCESS.
THIS WORK IS TO BE DONE AT ANY POINT DURING THE FOLLOWING
CONSTRUCTION PHASES.
2. SEE 18-AE-101 AND 18-AE-102 FOR ARCHITECTURAL PHASE
LOCATIONS.
GENERAL NOTES:
1/8" = 1'-0"
MECHANICAL TEMPORARY HVAC PLAN - FLOOR 01
Plan North
True North
KEYNOTES:
EXISTING WINDOWS ARE TO BE REMOVED TEMPORARILY TO
ALLOW FOR ROUTING OF TEMPORARY DUCTWORK. REINSTALL
WINDOWS AFTER PHASE 0.
"ø
L P
S
2 1/2"ø LPS
3"ø LPS 1"ø LPR
1"ø LPR
1"ø LPR
"ø
L P
S
"ø
L P
R
1"ø LPR
4"ø HPS 1 1/2"ø PC
3"ø LPS 1"ø LPR
"ø
L P
S "ø
L P
R
3"ø LPS
1"ø LPR
"ø
L P
R
3" DX PIPING
Plan North True North KEYPLAN th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t o n e e ig h th in c h o n e fo o t
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
Veterans Health
Administration
VA FORM 08-6231
Drawing Title Project Title
Location
Date Checked Drawn
Project Number
Building Number
Drawing Number
CONSULTANTS: 657-19-103JB
VA Health Care System Approval:
Revision: Date:
ARCHITECT/ENGINEER:
750 W HAMPDEN AVE
SUITE 300
ENGLEWOOD, CO 80110
(720) 550-6307
WWW.VALHALLAENGINEERING.COM VEG 19.7
100% CONTRACT DOCUMENT SUBMITTAL DRAWINGS
JEFFERSON BARRACKS
1 JEFFERSON BARRACKS DRIVE - ST. LOUIS, MO 63125
02/10/2020
/1
/2
:1 :1
A
M
18-MD-101
MECHANICAL DEMOLITION PLAN -
SUB-BASEMENT
FCA - REPLACE MECHANICAL
SYSTEMS IN BUILDING 18 & 60
DD RDT Drawing # 27 of 77
1/8" = 1'-0"
MECHANICAL DEMOLITION PLAN - SUB-BASEMENT
Plan North
True North
1. REFER TO 00-MG-001 AND 00-MG-002 FOR MECHANICAL SYMBOLS,
ABBREVIATIONS, AND GENERAL NOTES.
2. GENERAL CONTRACTOR SHALL FIELD VERIFY ALL EXISTING
CONDITIONS AND REPORT ANY DISCREPANCIES TO THE COR
BEFORE PROCEEDING WITH WORK.
3. REFER TO 00-MG-801 FOR ALL CONSTRUCTION PHASING
REQUIREMENTS.
GENERAL NOTES:
KEYNOTES:
EXISTING PRV, ASSOCIATED EQUIPMENT, AND CONTROLS
ARE TO BE DEMOLISHED PER SPECIFICATION SECTION 02
41 00 DEMOLITION.
EXISTING STEAM AND CONDENSATE PIPING ALONG
PERIMETER OF BUILDING IS TO BE DEMOLISHED UP TO
EACH RISER. EXISTING RISERS ARE TO BE ABANDONED IN
PLACE.
DEMOLISH EXISTING DX UNIT, CONCRETE PAD AND ALL
ASSOCIATED PIPING.
DEMOLISH EXISTING DOMESTIC WATER HEATER AND
ASSOCIATED PIPING BACK TO MAIN.
2 2
97"x78" RELIEF AIR OUTLET
(44140 CFM MAX)
40" DIAMETER VERTICAL
SUPPLY DUCT
60"x32" VERTICAL
RETURN DUCT
126"x96" OUTSIDE AIR
INTAKE (44,140 CFM MAX)
18"x12" EXHAUST AIR
OUTLET (590 CFM).
REUSE EXISTING
LOUVER.
VAV-B-E6
VAV-B-E4
VAV-B-E5VAV-B-E3VAV-B-E7
VAV-B-E2
VAV-B-E1
18-RF1
18-CCF1
18-AC1
PIPE CHASE
Z001
MECH. RM.
CORRIDOR
H001
ELEVATOR MACHINE
RM.
STAIRWELL NO. 2
S002
CORRIDOR
H002
MECH. RM.
MECH. RM.
003A
OI&T
003B
TOILET, UNISEX
TOILET, FEMALE
BREAK RM.
OFFICE
VENDING
H003
OFFICE
OFFICE
OFFICE, CHIEF
OFFICE
ELEVATOR LOBBY
ELEVATOR
E1
Plan North True North KEYPLAN th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t o n e e ig h th in c h o n e fo o t
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
Veterans Health
Administration
VA FORM 08-6231
Drawing Title Project Title
Location
Date Checked Drawn
Project Number
Building Number
Drawing Number
CONSULTANTS: 657-19-103JB
VA Health Care System Approval:
Revision: Date:
ARCHITECT/ENGINEER:
750 W HAMPDEN AVE
SUITE 300
ENGLEWOOD, CO 80110
(720) 550-6307
WWW.VALHALLAENGINEERING.COM VEG 19.7
100% CONTRACT DOCUMENT SUBMITTAL DRAWINGS
JEFFERSON BARRACKS
1 JEFFERSON BARRACKS DRIVE - ST. LOUIS, MO 63125
02/10/2020
/1
/2
:1 :1
A
M
18-MD-102
MECHANICAL DEMOLITION PLAN -
FLOOR 00
FCA - REPLACE MECHANICAL
SYSTEMS IN BUILDING 18 & 60
DD RDT Drawing # 28 of 77
1. REFER TO 00-MG-001 AND 00-MG-002 FOR MECHANICAL SYMBOLS,
ABBREVIATIONS, AND GENERAL NOTES.
2. GENERAL CONTRACTOR SHALL FIELD VERIFY ALL EXISTING
CONDITIONS AND REPORT ANY DISCREPANCIES TO THE COR
BEFORE PROCEEDING WITH WORK.
3. REFER TO 00-MG-801 FOR ALL CONSTRUCTION PHASING
REQUIREMENTS.
4. ALL SUPPLY DUCTS, AIR TERMINALS, AND MECHANICAL
EQUIPMENT SHOWN IN DEMOLITION PLAN ARE TO BE REMOVED
UNLESS OTHERWISE NOTED.
5. RETURN DUCT SHALL BE CLEANED AND REMAIN UNLESS
OTHERWISE NOTED.
GENERAL NOTES:
KEYNOTES:
PNEUMATIC COMPRESSORS AND CONTROL SYSTEMS SHALL
REMAIN FUNCTIONAL PER PHASING PLAN.
Plan North True North1/8" = 1'-0"
MECHANICAL DEMOLITION PLAN - FLOOR 00
UP
UP
UP
UP
UP
UP
UP
UP
UP
UP
RAD
RAD
RAD
RADRAD
RADRAD
RADRADRAD
RAD
RAD
RADRAD
RADRADRADRAD
RAD
RADRAD
RAD
RAD
RAD RAD
RAD RAD RAD
RAD
RAD RAD
RAD
RAD
RAD
RAD
RAD
RAD
RAD
RAD
RADRAD
RADRAD
RADRADRAD
RAD
RAD
RADRAD
RADRADRADRAD
RAD
RADRAD
RAD
RAD
RAD RAD
RAD RAD RAD
RAD
RAD RAD
RAD
RAD
RAD
RAD
RAD
OFFICE
OFFICE
OFFICE
FILE RM.
OFFICE
OFFICE
WORK RM.
STORAGE
TOILET, MALE
ELEVATOR LOBBY
100 TOILET, FEMALE
STAIRWELL NO. 2
S102
CORRIDOR
H102
CORRIDOR
H103
OI&T
OFFICE
CORRIDOR
H101
OFFICE
OFFICE
OFFICE
OFFICE
OFFICE
OFFICE
LIBRARY
CORRIDOR
H104
CONFERENCE RM.
OFFICE
OFFICE
OFFICE
OFFICE
OFFICE
OFFICE
OFFICE
114A
OFFICE
BREAK RM.
115A
OFFICE, OPEN
OFFICE
OFFICE, CHIEF
113A
OFFICE
OFFICE
OFFICE
CORRIDOR
H105
ELEVATOR
E1
STAIRWELL NO. 3
S103
RECEPTION
STAIRWELL NO. 1
S101
12"x10" VERTICAL
EXHAUST DUCT
38" DIAMETER
VERTICAL SUPPLY
DUCT
VERTICAL
RETURN SHAFT
VAV-1-E10
VAV-1-E11
VAV-1-E9
VAV-1-E12VAV-1-E2
VAV-1-E8VAV-1-E7
VAV-1-E13VAV-1-E14
VAV-1-E6
VAV-1-E15
VAV-1-E1
VAV-1-E16
VAV-1-E17
VAV-1-E5
VAV-1-E3VAV-1-E18
VAV-1-E4
Plan North True North KEYPLAN th re e in c h e s o n e fo o t o n e a n d o n e…