About this file

36C25520Q0038 36C25520Q0038_2.docx

View the file

Other files

File Type Posted
36C25520Q0038-0001001.pdf PDF
36C25520Q0038-0001000.docx DOCX document
36C25520Q0038-006.pdf PDF
36C25520Q0038-007.pdf PDF
36C25520Q0038-005.pdf PDF
36C25520Q0038-004.docx DOCX document
36C25520Q0038-007.pdf PDF
36C25520Q0038-005.pdf PDF
36C25520Q0038-006.pdf PDF
36C25520Q0038-003.docx DOCX document
36C25520Q0038-003.docx DOCX document
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C25520Q0038

PAGE 1 OF

1. REQUISITION NO.

2. CONTRACT NO.

3. AWARD/EFFECTIVE DATE

4. ORDER NO.

5. SOLICITATION NUMBER

6. SOLICITATION ISSUE DATE

a. NAME

b. TELEPHONE NO. (No Collect Calls)

8. OFFER DUE DATE/LOCAL

TIME

9. ISSUED BY

CODE

10. THIS ACQUISITION IS

UNRESTRICTED OR

SET ASIDE:

% FOR:

SMALL BUSINESS

HUBZONE SMALL

BUSINESS

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

WOMEN-OWNED SMALL BUSINESS

(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

8(A)

NAICS:

SIZE STANDARD:

11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

12. DISCOUNT TERMS

13a. THIS CONTRACT IS A

RATED ORDER UNDER

DPAS (15 CFR 700)

13b. RATING

14. METHOD OF SOLICITATION

RFQ

IFB

RFP

15. DELIVER TO

CODE

16. ADMINISTERED BY

CODE

17a. CONTRACTOR/OFFEROR

CODE

FACILITY CODE

18a. PAYMENT WILL BE MADE BY

CODE

TELEPHONE NO.

DUNS:

DUNS+4:

PHONE:

FAX:

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED

SEE ADDENDUM

19.

20.

21.

22.

23.

24.

ITEM NO.

SCHEDULE OF SUPPLIES/SERVICES

QUANTITY

UNIT

UNIT PRICE

AMOUNT

(Use Reverse and/or Attach Additional Sheets as Necessary)

25. ACCOUNTING AND APPROPRIATION DATA

26. TOTAL AWARD AMOUNT (For Govt. Use Only) 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA

ARE

ARE NOT ATTACHED.

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA

ARE

ARE NOT ATTACHED

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN _______________

29. AWARD OF CONTRACT: REF. ___________________________________ OFFER

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

DATED ________________________________. YOUR OFFER ON SOLICITATION

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED

SET FORTH HEREIN IS ACCEPTED AS TO ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER) 30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (TYPE OR PRINT) 31c. DATE SIGNED

AUTHORIZED FOR LOCAL REPRODUCTION

(REV. 2/2012)

PREVIOUS EDITION IS NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.212

7. FOR SOLICITATION

INFORMATION CALL:

STANDARD FORM 1449

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

36C25520Q0038 11-07-2019 Khamoy Sysengchanh @va.gov 913-946-1975 11-20-2019 5:00 pm 36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway Leavenworth KS 66048 X X 541330 $16.5 Million N/A X John J. Pershing VA Medical Center 1500 North Westwood Blvd. Building #7 Poplar Bluff MO 63901 36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway Leavenworth KS 66048

36C255 Department of Veterans Affairs Financial Services Center http://www.fsc.va.gov/einvoice.asp Austin TX 877-353-9791 512-460-5429 See CONTINUATION Page John J. Pershing VA Medical Center - Poplar Bluff, MO Boiler Plant Inspection and Safety Device Testing with reports.

1. This is a 100% Set Aside for Service-Disabled Veteran Owned Small Business (SDVOSB) and Veteran Owned Small Business (VOSB).

2. SDVOSB's and VOSB's must be registered and CVE Certified in VetBiz.gov (www.vip.vetbiz.gov) at submittal and time of award.

3. Contractor shall provide all tools and labor necessary to perform inspections, testing, and calibrations of the boiler plant burners, controls, and instruments as specified in the Statement of Work.

4. This contract will be a Base plus four option years.

5. See E.2 ADDENDUM to FAR 52.212-1: Instructions to Offerors on pages 38-40.

See CONTINUATION Page X X Frank Novello Contracting Officer Table of Contents

SECTION A1
A.1 SF 1449 SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS1
SECTION B - CONTINUATION OF SF 1449 BLOCKS3
B.1 CONTRACT ADMINISTRATION DATA3
B.2 SCHEDULE OF PRICE AND DELIVERY5
B.3 STATEMENT OF WORK6
SECTION C - CONTRACT CLAUSES19
C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL ITEMS (OCT 2018)19
C.2 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)24
C.3 52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000)24
C.4 SUPPLEMENTAL INSURANCE REQUIREMENTS25
C.5 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)25
C.6 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018)26
C.7 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (DEVIATION)26
C.8 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018)28
C.9 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)28
C.10 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008)30
C.11 52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR EXECUTIVE ORDERS—COMMERCIAL ITEMS (OCT 2019)30
SECTION D - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS38
SECTION E - SOLICITATION PROVISIONS39
E.1 52.212-1 INSTRUCTIONS TO OFFERORS—COMMERCIAL ITEMS (OCT 2018)39
E.2 ADDENDUM to FAR 52.212-1: Instructions to Offerors42
E.3 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)44
E.4 52.212-2 EVALUATION—COMMERCIAL ITEMS (OCT 2014)45
E.5 52.212-3 OFFEROR REPRESENTATIONS AND CERTIFICATIONS—COMMERCIAL ITEMS (OCT 2018)45

SECTION B - CONTINUATION OF SF 1449 BLOCKS

B.1 CONTRACT ADMINISTRATION DATA

(continuation from Standard Form 1449, block 18A.)

(a). CONTRACT ADMINISTRATION: All contract administration matters will be handled by the following individuals:

(1). CONTRACTOR:____________________________________
____________________________________
____________________________________
____________________________________
DUNS:____________________________________
Tax Identification Number (TIN):____________________________________
Contact person name:____________________________________
Contact person email:____________________________________
Contact person telephone:____________________________________
(2). GOVERNMENT:DEPT. OF VETERANS AFFAIRS
Veterans’ Health Administration
Network Contracting Office (NCO) 15
Contracting Officer: Frank Novello
3450 S 4th St.
Leavenworth KS 66048

(b). CONTRACTOR REMITTANCE ADDRESS: All payments by the Government to the contractor will be made in accordance with:

[X]
52.232-33, Payment by Electronic Funds Transfer—System For Award Management, or
[]
52.232-36, Payment by Third Party

(c). INVOICES: Invoices shall be submitted in arrears:

a. Quarterly[]
b. Semi-Annually[]
c. Other[X] Monthly, in arrears for services furnished during the previous

month.

(d). GOVERNMENT INVOICE ADDRESS: All Invoices from the contractor shall be submitted electronically in accordance with VAAR Clause 852.232-72 Electronic Submission of Payment Requests.

Department of Veterans Affairs Financial Services Center http://www.fsc.va.gov/einvoice.asp Austin TX ACKNOWLEDGMENT OF AMENDMENTS: The offeror acknowledges receipt of amendments to the Solicitation numbered and dated as follows:

AMENDMENT NO
DATE

(e). GOVERNMENT INVOICE ADDRESS: Invoices will be provided in accordance with the requirements listed in FAR 52.212-4, Commercial Items – Terms and Conditions, (MAY 2014), (g) Invoice; and VAAR 852.232-72 Electronic Submission of Payment Request (NOV 2012); electronically to:

Department of Veterans Affairs
Financial Services Center
http://www.fsc.va.gov/einvoice.asp
Austin TX

(f). REFERENCE NUMBERS: Please reference both the Task Order number (to be assigned) and the Purchase Order Number (to be assigned) on all correspondence and invoices. If contract option years are exercised, new obligation numbers will be issued and identified on the contract modification document.

(g). AUTHORIZATIONS:

(1). The Contracting Officer (CO) named in Section (a) above is responsible for the overall administration of this contract. Only the CO has the authority to make changes which affect:

(A). Contract prices, (B). Quality, (C). Quantities, or (D). Delivery terms and conditions.

(2). Contracting Officer Representatives (COR) and Alternate Contracting Officer’s Representatives (Alt-COR) may be assigned to this contract. The COR and Alt-COR shall be provided specific written delegated authority by the CO, a copy of which will be provided to the Contractor.

(h). CHANGES TO THE CONTRACT: No individual or activity has authority to ADD, DELETE, CHANGE, OR MODIFY this contract of issued orders except by the CO or by written authority specifically delegated by the CO.

(i). CONTRACT TIME PERIOD:

(1). It is anticipated that the contract will be for a base year and four (4) option years, which will be exercised at the discretion of the Government. The estimated contract Base year period of performance shall commence on or about January 1, 2020 and expire December 31, 2020.

B.2 SCHEDULE OF PRICE AND DELIVERY

This is a firm fixed price contract with a Base Year of performance and 4-Option Years. The exercise of option years is at the discretion of the Government.

Base Year: 01/01/2020 to 12/31/2020

CLIN
Description
Estimated Quantity
Unit
Unit Cost
Total Cost
0001
Provide Boiler Plant Inspection and Safety Device Testing per Statement of Work.
1
YR
$
$
Total Cost
$

Option Year 1: 01/01/2021 to 12/31/2021

CLIN
Description
Estimated Quantity
Unit
Unit Cost
Total Cost
1001
Provide Boiler Plant Inspection and Safety Device Testing per Statement of Work.
1
YR
$
$
Total Cost
$

Option Year 2: 01/01/2022 to 12/31/2022

CLIN
Description
Estimated Quantity
Unit
Unit Cost
Total Cost
2001
Provide Boiler Plant Inspection and Safety Device Testing per Statement of Work.
1
YR
$
$
Total Cost
$

Option Year 3: 01/01/2023 to 12/31/2023

CLIN
Description
Estimated Quantity
Unit
Unit Cost
Total Cost
3001
Provide Boiler Plant Inspection and Safety Device Testing per Statement of Work.
1
YR
$
$
Total Cost
$

Option Year 4: 01/01/2024 to 12/31/2024

CLIN
Description
Estimated Quantity
Unit
Unit Cost
Total Cost
4001
Provide Boiler Plant Inspection and Safety Device Testing per Statement of Work.
1
YR
$
$
Total Cost
$

Total of Base Year and 4-Option Years: $___________

Page 1 of Page 1 of

B.3 STATEMENT OF WORK

STATEMENT OF WORK

Project Title Inspection of Boilers and Boiler Plant Safety Device Testing

1. Introduction:

A. The John J. Pershing Veterans Affairs Medical Center (VAMC) have a central 3 Low pressure boilers in the boiler plant to provide steam for heating and air conditioning, domestic hot water and kitchens. SPS/Endo has 2 small high pressure boilers for sterilization.

B. Boiler plant safety, reliability, efficiency and equipment longevity are paramount concerns of VAMC management. Boilers and feedwater deaerators are pressurized devices containing steam and hot water. They can fail catastrophically causing injuries and death and massive property damage. Regular inspections by experts are an essential part of a program to address these concerns. Malfunctioning burners or controls can cause catastrophic events resulting in injuries and death and massive property damage. Inaccurate or inadequate data management and monitoring systems can fail to warn of unsafe or inefficient performance. Regular inspections, testing and calibration by expert technicians are an essential part of a program to address these concerns.

C. This “Statement of Work” describes the requirements for the boiler inspections to be performed by “Qualified Professional Inspectors” under contract. This “Statement of Work” also describes the requirements for the inspection, testing and calibration of the boiler plant burners, controls, and instruments by qualified burner and instrument technicians.

D. A separate document lists the facilities where the inspections will be required, lists the boilers to be inspected at each facility and provides a schedule for the inspections and safety testing. Other pressure vessels may be included in the inspection and testing requirements.

E. “Qualified Professional Inspectors” as defined below shall perform internal and external inspections on high pressure (over 15 psig) steam boilers and internal inspections on feedwater deaerators and other pressure vessels.

F. The terms of this contract will be for one year with four option years (subject to the availability of funds).

2. “Qualified Professional Inspector” is defined as any one or combination of:

A. A boiler inspector who has a valid commission from the National Board of Boiler and Pressure Vessel Inspectors (NB).

B. A boiler inspector who has qualified by passing a written examination under the laws, rules and regulations of a jurisdiction of a state.

C. A boiler inspector who is regularly employed as a boiler inspector by a jurisdiction which has adopted and administers one or more sections of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code as a legal requirement, and has a representative serving as a member of the ASME Conference Committee.

Page 1 of Page 1 of D. A boiler inspector who is regularly employed by an insurance company which has been licensed or registered by the appropriate authority of a State of the United States to write boiler or pressure vessel insurance.

3. Technician Qualifications:

A. Technicians shall have completed at least a one-year trade school and have five years successful experience in this field. The experience shall be largely with institutional and industrial boiler plants similar in design to the VAMC plant. The VAMC facility manager/engineer may define and accept equivalent qualifications.

B. Technicians shall demonstrate familiarity with and ready access to the current versions of the following references.

NFPA 85, Boiler and Combustion Systems Hazard Code. VHA Boiler Plant Safety Device Test Manual, 5th Edition.

C. Technicians shall be equipped with portable electronic flue gas analyzers and other test instruments necessary for the required tests and calibrations, all calibrated within one month of the site visits. At facilities with programmable digital controls, the technicians must be capable of programming the controls and have the appropriate hardware and software for this.

4. Qualifications for Non-Destructive-Testing Technicians:

The technicians shall be certified as being qualified Level II technicians in the non- destructive testing methods to be utilized. The certification shall be in accordance with the requirements of the American Society for Non-Destructive Testing (ASNT).

5. Reference Materials:

The “Qualified Professional Inspector” shall demonstrate familiarity with and ready access to the current versions of the following codes and manuals:

ASME Boiler and Pressure Vessel Code: Section I - Power Boilers Section IV - Heating Boilers Section VI - Care and Operation of Heating Boilers Section VII - Care of Power Boilers ASME B31.1, Power Piping Code ASME CSD-1, Controls and Safety Devices for Automatically Fired Boilers ANSI/NB-23, National Board Inspection Code NFPA 85, Boiler and Combustion Systems Hazards Code VHA Boiler Plant Safety Device Testing Manual, 5th Ed.

6. Boiler Safety Device Testing and Inspection Requirements:

A. Annual internal and external inspections are required for each boiler.

B. A generalized annual schedule of visits for the boiler plant is as follows:

1) February Internal inspection Boiler #1

2) February External inspection Boiler #3

3) February Annual Internal Electric High pressure Boiler #1

Page 1 of Page 1 of

4) February Annual External Electric High pressure Boiler #2

5) February Annual Safety Devices testing Boiler #3

6) February Semi-annual Safety Device testing Boiler #2

7) June Annual Safety Device testing Boiler #1

8) June Semi Annual Safety Device testing Boiler #3

9) June Annual Internal inspection Boiler #2

10) June Annual External inspection Boiler #1

11) June Annual Internal Electric High pressure Boiler #2

12) June Annual External Electric High pressure Boiler #1

13) June Annual Internal D.A Tank inspection

14) October Annual Internal inspection Boiler #3

15) October Annual Safety Device testing Boiler #2

16) October Semi-annual Safety Device testing Boiler #1

17) October Annual External inspection Boiler #2

18) October Annual Condensate tank Inspection At least two weeks’ notice to VAMC is required prior to an inspection and when the Contracting Officer’s Representative (COR) or his/her designate is available on site to monitor the inspections. To maintain steam service only one boiler at a time will be scheduled for internal inspections per inspection visit. Thus, five visits will be necessary every year to inspect all the boilers internally and perform Annual and Semi-Annual testing.

C. Coordinate the inspection schedule with the COR so that VAMC can prepare the boilers for the inspections in advance and have personnel available to monitor the inspections.

D. The COR is …. John J. Pershing VAMC.

E. Boilers scheduled for internal inspection will be prepared for the inspection by VAMC prior to the scheduled arrival of the inspector. This includes cooling the boilers to near ambient temperature and having all manways, handholes and furnace access doors open; the boilers cleaned of loose materials waterside and fireside; electrical “lock-out, tag-out” in place; connecting piping isolated; proper illumination provided; compliance with “confined space” access requirements including having safety personnel present in the boiler plant. Similar advance preparations will be made to the feedwater deaerator when it is scheduled for internal inspection.

F. VAMC will comply with any other requirements of the inspector that are considered reasonable by VAMC and have been presented in writing at least two weeks prior to the scheduled inspection.

G. The boiler inspector shall comply with the guidelines in the current issue of the NATIONAL BOARD INSPECTION CODE, Part RB, Inservice Inspection of Pressure- Retaining Items, and ASME Boiler and Pressure Vessel Code, Section VI or VII as applicable. In addition to those guidelines, the inspections shall comply with all VAMC requirements as listed in this document.

H. The inspector must completely enter the internal spaces of the boiler or feedwater deaerator and visually inspect all internal surfaces that can be accessed.

I. Methods for testing safety devices shall comply with VHA Boiler Plant Safety Device Testing Manual, 5th Edition.

J. Summary of the minimum inspection requirements for boilers:

1) Review the boiler history including: operating conditions, date of last inspection, current inspection certificate, ASME stamping on boiler, National Board registration number, history of repairs and modifications. Review boiler logs, water test reports, and reports on tests performed on the burner controls and interlocks.

2) Assess the external parts of the boilers and boiler accessories and piping and valves for safety, accessibility, proper maintenance and operation, cleanliness, and compliance with codes.

3) Inspect for evidence of leakage of combustion gases or fluids, externally and internally, including all gaskets.

4) Inspect foundations for signs of stress such as cracking or movement.

5) Inspect boilers externally and internally for defects including bulges, blisters, cracks, wasted or eroded material, warping, general corrosion, grooving and pitting, damaged insulation.

6) Inspect all accessible internal surfaces for waterside and fireside deposits, including scaling, sediment, debris, carbon deposits.

7) Examine all stays and stayed plates.

8) Inspect gas side baffles.

9) Inspect internal drum surfaces and steam separating internals.

10) Inspect soot blowers and verify proper alignment.

11) Inspect tubes, tube ends and tube alignment. Check for sagging tubes.

12) Verify that all nozzles of internal piping such as feedwater admission and bottom blowoff collection are clear with no obstructions.

13) Inspect seating surfaces of manways and handholes.

14) Check that boiler structure is plumb and level with no excessive deformations.

15) Check for missing items such as bolts and nuts.

16) Examine all valve and pipe connections to the pressure vessel.

17) Inspect refractory including burner throat, expansion joint, bull ring, furnace seals, furnace walls and floor.

18) Verify proper alignment of burner assembly.

19) Inspect furnace for evidence of flame impingement.

20) Test operation of water level gage glass.

21) Perform mechanical and electrical inspection of disassembled low water cutouts (disassembly by VA). After reinstallation, test operation to the extent possible. Test low water cutouts on hot boilers by lowering water level gradually.

22) Verify that steam pressure gage is properly calibrated.

23) Test operation of high steam pressure cutouts on hot boilers by raising steam pressure.

24) Inspect safety valve installations and verify that the valves have proper capacity and set pressure and valves, drains and vents are properly installed. Verify that valve locking seals are not broken. On boilers that are hot, perform an operation test under pressure to confirm operation at proper set pressures. Operate boiler with burner at high fire to verify adequate steam flow capacity of the safety valves (“accumulation test”).

25) Inspect piping connected to the boilers for evidence of leakage, provision for expansion, provision of adequate support, proper alignment, evidence of detrimental conditions.

26) Inspect piping to the water column, low water cutoffs and alarms, gage glass. Verify that interior of piping is clear of obstructions.

27) Inspect valves on boiler feedwater, blowdown, drain and steam systems.

28) Provide recommendations for non-destructive testing when the inspections indicate that this is necessary to assure continued safety and reliability under current operating conditions.

7. Boiler Plant Inspection, Testing and Calibration requirements:

A. Technicians shall provide all tools and labor necessary to perform inspection, tuning, testing, calibrating, and adjustments of burners and boiler and boiler plant controls as specified below. This shall be done every six months in accordance with a schedule provided by VAMC. VAMC may extend the schedule for burners in limited service.

B. Instrumentation, monitoring and data management systems as listed below shall be calibrated every six months.

C. Provide at least two weeks notice to the Contracting Officer’s Representative (COR) prior to performing the work. Work cannot be scheduled during heavy steam load periods. Only one boiler at a time can be out of service for the inspection, testing and calibration procedures. Work must be conducted when the COR or his/her designate is available on site to monitor the work.

The COR is:

D. VAMC will have the boilers that are to be serviced prepared for the technicians upon their scheduled arrival. This includes having the boilers clean of soot and loose scale; fully warmed and at normal steam pressure; steam exhaust silencer system operable; all boiler, burner and fuel train pressure gages and thermometers calibrated; fuel meters in accurate operation (pressure/temperature correction factors provided, if applicable); boiler steam flow, stack temperature and flue gas oxygen instruments operating.

E. VAMC will comply with any other requirements of the test personnel that are considered reasonable by VAMC and have been presented in writing at least two weeks prior to the scheduled testing.

F. The inspections, testing and calibrations shall comply with:

1) The recommendations and requirements of VHA Boiler Plant Safety Devices Testing Manual, 5th Edition.

2) The written recommendations of the equipment manufacturers.

3) The requirements and recommendations of NFPA 85 Boiler and Combustion Systems Hazards Code including applicable appendices.

4) Burner performance requirements in this document.

G. A summary of the work is as follows:

1) Review boiler plant log sheets and alarm and trouble reports.

2) Review records that show combustion performance (flue gas oxygen and carbon monoxide).

3) Perform overall visual inspection of systems. Verify that systems comply with referenced codes and VAMC requirements stated in this contract.

4) Test and record the operation and set points of all burner/boiler safety interlock devices. Refer to list below. Verify that the set points and operating points are within approximately 20% of normal operating parameters. Make adjustments as necessary and record the new settings. The operation of a device must result in burner shutdown and/or proper alarm operation.

5) Verify accuracy of instrumentation listed below. Verify that all devices are properly selected for the application in terms of type, size, set point range, performance, code approval. Calibrate all instruments that are not within manufacturer’s specifications for accuracy.

6) Immediately inform COR of any recommended repairs or modifications.

H. All of interlocks and safety devices to be inspected and tested on each boiler/burner/equipment, are contained in the VHA Boiler Plant Safety Devices Testing Manual, 5th Edition, along with testing procedures.

I. List of instrumentation and controls to be inspected and calibrated:

1) Steam flow transmitters (all).

2) Steam flow recorders/computer readout.

3) Flue gas oxygen sampling, analyzing and recorder/computer readout.

Page 1 of Page 1 of

4) Boiler and economizer stack temperature transmitters and recorder/computer readout.

5) Master steam pressure and combustion controllers.

6) Boiler outlet draft controllers.

7) Boiler water level controllers.

8) Feedwater deaerator and condensate storage tank water level controllers including overflow.

9) All boiler plant safety devices which require testing in the VHA Boiler Plant Safety Devices Testing Manual, 5th Edition.

8. Safety Device Testing Report Requirements:

A. Provide complete written report of the inspection fully describing all tests performed, all findings, and recommendations. The report shall have two sections the first section will be in a table form that with four columns:

a. The first column labeled “FUNCTION” did the device pass or fail.

b. The second column labeled “Device” list the device number and description in accordance with the VHA Boiler Plant Safety Devices Testing Manual, 3rd Edition.

c. The third labeled “Deficiencies-Recommendations”

d. The fourth column labeled “corrective actions” list any corrective actions taken during the inspection.

The next section shall be in paragraph/bulleted form and list each device individual in accordance to the VHA Boiler Plant Safety Devices Testing Manual, 5th Edition. Plus the section must reference the correct Master Specification and Standard Detail for that device. See sample below.

5.1. Condensate Storage Tank High Water Alarm

Purpose: High water level may be an indication of condensate transfer pump failure that could lead to low water condition in the feedwater deaerator and in the boilers. There may be a failure of make-up water controls.

Recommended set point: 4 inches below overflow level and 2/3 of tank height. Potential hazards due to failure of high water alarm: Feedwater deaerator running dry and, consequently, boiler feed pumps running dry will cause overheating and damage to pumps and potential for plant shut down. Failure of make-up water controls (in open position) could lead to significant cost from waste of water and condensate from the tank overflow if this occurs over a long time period.

Recommended type of device: Conductivity probe type switch. Float type switches have high failure rate in this application where they are exposed to flash steam that causes seals to harden and prevent float movement.

VA Master Specification section: 23 50 11 (old 15625). www.va.gov/facmgt/standard/ VA Standard Detail: SD232111-05.pdf www.va.gov/facmgt/standard/ Failure rate of float types: 48% (BEI study of VA boiler plants).

Make and Model: Mercoid Float Did it function properly: No Category & Action Time Limit: Upon Failure or Within 5 Years

Page 1 of Page 1 of Comments: Float type switches are not allowed for high water alarms. The VA recommended switch type is a conductivity probe type switch. Install the VA recommended switch and set to alarm at 2/3 of the tank height. There are valves that can isolate this alarm. These valves must be made lockable only in the operating position.

B. Furnish report within one week of each facility inspection in “Microsoft Word” format by email to the COR and to the VA Headquarters office designated.

C. All safety-related deficiencies shall be immediately reported to the COR, during the inspection visit.

9. Boiler Inspection Report Requirements:

1. Provide complete written report fully describing all inspections and tests performed, findings, and recommendations. The condition of all items inspected shall be stated whether acceptable or deficient. All deficiencies shall be fully described along with recommendations for methods of correction. Utilize National Board Forms NB-6 and NB- 7, or other similar forms acceptable to owner.

2. Provide sketches and photographs as necessary and as requested by owner to show areas identified as not acceptable for continued service or requiring repair.

3. Include test data and calculations. Show locations and extent of all non-destructive testing by sketches.

4. Furnish report within one week of each facility inspection in “Microsoft Word” format by email to the COR and to the VA Headquarters office designated in the attachment.

5. All safety-related deficiencies shall be immediately reported to the COR during the inspection visit.

6. Provide recommendations on need for re-inspections after correction of deficiencies. Cost of re-inspections shall be extra cost negotiated with VA Contracting Officer.

10. Boiler Plant inspection and Safety Device Testing Location:

John J. Pershing VA Medical Center 1500 North Westwood Blvd. Building #7 Poplar Bluff, MO 63901

(573) 778-4704

COR:

Equipment serviced:

Boiler#1: Kewannee Classic Boiler Corporation MBH: 300 Horsepower MWSP 200 psi Low pressure converter.

Boiler#2: Kewannee Classic Boiler Corporation MBH: 300 Horsepower MWSP 200 psi Low pressure converted Boiler#3: Hurst boiler Low pressure 250 Horsepower Boiler #4 High Pressure-AMSCO Powerpack Electric Steam Boiler Model# CH10-861-500 Serial# 25447 National Board# 17070 Boiler #5 High Pressure-AMSCO Powerpack Electric Steam Boiler Model# CH10-861-500 Serial# 32961 National Board# 4484 Deaerator Condensate Tank Performance Period: The contractor shall complete the work required under this Scope of Work (SOW) within 14 days of the notice to proceed.

Hours of Operations Business hours for the VAMC follow:

· Administrative hours: Monday through Friday, 8:00 a.m. ‐ 4:30 p.m.

· National Holidays: The 10 holidays observed by the Federal Government are:

· New Year’s Day

· Martin Luther King’s Birthday

· Presidents Day

· Memorial Day

· Independence Day

· Labor Day

· Columbus Day

· Veterans Day

· Thanksgiving

· Christmas Any other day specifically declared by the President of the United States to be a national Holiday.

· Off‐Duty hours: Friday through Monday, 4:30 p.m. ‐ 8:00 a.m.; Monday through Thursday, 4:30 pm – 8:00 am.

Identification, Parking, Smoking, and VA Regulations

1. Contractor’s personnel shall wear visible identification at all times while on the premises of the VA. Identification shall include, as a minimum, the employee’s name, position, and the contractor’s trade name.

2. It is the responsibility of the contractor to park in the appropriate designated parking areas. Information on parking is available from VA Police Service. VA will not invalidate or make reimbursement for parking violations of the contractor under any conditions.

3. Possession of weapons is prohibited. Enclosed containers, including tool kits, shall be subject to search. Violations of VA regulations may result in citation answerable in the United States (Federal) District Court, not local district, state, or municipal court.

4. Smoking is prohibited on all VA property.

5. Possession of weapons is prohibited. Enclosed containers, including tool kits, shall be subject to search. Violations of VA regulations may result in citation answerable in the United States(Federal) District Court, not a local district, state or municipal court.

6. Facility security requirements. Upon arrival at the VA Medical Center all contractor personnel are required to report to the VA Medical Center Police for a temporary ID and check in. This check‐in process is mandatory. When the service is completed all contractor personnel are required to check out with VA Medical Center Police.

Page 1 of Page 1 of

SECTION C - CONTRACT CLAUSES

C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL ITEMS (OCT 2018)

(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights—

(1) Within a reasonable time after the defect was discovered or should have been discovered; and

(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.

(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.

(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.

(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at FAR 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.

(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.

(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.

(g) Invoice.

(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include—

(i) Name and address of the Contractor;

(ii) Invoice date and number;

(iii) Contract number, line item number and, if applicable, the order number;

(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;

(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;

(vi) Terms of any discount for prompt payment offered;

(vii) Name and address of official to whom payment is to be sent;

(viii) Name, title, and phone number of person to notify in event of defective invoice; and

(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.

(x) Electronic funds transfer (EFT) banking information.

(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.

(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer—System for Award Management, or 52.232-34, Payment by Electronic Funds Transfer—Other Than System for Award Management), or applicable agency procedures.

(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.

(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C. 3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR part 1315.

(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.

(i) Payment.—

(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.

(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR part 1315.

(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-5(b) for the appropriate EFT clause.

(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.

(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall—

(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the—

(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);

(B) Affected contract number and delivery order number, if applicable;

(C) Affected line item or subline item, if applicable; and

(D) Contractor point of contact.

(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.

(6) Interest.

(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.

(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.

(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if—

(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;

(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or

(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).

(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.

(v) Amounts shall be due at the earliest of the following dates:

(A) The date fixed under this contract.

(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.

(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on—

(A) The date on which the designated office receives payment from the Contractor;

(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or

(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.

(vii) The interest charge made under this clause may be reduced under the procedures prescribed in 32.608-2 of the Federal Acquisition Regulation in effect on the date of this contract.

(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:

(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or

(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.

(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.

(l) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.

(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.

(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.

(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.

(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.

(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.

(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C. chapter 87, Kickbacks; 41 U.S.C. 4712 and 10 U.S.C. 2409 relating to whistleblower protections; 49 U.S.C. 40118, Fly American; and 41 U.S.C. chapter 21 relating to procurement integrity.

(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:

(1) The schedule of supplies/services.

(2) The Assignments, Disputes, Payments, Invoice, Other Compliances, Compliance with Laws Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause;

(3) The clause at 52.212-5.

(4) Addenda to this solicitation or contract, including any license agreements for computer software.

(5) Solicitation provisions if this is a solicitation.

(6) Other paragraphs of this clause.

(7) The Standard Form 1449.

(8) Other documents, exhibits, and attachments

(9) The specification.

(t) [Reserved]

(u) Unauthorized Obligations.

(1) Except as stated in paragraph (u)(2) of this clause, when any supply or service acquired under this contract is subject to any End User License Agreement (EULA), Terms of Service (TOS), or similar legal instrument or agreement, that includes any clause requiring the Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti-Deficiency Act violation (31 U.S.C. 1341), the following shall govern:

(i) Any such clause is unenforceable against the Government.

(ii) Neither the Government nor any Government authorized end user shall be deemed to have agreed to such clause by virtue of it appearing in the EULA, TOS, or similar legal instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an “I agree” click box or other comparable mechanism (e.g., “click-wrap” or “browse-wrap” agreements), execution does not bind the Government or any Government authorized end user to such clause.

(iii) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.

(2) Paragraph (u)(1) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.

(v) Incorporation by reference. The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.

(End of Clause) ADDENDUM to FAR 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL ITEMS Clauses that are incorporated by reference (by Citation Number, Title, and Date), have the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available.

The following clauses are incorporated into 52.212-4 as an addendum to this contract:

C.2 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/

(End of Clause)

FAR Number
Title
Date
52.217-8
OPTION TO EXTEND SERVICES
NOV 1999

C.3 52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000)

(a) The Government may extend the term of this contract by written notice to the Contractor within 30 days; provided that the Government gives the Contractor a preliminary written notice of its intent to extend at least 60 days before the contract expires. The preliminary notice does not commit the Government to an extension.

(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.

(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed five (5) years.

(End of Clause)

FAR Number
Title
Date
52.227-14
RIGHTS IN DATA—GENERAL
MAY 2014

C.4 SUPPLEMENTAL INSURANCE REQUIREMENTS

In accordance with FAR 28.307-2 and FAR 52.228-5, the following minimum coverage shall apply to this contract:

(a) Workers' compensation and employers liability: Contractors are required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 is required, except in States with exclusive or monopolistic funds that do not permit workers' compensation to be written by private carriers.

(b) General Liability: $500,000.00 per occurrences.

(c) Automobile…