36C25519R0100-004.docx
DOCX document 14 KB Posted
- Solicitation number
- 36C25519R0100
About this file
36C25519R0100 36C25519R0100_2.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25519R0100-005.pdf | ||
| 36C25519R0100-003.pdf | ||
| 36C25519R0100-001.docx | DOCX document | |
| 36C25519R0100-002.pdf | ||
| 36C25519R0100-000.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FedBizOpps Amendment to a Previous Combined Solicitation
CLASSIFICATION CODE
SUBJECT
CONTRACTING OFFICE'S
ZIP-CODE
SOLICITATION NUMBER
BASE NOTICE TYPE
RESPONSE DATE (MM-DD-YYYY)
ARCHIVE
DAYS AFTER THE RESPONSE DATE
RECOVERY ACT FUNDS
SET-ASIDE
NAICS CODE
CONTRACTING OFFICE
ADDRESS
POINT OF CONTACT
(POC Information Automatically Filled from User Profile Unless Entered)
DESCRIPTION
See Attachment
AGENCY'S URL
URL DESCRIPTION
AGENCY CONTACT'S EMAIL
ADDRESS
EMAIL DESCRIPTION
ADDRESS
POSTAL CODE
COUNTRY
ADDITIONAL INFORMATION
GENERAL INFORMATION
PLACE OF PERFORMANCE
* = Required Field FedBizOpps Amendment to a Previous Combined Solicitation Rev. March 2010 Z
657A4-17-901 REPLACE LIFE SAFETY GENERATOR (VA-19-00066349)
ANSWERS TO QUESTIONS RECIEVED AND PRE-BID SIGN- IN
66048 36C25519R0100 08-02-2019 N 238210 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway Leavenworth KS 66048 michael.bottary@va.gov See attached document: Sign in Pre-Proposal Conference, PB Replace 518kVA Life Safety Generator.
PRE-BID QUESTIONS FOR PROJECT 657A4-17-901 REPLACE LIFE SAFETY GENERATOR
1. Please confirm the General Contractor is to provide the commissioning agent and NOT the VA.
The Contractor Provides Commissioning, see Cx specification section.
1. Can the Superintendent act as the QC and SSHO?
No, the SSHO and Superintendent shall be separate individuals. The SSHO can act as QC; the Superintendent cannot act as QC.
1. Please provide drawings and details for the pre-engineered metal buildings.
This is manufacturer specific and the plans detail a general space/functional requirement. The Metal Enclosed Switchgear will have to be ordered through the submittal process. There are no detailed drawings as variations exist between manufacturers.
1. Please provide the site visit sign-in sheet.
CO shall provide
1. What is the size of the diesel tank?
The generator manufacturer shall size the tank for required sizing to facilitate fuel storage for run times of 96+ hours. The tank is dependent of fuel burn rate of the generator. The tank shall be sized per NFPA 99, 101, 110.
1. How old is the fuel in the tank?
The fuel is not stagnant; we regularly operate the generator. The fuel shall be retuned (filtered transferred) to the VA. We keep a minimum quantity to support required run times.
1. Has the fuel been treated yearly for summer and winter?
No, the diesel is not treated.