FedBizOpps Amendment to a Previous Combined Solicitation

CLASSIFICATION CODE

SUBJECT

CONTRACTING OFFICE'S

ZIP-CODE

SOLICITATION NUMBER

BASE NOTICE TYPE

RESPONSE DATE (MM-DD-YYYY)

ARCHIVE

DAYS AFTER THE RESPONSE DATE

RECOVERY ACT FUNDS

SET-ASIDE

NAICS CODE

CONTRACTING OFFICE

ADDRESS

POINT OF CONTACT

(POC Information Automatically Filled from User Profile Unless Entered)

DESCRIPTION

See Attachment

AGENCY'S URL

URL DESCRIPTION

AGENCY CONTACT'S EMAIL

ADDRESS

EMAIL DESCRIPTION

ADDRESS

POSTAL CODE

COUNTRY

ADDITIONAL INFORMATION

GENERAL INFORMATION

PLACE OF PERFORMANCE

* = Required Field FedBizOpps Amendment to a Previous Combined Solicitation Rev. March 2010 Z

657A4-17-901 REPLACE LIFE SAFETY GENERATOR (VA-19-00066349)

ANSWERS TO QUESTIONS RECIEVED AND PRE-BID SIGN- IN

66048 36C25519R0100 08-02-2019 N 238210 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway Leavenworth KS 66048 michael.bottary@va.gov See attached document: Sign in Pre-Proposal Conference, PB Replace 518kVA Life Safety Generator.

PRE-BID QUESTIONS FOR PROJECT 657A4-17-901 REPLACE LIFE SAFETY GENERATOR

1. Please confirm the General Contractor is to provide the commissioning agent and NOT the VA.

The Contractor Provides Commissioning, see Cx specification section.

1. Can the Superintendent act as the QC and SSHO?

No, the SSHO and Superintendent shall be separate individuals. The SSHO can act as QC; the Superintendent cannot act as QC.

1. Please provide drawings and details for the pre-engineered metal buildings.

This is manufacturer specific and the plans detail a general space/functional requirement. The Metal Enclosed Switchgear will have to be ordered through the submittal process. There are no detailed drawings as variations exist between manufacturers.

1. Please provide the site visit sign-in sheet.

CO shall provide

1. What is the size of the diesel tank?

The generator manufacturer shall size the tank for required sizing to facilitate fuel storage for run times of 96+ hours. The tank is dependent of fuel burn rate of the generator. The tank shall be sized per NFPA 99, 101, 110.

1. How old is the fuel in the tank?

The fuel is not stagnant; we regularly operate the generator. The fuel shall be retuned (filtered transferred) to the VA. We keep a minimum quantity to support required run times.

1. Has the fuel been treated yearly for summer and winter?

No, the diesel is not treated.