36C25518Q9624-0001000.docx
DOCX document 29 KB Posted
- Solicitation number
- 36C25518Q9624
About this file
36C25518Q9624 0001 36C25518Q9624 0001.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| -15452.docx | DOCX document | |
| -15451.docx | DOCX document | |
| 36C25518Q9624-0001001.pdf | ||
| 36C25518Q9624-001.docx | DOCX document | |
| 36C25518Q9624-000.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2.
AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE
OF PAGES
10A. MODIFICATION OF
CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV.
11/2016) is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:
Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITE M 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR
43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes r eference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS
ENTERED INTO
PURSUANT TO AUTHORITY OF:
D. OTHER
BY
Contractor
16C. DATE SIGNED
14.
DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME
AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS
OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 09-19-2018 Amended RFQ 589-18-2-1311-0001 None 36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway Leavenworth KS 66048 36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway Leavenworth KS 66048 To all Offerors/Bidders
36C25518Q9624 09-19-2018
X X X
TBD
X The purpose of this amendment to the solicitation is to;
1) Post questions and answers to the original solicitation
2) Extend the response date from 09/20/18 @ 10:00 am (est) to 09/21/18 @ 4:00 pm (est)
3) Add second Site Visit: Not Mandator y - Scheduled for 2:30 pm 09-19-18 @ Valor Building, Room V3-625
Zaritz, Larry
RFQ 36C25518Q9624
Questions and Answers
1) Medium/Large sterilizer area
· Can you provide the distance to an air supply that is dry filtered, oil less and would supply 50 – 90 PSIG?
· ANSWER: There is a system up on the 4th floor about 100’ away that they can connect to.
· Can you please confirm number of transferable chamber racks required?
· ANSWER: For Medium we do not need the racks or carts. Only need the removeable shelves.
· Can you please confirm number of exterior loading an transport cars required?
· 2 transferable chamber racks and 2 exterior loading and transport carts currently in department
· ANSWER: As written in SOR, for Large Sterilizer need 4 transport Cars and 4 transferable chamber Racks
2) Steam Sterilizer/Small area
· Area determined to be extremely space restrained not allowing for installation of 2 sterilizers, let alone 1 sterilizer due to the inability to load and unload the sterilizer and also no ability to service sterilizer(s)
· ANSWER: Requirement reduced to 1 sterilizer, with no transportation cars.
· No available space to utilize with transferable chamber racks with exterior loading and transport car (as per spec)
· ANSWER: See above
· Can we respond with interior rack and 2 shelves?
· ANSWER: Yes
· Water feed in RFP states ¾”, appeared to be ½” onsite.
· ANSWER: Water line above ceiling is shown as 1”, otherwise the locker room 15’ away has larger lines.
· Can you provide distance to get to a ¾” water feed for each sterilizer?
· ANSWER: As stated above, 15’ in locker room
· Steam Line onsite is ½”
· ANSWER: ½” steam feed line is shown as 2” above the ceiling
· Can you provide distance to get to a ¾” steam line for each sterilizer?
3) Washer/Disinfector Area
· Can you please confirm number of 3 Level Manifold Racks required?
· ANSWER: 3 for each Washer
· Can you please confirm number of docking transfer carts required?
· ANSWER: 2ea, 1 for each side
4) First, with the request for turnkey I need clarification as to what should be included in our quote.
· ANSWER: Needs to include removal and disposal of existing equipment, delivery and installation of new equipment to include operational testing after installed. In addition; operational and clinical training of staff and servicing and repair for BioMed.
5) Should existing steam traps be re-installed or quote new steam traps?
· ANSWER: New Steam Traps
6) 2ea/team sterilizer, small
· ANSWER: Changed to 1ea.
7) *2 each shelf transferable chamber racks with exterior loading and transport car
· ANSWER: As stated above
8) Room we saw where planned for installation only has 1 drain and no water, steam or 208v 3 phase.
· ANSWER:
· 208v 3phase available
· 1 drain as only one sterilizer being purchased and water is available
10) Can you please confirm if we are to quote running the electrical? Steam lines? Water lines? and drains? And any other requirements for turn key?
· ANSWER: Yes, those listed and any other needed
11) Can you please confirm rack and non-removable shelves are acceptable as a transport car is not available with 16” units? And will not fit in the space requested to install?
· Small Sterilizer: We do not need the racks or carts. Only need the removeable shelves.
12) 2/EA Steam Sterilizer, Medium/Large
· ANSWER:
· 2ea Large
· 1ea Medium/small
14) Can you please confirm if our quote should include running electrical? And any other requirements for Turn Key?
· Yes, those listed and any other needed
15) Trade-in and removal of current units (Steris Eagles 2/ea) Can you please confirm we should also dispose of the units?
· ANSWER: Yes
16) Biomedical engineering technical training, Can you please confirm OEM Biomedical engineering technical training should be offered at the facility? Or at our training center?
· ANSWER: Either
17) Can you please confirm if turnkey work outside of the SPD can be done during normal weekday working hours?
· ANSWER: Yes-Depending on workflow and infection control requirements (Night/day etc.)
18) Can you please confirm if the we should quote and install all infection control barriers?
· ANSWER: Yes
19) Can you please confirm if the tile with camera in hallway path from dock need to be moved due to height of equipment that it will be done by the facility?
· ANSWER: Yes
See attached document: Questions - Answers to RFQ.