This is a Statement of Work for emergent repairs to water towers at the VA Illiana Health Care System facility located at 1900 East Main Street, Danville, Illinois 61832.
The project (550-26-121) encompasses repair and upgrade work on two water towers: North Water Tower 71 and South Water Tower 94. For North Water Tower 71, the contractor must provide all labor, material, supplies, equipment, management, and supervision to upgrade and repair the tower per plans and specifications, with ground restoration to original conditions upon completion. For South Water Tower 94, the base bid includes 17 specific tasks: installing a thermometer; replacing the manway with a 24" riser manway including davit arm and confined space entry signage; installing a screen on the overflow pipe; removing and securing co/ax cable from the ladder; adjusting windage rods to withstand 100 mph winds; installing four cable-type ladder safety devices at various locations; installing two OSHA-compliant interior access ladders with standoffs every 10 feet and cable safety devices; cleaning and calibrating the liquid level indicator; installing a compliant safety grill over the riser opening; performing interior abrasive blasting and epoxy coating to achieve 8-10 mils dry film thickness; drilling additional weep holes on the balcony floor; installing two warning signs on the fence; and conducting water quality testing. Work must comply with NFPA 22-2018, AWWA D100-21, and OSHA standards. The period of performance is 135 calendar days from issuance of Notice to Proceed. Prior to work commencement, contractors must coordinate with VAIHCS Facility Management Service, with primary contact Ryan Nesbitt at (217) 274-5059 and alternate contact Andrew Butts at (447) 792-8493. A pre-bid inspection will be conducted. Certification, accreditation, and security accreditation requirements do not apply.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VA Illiana Health Care System October 20, 2026 Facility Management Service
Butts
STATEMENT OF WORK
Project Number: 550-26-121
Project Name: Emergent Repairs North Water Tower 71
SCOPE OF WORK – NORTH WATER TOWER 71
The contractor shall provide all labor, material, supplies, equipment, management, supervision, and all other resources to upgrade and repair the north water tower in accordance with plans and specifications. The south water tower work is included below under individual tasks for the base bid in accordance with the specifications. Ground is to be returned to original conditions after tasks are complete. Work location is on the campus of the Veterans Affairs Illiana Healthcare System (VAIHCS) located at 1900 East Main Street, Danville, Il 61832. A pre-bid inspection will be conducted to allow bidders to inspect existing conditions and bring questions to the attention of VA prior to bid submission.
Prior to work commencing, direct coordination with Veterans Affairs Illiana Health Care System (VAIHCS) Facility Management Service is required. Primary point of contact is Ryan Nesbitt at (217) 274-5059 and alternate point of contact is Andrew Butts at (447) 792-8493.
NOTE: The Certification and Accreditation requirements do not apply, and a Security Accreditation Package is not required.
SCOPE OF WORK – SOUTH WATER TOWER 94
A. BASE BID – The Contractor shall provide all labor, material, supplies, equipment, management, supervision, and all other resources, to perform the following Tasks in accordance with the accompanying plans and specifications. The south water tower tasks are listed below.
Task #1: Thermometer: Install a thermometer on the outside of the tank to allow proper monitoring of the water temperature, PER NFPA 22-2018; 16.1.1 and NFPA 22-2018; 16.1.9.1.
Task #2: Manway: Replace current manway 12” x 18” with a 24” riser manway. Install davit arm on riser manway and post Confined Space Entry sign, PER AWWA D100-21; 5.4.4: Steel riser manhole and OSHA 1910.146(c)(2) Confined spaces. Paint new manway to match the water tower. New manway should be lockable.
Task #3: Overflow Pipe: Install a new screen on existing overflow pipe elbow, PER AWWA D100-21; 5.3: Overflow.
Task #4: Co/ax cable: Remove co/ax cable from the ladder and secure it, with standoffs, to the tank leg to eliminate the climbing hazard.
VA Illiana Health Care System October 20, 2026 Facility Management Service
Butts
Task #5: Windage Rods: Adjust windage rods, as needed, to withstand 100 mph winds blowing from any direction, PER AWWA D100-21; 3.1.4 Wind load.
Task #6: Ladder Safety Device #1: Install a cable type ladder safety device for the primary interior bowl access ladder.
Task #7: Ladder Installation: Install an OSHA compliant interior bowl access ladder complete with standoffs ever 10’ on center, and a cable type ladder safety device at the secondary shell manway.
Task #8: Liquid Level Indicator: Clean and lubricate all moving parts on the liquid level indicator, then adjust and calibrate the unit.
Task #9: Ladder Safety Device #2: Install a new cable type ladder safety device for the external roof access ladder.
Task #10: Replace Ladder: Install an OSHA compliant interior access ladder complete with standoffs every 10’ on center, and a cable type ladder safety device at the primary roof hatch.
Task #11: Ladder Safety Device #3: Install a cable type ladder safety device at secondary interior access ladder.
Task #12: Safety Grill: Install a compliant safety grill, designed for fall protection, over the riser opening to bring the tank in compliance, PER AWWA D100-21; 5.1.1: Safety grill and
OSHA 1910.28.
Task #13: Ladder Safety Device #4: Install a new cable type ladder safety device for the interior riser access ladder.
Task #14: Interior Coating: Abrasive blast all rusted and abraded interior areas to SSPC-SP10 and brush blast all remaining interior areas to SSPC-SP7; then apply one spot coat of epoxy primer to all areas blasted to #10, Strip coating at all weld seams, and apply an epoxy liner to the entire tank, to achieve 8 to 10 mils of total dry film thickness. Total mil thickness will include a combination of the existing and new coating.
Task #15: Balcony Floor: Drill additional weep holes on both sides of balcony floor sufficient to eliminate ponding of water.
Task #16: Signage: Install 2 signs on fence. The two signs posted shall be “Warning, Tampering with This Facility is a Federal Offense” and “No Trespassing”.
Task #17: Water Test: Water is to be tested after above tasks are completed to ensure water is safe for human consumption.
Period of Performance shall be 135 Calendar Days after issuance of Notice to Proceed.