This is Amendment 0001 to Request for Quote (RFQ) 36C25226Q0557 issued by the Department of Veterans Affairs, Great Lakes Acquisition Center - HC (Milwaukee, Wisconsin). The amendment provides answers to vendor questions and schedules a mandatory site visit for the Air Handling Units (AHU) refurbishment project at Jesse Brown VA Medical Center in Chicago, Illinois.

The site visit is scheduled for Monday, July 13, 2026, at 10:00 AM local time at Jesse Brown VA Medical Center, 820 S Damen Avenue, Chicago, Illinois 60612, where Contracting Officer Representative Manuel Alvarado will meet interested parties in the lobby. The Government emphasizes that attendance is strongly suggested and expected, and vendor absence at the site visit does not constitute grounds for claims after contract award. In response to six RFQ questions, the Government clarified that detailed technical specifications regarding AHU dimensions, square footage, equipment lists, drawings, and interior photographs are not currently available and will not be obtained prior to quote submission; vendors are directed to attend the site visit for this information. The Government also indicated willingness to consider UV-C coil/air handler/airstream irradiation as an optional enhancement or supplemental component if fully explained in submitted quotes, though it stated unfamiliarity with this method. All other terms and conditions of the original solicitation remain unchanged.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

None

0001 07-09-2026

537-26-2-6112-0218

Department of Veterans Affairs 36C252 115 South 84th Street, Suite 101

Milwaukee WI 53214-1476

Department of Veterans Affairs 36C252 Great Lakes Acquisition Center - HC 115 South 84th Street, Suite 101 Milwaukee WI 53214-1476

To all Offerors/Bidders

36C25226Q0557

X

X X

537-3660162-6112-850100-2543 010050100

X 1

The purpose of this amendment is to provide answers to RFQs received and include site visit information.

Ashley Johnson Contracting Officer

CONTINUATION PAGE

Site Visit Information

A. SITE VISIT:

A site visit has been scheduled for this requirement. It is strongly suggested and expected that interested vendors inspect the campus to be serviced to fully understand the nature of the work and the conditions under which the work is to be performed. In no case shall a contractor’s absence at a site visit to inspect the campus constitute grounds for a claim after contract award.

THE SITE VISIT IS SCHEDULED FOR MONDAY, JULY 13, 2026, AT 10:00 AM LOCAL TIME.

COR MANUEL ALVARADO WILL MEET ALL INTERESTED PARTIES IN THE LOBBY OF THE

JESSE BROWN VA MEDICAL CENTER, 820 S DAMEN AVENUE, CHICAGO, ILLINOIS 60612.

RFQ Questions

1. Could the Government provide the dimensions (length, width, and height) of each of the 11 Air Handling Units?

No, that information is not currently available, and the Jesse Brown VA Medical Center (JBVAMC) will be unable to obtain that information prior to when quotes are due. It is strongly recommended that potential vendors attend the site visit.

2. Is there a schedule, drawing, or equipment list showing the dimensions or approximate square footage of each AHU?

No, that information is not currently available, and JBVAMC will be unable to obtain that information prior to when quotes are due. It is strongly recommended that potential vendors attend the site visit.

3. Are there any photographs of the interior of the Air Handling Units that can be shared?

Pictures of the interior of the Air Handling Units are not available, and JBVAMC will be unable to obtain any pictures prior to when quotes are due. It is strongly recommended that potential vendors attend the site visit.

4. Can the Government provide the approximate surface area (square feet) that will require epoxy, fire barrier, antimicrobial coating, and coil refurbishment?

No, that information is not currently available, and JBVAMC will be unable to obtain that information prior to when quotes are due. It is strongly recommended that potential vendors attend the site visit.

5. Will a site visit be scheduled, or can interested contractors coordinate a site visit prior to submitting a quote?

A site visit is scheduled for Monday, July 13, 2026. See above for full details.

6. Would the VA consider UV-C coil/air handler/airstream irradiation as an optional enhancement, additive line item, or supplemental component within the AHU refurbishment scope, if proposed by a qualified mechanical contractor or teaming partner?

JBVAMC is not familiar with the method suggested. This method may be considered so long as it is fully explained in a quote submitted in response to the Solicitation.