36C25223Q0767 0001.docx
DOCX document 26 KB Posted
- Attached to
- N059--FIBER-OPTIC OUTSIDE PLANT INSTALLATION
- Solicitation number
- 36C25223Q0767
About this file
This document contains an amendment to a solicitation for a fiber-optic outside plant installation project. The amendment extends the quote due date to August 4, 2023 and provides responses to vendor questions to clarify requirements. The project involves installing new fiber between buildings 1017 and 237 at a Department of Veterans Affairs facility. The amendment provides guidance on trenching, restoration requirements, inner duct and conduit needs, fiber routing and mounting, slack requirements, manhole access and safety protocols. The solicitation number is 36C25223Q0767 and is being conducted by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 12. Vendors must acknowledge receipt of the amendment by the new due date to be considered for the award.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| P01 - FIBER OPTIC PLANT DRAWING 0001.pdf | ||
| 36C25223Q0767.docx | DOCX document | |
| P07 - Lake County WD 2015-4935 (Rev 21) dated 12-27-2022.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7.
ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF
PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE
OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERE
D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED
STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF
CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF
SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) None Department of Veterans Affairs
GLAC
(69D) 115 South 84th Street, Suite 101 Milwaukee WI 53214-1476 Department of Veterans Affairs
GLAC-MILWAUKEE (69D)
Great Lakes Acquisition Center - HC 115 South 84th Street, Suite 101 Milwaukee WI 53214-1476 To all Offerors/Bidders
36C25223Q0767
X X Quote Due Date extended to 13:00 8/4/23 Amendment to solicitation 36C25223Q0767 to extend due date for offers to 13:00 on 8/4/2023, as well as to provide facility responses to received questions and requests for clarifications.
See Attachment 1 for specific questions and corresponding answ ers/clarifications.
Richard Ruffin Contracting Officer
CONTINUATION PAGE
ATTACHMENT 1
Questions & Answers/Clarifications Vendor Question = Q, FHCC Response = R Q. L30/C30 to C30A requires an open trench can you please provide the depth of the trench, the acceptable material needed to backfill and the sealing of inner duct in the manhole wall.
R. The Contractor will conduct survey and submit recommendations/options in bid as required.
Q. Will there be any restoration required after the open trench is complete?
R. Depending on the ground disrupted, i.e. soil, grass, concrete, etc.., must be replaced.
Q. Does the fiber need to be coiled in each manhole and if so, how many feet?
R. Not required.
Q. How will the 10’ coils on the end to end be mounted in buildings 1017 and 237?
R. Coils can be ‘J-hook’ mounted on the wall, or if available, coils can be mounted/placed in over-head ceiling.
Q. Is there existing inner duct available in each manhole? If so, is the inner duct roped?
R. No. Expect to procure necessary inner-duct.
Q. Are there available ducts to install the inner duct in each manhole?
R. Yes, via the existing fiber-optic routes.
Q. Will the old fiber between 1017 to 237 needed to be removed?
R. No. Removal of existing fiber is not required.
Q. If the route of the fiber from C34 to 237 doesn't follow route entering the building into the IT room, will we be able to provide a new route?
R. Yes. If after conducting survey, and the existing route does not support the new fiber, proposal can include ‘options’ or alternative solutions.
Q. Can the fiber be run in the ceilings in buildings 237 and 1017?
R. Yes. Mounted with appropriate conduit to support.
Q. Is there a purposed fiber route inside buildings 1017 and 237?
R. The fiber is only planned for the outside plant, from demark to demark.
Q. How will the fiber be mounted in the manholes and inside the buildings?
R. Mounted and marked/flagged, as appropriate.
Q. Will the fiber need to be labeled in each manhole, cable tray, and rack mount?
R. Yes.
Q. At the fiber consolidation points will be splicing into any other existing fiber or just the run from 1017 to 237?
R. No. Fiber from 1017 to 237. Fiber should not be consolidated/spliced with any other runs.
Q. If we are splicing into existing fiber who assumes responsibility on the testing of existing fiber runs?
R. No splicing required.
Q. If the manholes are full of water is there a process or procedure needed to take to pump the water?
R. Yes. A work-permit/authorization is required by NAVFAC, to enter and conduct any work in manholes.
Q. What is present in the existing manholes (for example electrical and communication cables)?
R. The Contractor, will be required to conduct a survey and submit a work-permit to NAVFAC, which will validate each man-hole used for routing the fiber.
Q. Is there any Maintenance on the fiber once installed?
R. No follow-on maintenance required.
Q. How much fiber slack or service length is needed in each IT room.
R. 10’
Q. Do all ducts have a pull rope and/or inner duct?
· If not, should this be included in the pricing or assume all duct is good with a rope?
· If we should include inner-ducts, can you provide the size of number of inner-ducts required?
R. No. Pricing for inner-duct should be included, number and size in accordance with SOW.
Q. Are all the manholes’ communications only or is there electric in the manholes as well?
· Some of the lids say electric and some say communications.
R. The Contractor, will be required to conduct a survey and submit a work-permit to NAVFAC, which will validate each man-hole used for routing the fiber.
Q. At building 237, it is unclear where the pipe penetrates the wall to bring the fiber into the building. Can you clarify that?
R. There is a crawl-space, where the fiber inters the facility. Upon conducting survey, site PM, will show location.
Q. At manhole C30 and L30, plan calls for 12’ of trench. Can you confirm that is indeed needed and should be included in the bid?
R. The Contractor, will be required to conduct a survey and provide options/alternative solutions. If required, it should be indicated in the bid, or as an optional CLIN.
Q. At building 1017, under the IT rooms is the crawl space considered a “confined space” for safety/OSHA requirements?
R. Yes. A work-permit must be submitted to NAVFAC for authorization to perform work in these locations.
File details come from the government source that posted it. Updated .