S05 RFIs Response for 550-21-105.pdf

PDF 113 KB Posted

Attached to
Z1DA--Construct Parking Lot Street Lighting Project 550-21-105 CON IFB
Solicitation number
36C25223B0006
Issued by

About this file

This document contains responses to requests for information (RFIs) regarding Solicitation Number 36C25223B0006 from the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 12. The solicitation is for Project 550-21-105 to construct a parking lot and street lighting at a General Health area. The RFI responses clarify that the quality control manager requires only sufficient construction experience, confirm the need to remove 3.5-6.5 feet of material and place up to 5.5 feet of structural fill, recommend replacing existing small trees that may not survive being moved with new white oak trees, and state that the prime contractor's superintendent can fulfill the duties of site safety and health officer with OSHA 30-hour training.

View the file

Other files

File Type Posted
36C25223B0006 0002.docx DOCX document
S06 GeoTech Report 550 21 105.pdf PDF
Wage Detremination January 06 2023.pdf PDF
Wage Determination 12 29 2022.pdf PDF
36C25223B0006 0001.docx DOCX document
Wage Determination 11_28_2022.pdf PDF
550-21-105 SOW Synopsis.pdf PDF
550-21-105 Bid Drawings.pdf PDF
Pre-Construction Checklist.pdf PDF
550-21-105 100pct BD Specifications including COVID-19.pdf PDF
36C25223B0006_1.docx DOCX document
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

12/27/2022

Dahal

Project 550-21-105 Construct Parking Lot and Street Lighting GH Area CON

Solicitation 36C25223B0006

Requests for Information (RFIs)

Reference: 014500 Quality Control; 3.4 Quality Control Organization

Question: The reference spec section requires a CQC Manager to be a graduate engineer, or a graduate of construction management, with a minimum of 3 years construction experience on construction similar to the scope of this contract. Please confirm the education requirements for the CQC Manager for this contract. Or would a CQC Manager with only sufficient construction experience be acceptable for the project?

Response: Required a fulltime Superintendent Who can fulfill contractor site safety and health officer (SSHO) requirements and will need to have the OSHA 30-hour training. Yes, CQC Manager with only sufficient construction experience be acceptable for the project.

Question: In the plans on page CS502 it shows us removing approximately 3.5 – 6.5 feet of material to place up to 5.5’ of structural fill which I assume is clay. Just wanted to make sure that is what is wanted because that is a lot of clay we would need to bring in for the project.

Response: Yes, based on drawing and page CS502 under Asphalt Pavement Section, it does require approximately 3.5 – 6.5 feet of material to place up to 5.5’ of structural fill. Follow drawing and specification for detail clarification.

Question: Regarding the removal and resetting of 3 small trees on site. Because of the size of these trees, I would recommend removal and putting in 3 new trees because there is no way we would guarantee survival of these trees after they have been moved.

Response: This are only 2-3 years old trees. Use tree spades or work with tree companies to re-use the same trees.

Question: If we did provide 3 new trees, what trees would be wanted for replacement?

Response: In worst case scenario if the existing tree dies than the new replacement tree should white oak trees.

Reference: 013526 Safety Requirements; 1.7 SSHO

Question:

The reference spec requires a project Site Safety and Health Officer to be a separate qualified individual from the prime contractors site superintendent and/or quality control manager with duties only as the SSHO. Please confirm this requirement. Or, can the prime contractor superintendent and/or quality

12/27/2022

Dahal control manager fulfil the SSHO duties on this project?

Answer:

One full time Superintendent can fulfill contractor site safety and health officer (SSHO) requirements and will need to have the OSHA 30-hour training.