36C25223B0003.docx
DOCX document 29 KB Posted
- Solicitation number
- 36C25223B0003
About this file
This sources sought notice requests information from small businesses interested in performing construction work replacing chillers at the Oscar G. Johnson VA Medical Center in Iron Mountain, Michigan. The project scope includes replacing three existing 250-ton chillers, upgrading the building automation system, and removing a heat recovery chiller. The construction value is estimated between $2-5 million. Responses are requested from SDVOSBs, VOSBs, WOSBs, 8(a), HUBZone, and small businesses. Interested sources must submit company information, descriptions of relevant past projects, teaming plans including details on 50% minimum SDVOSB subcontracting, and bonding capacity by October 26, 2022. The notice indicates this is not a request for proposal but a market research effort to determine acquisition approach.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sources Sought Notice Sources Sought Notice
| SUBJECT* |
| 585-21-116 Replace Chiller Plant Phase 2 (Construction) at the Oscar G. Johnson VA Medical Center Iron Mountain, MI |
GENERAL INFORMATION
| CONTRACTING OFFICE’S ZIP CODE* |
| 53214-1476 |
| SOLICITATION NUMBER* |
| 36C25223B0003 |
| RESPONSE DATE/TIME/ZONE |
| 10-26-2022 16:30 CENTRAL TIME, CHICAGO, USA |
| ARCHIVE |
| 7 DAYS AFTER THE RESPONSE DATE |
| RECOVERY ACT FUNDS |
| N |
SET-ASIDE
| PRODUCT SERVICE CODE* |
| Z1DZ |
| NAICS CODE* |
| 238220 |
| CONTRACTING OFFICE ADDRESS |
| Department of Veterans Affairs |
Great Lakes Acquisition Center (GLAC) 115 S 84th Street, Suite 101
Milwaukee WI 53214-1476
POINT OF CONTACT*
Contracting Officer Kristi Kluck Kristi.Kluck3@va.gov
PLACE OF PERFORMANCE
| ADDRESS |
| Oscar G. Johnson VA Medical Center |
Department of Veterans Affairs
325 East H Street
Iron Mountain MI
| POSTAL CODE |
| 49801-4760 |
| COUNTRY |
| USA |
ADDITIONAL INFORMATION
AGENCY’S URL
URL DESCRIPTION
AGENCY CONTACT’S EMAIL ADDRESS
EMAIL DESCRIPTION
DESCRIPTION
THIS IS A SOURCES SOUGHT NOTICE ONLY
| Solicitation: | 36C25223B0003 |
| Project: | 585-21-116 Replace Chiller Plant – Phase 2 |
| Place of Performance: | Oscar G. Johnson VA Medical Center | |
| 325 East H. Street | ||
| Iron Mountain, MI 49801-4760 |
PART 1 - General Description:
The purpose of this notice is to obtain information on the interests, capabilities, and qualifications of multiple types of small business firms to determine if a set-aside is appropriate. Responses to this Sources Sought announcement will be used by the Government to make appropriate acquisition decisions. Proposals are NOT being requested or accepted at this time.
The Department of Veterans Affairs, Great Lakes Acquisition Center, requests letters of interest, with detailed construction background, from the following types of specialized construction small businesses firms interested in performing construction work at the Oscar G. Johnson VA Medical Center:
· Service-Disabled Veteran Owned Small Businesses (SDVOSB),
· Veteran Owned Small Businesses (VOSB),
· Women Owned Small Businesses (WOSB),
· 8(a) Businesses,
· HUBZone Businesses, and
· Small Businesses (SB)
This project is classified under NAICS Code: 238220 Plumbing, Heating and Air Conditioning with a small-business size limit of $16.5 Million.
Should the contract be set-aside for CVE-verified SBVOSBs, in accordance with VAAR 852.219-10(d)(4) (4), in the case of a contract for specialized construction, it [the prime contractor] will NOT pay more than 50% of the amount paid by the government to it to firms that not VIP-listed SDVSOBs.
(5) Any work that a VIP-listed SDVSOB subcontractor further subcontracts will count towards the percent of subcontract amount that cannot be exceeded. For supply or construction contracts, cost of materials is excluded and not considered to be subcontracted.
Ref: https://www.va.gov/oal/docs/business/pps/deviationVaar20190718.pdf
The magnitude of construction for this work is between $2,000,000 and $5,000,000.
PART 2 - SCOPE OF WORK OVERVIEW:
585-21-116 Replace Chiller Plant – Phase 2 will replace three (3) of the existing 250-ton chillers to account for future cooling demand and N+1 redundancy plus design a chiller sized for spring/fall operation with the ability to run in low ambient air temperature conditions. Phase 2 will also include eliminating electrical panel X-Chill and refeeding all circuits from Building 11. In addition, the Building Automation System will be upgraded on the chillers to allow for more reliable alarm reporting, allow chillers to control pump operation to reduce winter nuisance alarms, connect existing AHU Belimo Energy Valves to our network and program each valve, and upgrade plant to a Variable Primary Flow System. Lastly, the facility intends to remove the heat recovery chiller in the subbasement including all piping, pumps, and electrical. The 4” HW piping connecting the chiller to the heat exchanger in 6122A shall be capped and abandon in place.
PART 3 - PERIOD OF PERFORMANCE:
Complete all work including submittals, reviews, quality assurance, and closeout no later than 300 calendar-days from the Notice to Proceed (NTP) as shown below. Contractor must plan accordingly to maintain the contractual period of performance. This schedule includes submittals, submittal reviews, material lead-time, installation, testing and balancing, punchlist inspections/ corrective action, training and standard closeout.
| ACTIVITY |
| DURATION (CALENDAR DAYS) |
| Completion Date (Approximate) |
| Award |
| 0 |
| 1/25/2023 |
| Kick-Off Meeting/NTP |
| 14 |
| 2/8/2023 |
| Submittals (Schedule, QC, Safety, ICRA, Product Data, Shop Drawings, Schedule of Values, etc.) |
| 45 |
| 3/25/2023 |
| VA Submittal Reviews |
| 21 |
| 4/15/2023 |
| Mobilization |
| 1 |
| 4/16/2023 |
| Site Work (including mobilization, installations, shut-downs, testing, inspections, commissioning, training, punchlist/corrections and demobilization) |
| 219 |
| 11/21/202 |
| Administrative Closeout |
| 14 |
| 12/5/2023 |
| TOTAL DURATION = 300 MAX |
| 300 |
| 12/5/2023 |
*** Some Actions occur simultaneously
PART 4 - Interested sources shall submit the following:
1. Company name, address, point of contact, phone number, SAM OID number, and business status.
2. Indicate the primary nature of your business, any teaming agreements or arrangements, planned self- performance and subcontracting program. Include specific details as to how SDVOSBs will fulfill the 50%.
3. Documentation relating to capability of performance. Provide two (2) examples of projects similar in scope, complexity, and cost magnitude of project description above.
4. Letter from the surety regarding the maximum bonding capability for a single contract action as well as the total aggregate bonding capacity.
Total submittal shall be no longer than (6) six pages in one .pdf file or word document.
Responses are required to be sent via email to Kristi.Kluck3@va.gov no later than Wednesday, October 26, 2022 CST.
THIS IS NOT A REQUEST FOR PROPOSALS. It is a market research tool being utilized to determine the availability of potential qualified contractors before determining the method of acquisition. In addition, this Sources Sought is not to be construed as a commitment by the government, nor will the government pay for any information solicited or delivered.
| *= Required Field |
| Sources Sought Notice |
Sources Sought Notice
File details come from the government source that posted it. Updated .