36C25219Q0327-0001000.docx

DOCX document 28 KB Posted

Attached to
Services to Abandon 10, 000 Gallon Underground Storage Tank-in-Place
Solicitation number
36C25219Q0327
Issued by

About this file

36C25219Q0327 0001 36C25219Q0327 0001.docx

View the file

Other files

File Type Posted
36C25219Q0327-001.docx DOCX document
36C25219Q0327-000.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION

OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:

Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADM

INISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and d ate specified.

C. THIS SUPPLEMENTAL AGREEMENT IS

ENTERED INTO

PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 3

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO

MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) none 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S. 84th Street, Suite 101 Milwaukee WI 53214-1476 36C252 Department of Veterans Affairs

GLAC-NORTH CHICAGO IL

3001 Green Bay Road Building 1, Room 326 North Chicago IL 60064-3048 To all Offerors/Bidders

36C25219Q0327 02-20-2019

X X

X Reference solicitation 36C25219Q0327 for removal of diesel fuel from Underground Storage Tank (UST), and fill abandoned tank at Jesse Brown VAMC in Chicago, IL. THe purpose of this amendment is to provide answers to questions asked. Due date for offers remains 10:00am EST on 28 February 2019. End of Amendment.

DONALD ST. ONGE

Contracting Officer

QUESTIONS & ANSWERS RELATED TO 36C25219Q0327:

1. Bid SOW; to fill tank in place. Will there be an alternate bid process for tank removal?

ANSWER: State of Illinois OSFM PERMIT Abandon in place is necessary. An alternate bid to remove the tank is not required at this time.

2. Will JBVAMC provide a schedule for trailer occupation of space?

ANSWER: YES, BUT IT IS RECOMMENDED THAT WORK SHOULD NOT OBSTRUCT THE REMOVAL OF TRAILER.

3. What is the fuel amount to be removed, was fuel maintained, what is fuel quality?

ANSWER: 8435-GALLLONS; FUEL TREATED ANNUALLY; FUEL RATING A-3; LAST TREATED 9/9/ 2018

4. Will demolition be possible when the PET SCAN/MRI is treating patients?

ANSWER: A risk assessment for noise will have to be completed prior to any demolition starting. Options such as saw cutting should be considered. AIR HAMMERING WILL INTERFERE WITH PATIENT TREATMENTS AND IS NOT RECOMMENDED.

5. Will a schedule for work (DATES AND TIMES) be provided with the JBVAMC?

ANSWER: YES, work will be scheduled and approved by the Chief of Engineering so not to interfere with Hospital Business or delay work.

6. Will safety barriers be required for all phases of demolition/construction?

ANSWER: Yes, Safety barriers will be required as described in the OSHA standards.

7. Will a steel plate need to be required to permit the removal of PET SCAN/MRI TRAILERS?

ANSWER: YES. Steel plate must be rated to 40-ton capacity when open trench exists or hazards exist until resurfacing of excavation with 8” of 4000 PSI fiber reinforced concrete.

8. Are current and accurate site utility drawings available to bidders?

ANSWER: No new drawings where created for this project.

9. Will vibrations due to hammering or saw concrete impact the mobile MRI or any other hospital equipment?

ANSWER: A risk assessment for noise will have to be completed prior to any demolition starting. Options such as saw cutting concrete should be considered. AIR HAMMERING WILL INTERFERE WITH PATIENT TREATMENTS AND IS NOT RECOMMENDED.

10. Can you please provide a schedule for when the medical trailer will need to be moved in and out of the work area?

ANSWER: YES, work will be scheduled and approved by the Chief of Engineering so not to interfere with Hospital Business or delay work.

11. Do all UST openings on the concrete surface need to be removed and concrete patched? Typically, on abandonments like this; we just use one of the openings, saw cut a 3’ x 3’ square, hand dig to the top of tank, open, clean, fill, and patch concrete all from same opening. There is no reason per OSFM guidelines to remove the other openings in the concrete.

ANSWER: OSFM compliance is required. Demolition and construction will be scheduled and plan to perform Demolition will be reviewed and approved by the Chief of Engineering. All demolition and resurfacing should be planned and bid so as to not damage the least amount existing pavement and utilities beneath pavement.

File details come from the government source that posted it.