FAX to Infection Control x22481 and to Safety x25613 or scan & attach via e-mail to “Hines Infection Control Service”
Infection Control Risk Assessment for Construction / Renovation Projects Project Name: Restore Paved Surfaces at Hines Project/ Work-Order Number: 578-19-029 Project Planner or Technician: Ernie Wright Extension: 708-202-8387 ext. 21147 Building Number: Hines Campus Floor(s)/Room(s): Roads, Sidewalks, and Storm Sewers Start date: September 15, 2019 Projected completion date: September 15, 2020
Construction Activity Infection control risk group X TYPE A: Non-invasive activity, low noise, no vibration
DUST LEVEL Low X GROUP 1: Low office areas, FMS areas, all non-patient care areas.
TYPE B: Small scale, short duration, low-moderate noise, low-moderate vibration DUST LEVEL: Moderate to High
GROUP 2: Medium All other patient care areas including general medicine floors, ultrasound, Rehab, Occupational Therapy.
TYPE C: Requires more than one work shift to complete, low-moderate noise, moderate–high vibration DUST LEVEL Moderate to High
GROUP 3: Medium/High ED, Radiology/MRI, admissions, food service areas, laboratories.
TYPE D: Major demolition and construction activities Requiring consecutive work shifts, moderate-high noise, moderate-high vibration DUST LEVEL High
GROUP 4: Highest Operating rooms, SPS, ICU’s, Outpatient areas, oncology, anesthesia, post anesthetic recovery, all endoscope areas, Pharmacy, Renal Dialysis
Project Class Determination Matrix Construction Activity
Risk Level
Type “A”
Type “B”
Type “C”
Type “D”
Group 1 I II II III Group 2 I II III IV Group 3 I III III IV Group 4 III IV IV IV
Contractors Actions by Project Class
CLASS
I
1. Execute work by methods to minimize raising dust from construction operations.
2. Immediately replace any ceiling tile displaced for visual inspection.
3. Contain construction waste before transport in tightly-covered containers.
4. Emergency Preparedness training/posting/ID card.
CLASS
II
1. Provide active means to prevent air-borne dust from dispersing into atmosphere.
2. Water mist work surfaces to control dust while cutting.
3. Seal unused doors with duct tap
4. Block off and seal air vents.
5. Wipe surfaces with disinfectant.
6. Contain construction waste before transport in tightly-covered containers.
7. Emergency Preparedness training/posting/ID card.
CLASS
III
1. Isolate HVAC system in area where work is being done to prevent contamination of the duct system.
2. Complete all critical barriers before any work begins.
3. Maintain negative air pressure within work area utilizing
HEPA-equipped air filtration units.
4. Provide dust mat at entrance and exit of work area.
5. Contain construction waste before transport in tightly-covered containers.
6. Wet mop or vacuum with HEPA-filtered vacuum before leaving work area.
7. Cover transport receptacles or carts. Tape covering.
8. Emergency Preparedness training/posting/ID card.
CLASS
IV
1. Isolate HVAC system in area where work is being done to prevent contamination of the duct system.
2. Complete all critical barriers before any work begins.
3. Maintain negative air pressure within work area utilizing
HEPA-equipped air filtration units.
4. Provide adhesive walk-off mat at entrance and exit of work area.
5. Seal holes, pipes, conduits and punctures appropriately.
6. Vacuum the entire work area with HEPA vacuums or wet mop with disinfectant at the completion of project.
7. Do not remove barriers from work area until completed project is thoroughly cleaned by housekeeping and inspected by the Infection Control Department, Safety Section, and Engineering Service.
8. Remove barrier materials carefully to minimize spreading dust and debris associated with construction.
9. Contain construction waste before transport in tightly-covered containers.
10. Cover transport receptacles or carts. Tape covering.
11. Remove isolation of HVAC system in areas where work was performed at the end of the project.
12. Emergency Preparedness training/posting/ID card.
Risk Assessment for TB exposure: Does the project involve the building’s: a) HVAC Yes No X ; b) HEPA filters Yes No_X_ ;
c) Negative Pressure Room (s) Yes No X ? If any checked yes, an N95 mask will be required.
Classification: I Contractor’s signature (for Projects only)
Project Planner or Technician Signature: __________________________
Supervisor signature: _________________________________________ Date: June 27, 2019
| Infection Control Risk Assessment for Construction / Renovation Projects |
| Infection control risk group |
| Project Class Determination Matrix |
| Construction Activity ( |
| Risk Level ( |
| Group 1 |
| I |
| Group 4 |
| Contractors Actions by Project Class |
| CLASS |
| CLASS |
| CLASS |
| CLASS |
| Construction Activity |
| Risk Assessment for TB exposure: Does the project involve the building’s: a) HVAC Yes No X ; b) HEPA filters Yes No_X_ ; c) Negative Pressure Room (s) Yes No X ? If any checked yes, an N95 mask will be required. ... |
| Classification: I Contractor’s signature (for Projects only) |
| Project Planner or Technician Signature: __________________________ |
| Supervisor signature: _________________________________________ Date: June 27, 2019 |
| 2019-06-27T07:34:58-0500 | |
| LAWRENCE P DOYLE 233105 |
| 2019-06-27T10:51:34-0500 | |
| ERNEST G. WRIGHT 1107358 |
File details come from the government source that posted it.