36C25218Q0643-00002001.docx

DOCX document 14 KB Posted

Attached to
Parking Garage Maintenance Service (Base Year)
Solicitation number
36C25218Q0643
Issued by

About this file

36C25218Q0643 00002 amendment answers 02.docx

View the file

Other files

File Type Posted
36C25218Q0643-00002000.docx DOCX document
36C25218Q0643-00001000.docx DOCX document
36C25218Q0643-002.pdf PDF
36C25218Q0643-001.docx DOCX document
36C25218Q0643-000.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. 3rd possible structure being built? No

1. Fire hydrate/water hook-ups available within/near parking structures? Yes there are water hook-ups and hydrants at both ramps

1. Will the “slab on grey” need cleaning as well, or just the pre-cast? Everything

1. What’s the square footage surface area for the 2nd parking structure? One is 80k the other is 123k

1. What year was the garage built? One in 2016 one in 2017 (completion dates)

1. Is more than one facility involved? Is more than 80,000 sq. ft. involved? This is only for the Milwaukee VA and the SF is 80k and 123k

1. Will the garage be power swept by the owner prior to the deck washing or is that the contractors responsibility? No, the power cleaning should take care of anything on the parking ramp

1. Is the garage post tension or precast? Precast

1. Are there drains and a water source in the garage, if not is there a hydrant near- by? There are drains and water sources for each parking ramp as well as a hydrant near each of them