36C25218B1094_A00003.docx
DOCX document 19 KB Posted
- Attached to
- Upgrade 4 East In-Patient Rooms Construction Project 585-17-107 At the Oscar G Johnson VA Medical Center
- Solicitation number
- 36C25218B1094
About this file
36C25218B1094 A00003 36C25218B1094 A00003.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25218B1094_A00004.docx | DOCX document | |
| 36C25218B1094-A00002000.docx | DOCX document | |
| 36C25218B1094-A00001001.pdf | ||
| 36C25218B1094-A00001000.docx | DOCX document | |
| 36C25218B1094-002.pdf | ||
| 36C25218B1094-001.docx | DOCX document | |
| 36C25218B1094-003.pdf | ||
| 36C25218B1094-000.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SF30 Continuation Page
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) A00003 12-10-2018 585-19-1-6985-0005 585-17-107 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S 84th Street, Suite 101 Milwaukee
WI
53214-1476 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S 84th Street, Suite 101 Milwaukee
WI
53214-1476 To all Offerors/Bidders
36C25218B1094 12-10-2018
X X X
X
Amendment A00003 - Contractor Questions and the Answers/Responses
Please see the attached for additional details
Anne Vossler Contracting Officer Solicitation: 36C25218B1094 Project: Upgrade 4-East Inpatient Rooms Construction Project #: 585-17-107 At the Oscar G Johnson VA Medical Center, Iron Mountain, MI 49801 A00003 – Contractor Solicitation Questions and the Responses
Question: Most of the time at the VA we use either G60 or G90 for our Galvanized coating on our metal studs, But the spec does say G40. Just making sure that is the correct galvanized coating you want to use.
Answer: Use the VA standard spec G40.
Question: On Sheet A101A Note 7 shows new 2.5” foil faced ridged insulation and 3 5/8” metal stud wall. Will the new wall be the entire length from one arrow to the other or just 2 small sections? And will they be demoing the existing wall completely in order to access the existing exterior wall to install the new wall?
Answer: The intent is to insulate the exterior wall while it is exposed to during renovation of the bathrooms. The insulation should be added in the area between the arrows. As noted on the drawings existing insulation/conditions should be evaluated with owner/architect once initial demo is complete.
Question: Sheet A101A - In each MED/SURG rooms (i.e. 4250,4251,4245), there is a dashed box with no key note referencing it. Looks like possibly A new wall please advise?
Answer: The dashed box being referenced is the existing headwall. Reference typical enlarged plan details for confirmation.
Question: For the Foil faced 2.5” ridged insulation against exterior wall do they a specific ridged Material they would like to use, also what kind of sealant?
Answer: Please refer to specification section 072113 Thermal Insulation for the type of rigid insulation to be used. Sealant should be approved by the insulation manufacturer for use with their product and in compliance with 079200 Joint Sealants.
*** Contractor is required to acknowledge all amendments in Block 19 on the 2nd page of the SF-1442 prior to the date and time set for the Bid Opening.