This is a solicitation (36C25025Q0238) issued by the VA Network Contracting Office 10 for replacing damaged hot water supply and return lines in room C-2099A at the Richard L. Roudebush VA Medical Center in Indianapolis, IN. The project requires replacing approximately 40 linear feet of 1-1/4" black welded hot water piping, asbestos abatement of approximately 20 linear feet of pipe insulation, installation of new valves on supply and return lines, and new pipe insulation.

The solicitation is set aside for Service-Disabled Veteran-Owned Small Businesses with a magnitude of construction between $25,000-$100,000. The period of performance is 45 days from Notice to Proceed, with work to be performed during weekend hours (6 AM to 5 PM). Quotes are due by March 25, 2025 at 4:30 PM EDT and must be submitted via email to samuel.galbreath@va.gov. The contractor must provide a phase plan within 5 days of award and a site-specific safety plan within 10 days. A NAICS code of 237110 applies with a size standard of $45M. Site visits are available upon request. The VA will consider material and equipment stored off-site for progress payments under certain conditions.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER

7. ISSUED BY CODE 8. ADDRESS OFFER TO

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014) STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within ____________ calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES NO

a. Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________

(hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b. An offer guarantee is, is not required.

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

1 68

36C25025Q0238

X

02-20-2025

583-25-3-650-0018

583-25-518

Department of Veterans Affairs Network Contracting Office (NCO) 10 260 E. University Avenue Cincinnati OH 45219

Contract Specialist Samuel Galbreath samuel.galbreath@va.gov

Samuel Galbreath 301-456-3435

Replace Degraded Hot Water Piping Project Number: 583-25-518

All work shall be performed within C-2099A on the second level at the Richard L. Roudebush VA Medical Center (RLR VAMC) campus, located at 1481 West 10th Street, Indianapolis, IN 46202.

Period of Performance shall be 45 days following Notice to Proceed (NTP).

Email quote to samuel.galbreath@va.gov. No physical quotes will be accepted.

The Contractor shall replace damaged hot water supply and return lines in a mechanical chase within room C-2099A of the chaplain area as detailed in the Technical Requirements section, project bid drawings and documents, and VHA Master Construction Specifications. This project includes installation of new valves on both the supply and return lines, asbestos abatement for approximately 20 linear feet of pipe insulation and insulating the new hot water piping.

Please refrence PO# 583-

Site visits are available as needed. please reach out to samuel.galbreath@va.gov to schedule

0 45

X X 52.211-10

X 10

1 4:30PM EDT

03-25-2025

X

14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( ) 41 U.S.C. 3304(a) ( )

26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY

PHONE: FAX:

28. NEGOTIATED AGREEMENT 29. AWARD Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code)

(Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

(Type or print)

(4 copies unless otherwise specified)

(Type or print) (Type or print)

(Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror)

(To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

583-3650162-650-854200-3223 23NRNR000

36C250

Network Contracting Office (NCO) 10 260 E. University Avenue Cincinnati OH 45219

FMS-VA-2(101)

Financial Services Center PO Box 149971 Austin TX 78714-9971

Jeffery Hairston Contracting Officer

Table of Contents

PART I - THE SCHEDULE

SECTION A - SOLICITATION/CONTRACT FORM

A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)

A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION,

ALTERATION, OR REPAIR)– BACK

STATEMENT OF WORK

PROJECT SPECIFIC INFORMATION

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE

OF THE WORK (MAY 2014)

2.2 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE

EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION

MATERIALS (MAY 2014)

2.4 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

2.5 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB

1998)

2.6 VAAR 852.239-75 INFORMATION AND COMMUNICATION TECHNOLOGY

ACCESSIBILITY NOTICE (FEB 2023)

REPRESENTATIONS AND CERTIFICATIONS

3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2025)

3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS

AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)

3.3 52.204-29 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—

REPRESENTATION AND DISCLOSURES (DEC 2023)

GENERAL CONDITIONS

4.1 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR

INFORMATION SYSTEMS (NOV 2021)

4.2 52.204-30 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—

PROHIBITION (DEC 2023)

4.3 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

(APR 1984)

4.4 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION

(FEB 2024)

4.5 52.223-20 AEROSOLS (MAY 2024)

4.6 52.223-21 FOAMS (MAY 2024)

4.7 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)

4.8 52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (NOV 2020)

4.9 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

4.10 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022)

4.11 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)

4.12 VAAR 852.204-70 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR

PERSONNEL (MAY 2020)

4.13 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED

SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023)

(DEVIATION)

4.14 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION

CONTRACTS (WITHOUT NAS– CPM) (NOV 2018)

4.15 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV

2018)

4.16 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)

4.17 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT

ADMINISTRATION (OCT 2020)

4.18 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) ..57

4.19 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT

(SEP 2019)

4.20 IT CONTRACT SECURITY

Attachments

STATEMENT OF WORK

Replace Degraded Hot Water Piping

Project Number: 583-25-518

GENERAL PROJECT SCOPE:

The Contractor shall replace damaged hot water supply and return lines in a mechanical chase within room C-2099A of the chaplain area as detailed in the Technical Requirements section, project bid drawings and documents, and VHA Master Construction Specifications. This project includes installation of new valves on both the supply and return lines, asbestos abatement for approximately 20 linear feet of pipe insulation and insulating the new hot water piping.

Location: All work shall be performed within C-2099A on the second level at the Richard L. Roudebush VA Medical Center (RLR VAMC) campus, located at 1481 West 10th Street, Indianapolis, IN 46202.

Period of Performance: Period of Performance shall be 45 days following Notice to Proceed (NTP). All work shall be performed to minimize outages and disruption to the RLR VAMC, including phasing. Work shall be performed during normal weekend VAMC business hours, which are 6 AM to 5 PM during the weekend. The hot water supply and return system shall be returned to service in one weekend, preferably one workday.

TECHNICAL REQUIREMENTS:

A. The Contractor shall provide all necessary services (i.e., labor, materials, tools, equipment, and competent supervision) to perform all work as detailed in the project bid drawings and specifications, as well as the below to meet the scope objectives and requirements, and to provide the required outcome in terms of overall quality, timeliness, and documentation. All work performed under this project shall fully adhere to all VA Design and Master Specification criteria including energy conservation requirements, as well as relevant additional standards and criteria outlined in the Project Specifications.

The Contractor shall be responsible for field verifying existing conditions prior to bid.

The Contractor shall be responsible for obtaining and coordinating the services of all third-party subcontractors performing services on-site as part of the contract to accomplish the following:

1. The Contractor shall provide all necessary infection prevention equipment including but not limited to temporary barriers, negative air machine, and dust control matting to meet VA infection prevention requirements.

2. The Contractor shall erect a working platform within the mechanical chase to provide a safe, compliant working surface to effectively reach the material being replaced.

The Contractor shall provide two bid options for the platform:

a. (Base Bid) A temporarily erected platform constructed from either Fire Retardant Treated Wood or metal scaffolding. Temporary platform shall be removed by the contractor after the work is complete.

b. (Alternate 1) A permanently erected work platform to include grating, railing, and ladder access that does not prevent access to existing platforms.

c. Platform construction shall be approved by VA safety before work commences and approved daily by a qualified scaffolding inspector.

3. The Contractor shall perform asbestos abatement on approximately 20 linear feet of friable Asbestos Containing Material (ACM) pipe insulation installed along the damaged piping. ACM removal technique shall be glovebag abatement following all applicable local, state, federal, and VA regulations and specifications.

4. The Contractor shall use proper disposal techniques per regulatory standards and VA specifications. The VA will hire a third-party VPIH to conduct air quality monitoring and clearance testing during the abatement to ensure safe air quality levels.

5. The Contractor shall remove approximately 40 linear feet of damaged sections of 1- 1/4” black welded hot water supply and return lines within the designated mechanical chase and overhead ceiling access:

a. VA pipe shop personnel shall be responsible for system shutdown and drainage prior to piping removal. The Contractor shall be responsible for excess water containment after pipe cutting begins and thereafter.

b. Piping replacement shall be conducted during a warm day to minimize system downtime impact. Reference outside air temperature is approximately 55 °F.

ACM abatement shall be coordinated for completion before pipe replacement.

c. The Contractor shall determine the best method for connecting the new piping to the existing system risers. If the existing welded outlets or holes are not reused, they shall be capped or plugged. A certified welder shall be required for all welding work.

6. The Contractor shall install new hot water supply and return piping and fittings to replace the existing using Type K or L copper conforming to VA specified piping materials. The Contractor shall reconnect the new piping to the existing risers and branch piping, and ensure all connections are properly sealed and pressure tested to confirm the system is leak free.

7. The Contractor shall install new gate valves on both the hot water supply and return lines. Refer to the VA COR regarding valve placement after initial inspection of existing conditions. Ensure that valves are clearly labeled, accessible, and compatible with the existing hot water system.

8. The Contractor shall install inline tees with ball valves for draining both the hot water supply and return systems. Ball valves shall be installed after the branch line shut-off gate valves. Ensure down tee connector is National Pipe Thread (NPT) to Garden Hose Thread (GHT) for maintenance drain down.

9. The Contractor shall install new pipe insulation using fiberglass pipe insulation conforming to VA specified piping insulation materials.

10. Installation and components shall comply with all applicable International Building Code (IBC) standards, National Fire Protection Association (NFPA) standards, and the local Authorities Having Jurisdiction (AHJ).

11. The Contractor shall patch any rated walls, ceilings, or ceiling components disturbed during construction to the safety requirements of the UL assembly.

12. All plumbing work shall comply with all Federal Healthcare Regulations, State and Local Codes, as well as all utility company regulations.

13. The Contractor shall be responsible for complying with all requirements of working within an active Medical Center, including noise restrictions, equipment restrictions, hours restrictions, phase restrictions, infection prevention restrictions, PPE requirements, etc.

B. Prior to the start of work, the Contractor is responsible for verifying existing conditions and maintaining current conditions of the RLR VAMC during and following completion of the repairs. Responsibilities include but are not limited to:

1. The Contractor shall deliver/install equipment without interfering with the normal flow of vehicle and pedestrian traffic at the Medical Center.

2. It shall be the responsibility of the Contractor to keep the construction areas clean and the surrounding areas free from damage. If during work, surrounding areas are damaged, the Contractor will be responsible for any repairs/replacements that are required.

3. It is the responsibility of the Contractor to understand and comply with all applicable city, county, state, and federal codes, laws, ordinances, standards, rules, and regulations.

CONTRACTOR GENERAL REQUIREMENTS

C. All communication from the Contractor to the VA must be submitted and communicated through the Contracting Officer’s Representative (COR).

D. The Contractor is authorized two parking spaces on the RLR VAMC campus. All other Contractor employees or subcontractors will be required to park at the VA’s Cold Springs Road (CSR) campus located at 2669 Cold Springs Road, Indianapolis, IN 46222.

Contractor parking is authorized in the F-Lot only when directed by the COR.

E. The Contractor shall store materials and equipment only within their authorized construction site. The Contractor may be authorized (at their own expense) one 20’ temporary storage container to store materials and equipment on-site or at the CSR campus, depending on space availability. The Contractor shall request storage space for a temporary storage container from the COR. If approved, the COR will designate where the temporary storage container shall be located. Any additional storage space shall be located at the CSR campus. The VA is not responsible for any damages that may occur to the temporary storage container while on RLR VAMC property. If approved, the temporary storage container shall be:

1. Labeled including the company name, contact information, and project(s) name.

2. Painted in a single color, limited to no rust, clean, with no branding, advertisements, or graffiti.

3. Locked and located only in the space authorized by the COR.

4. Used for storage of materials and equipment for the specific project only.

5. Not used for a working space. No work shall be conducted inside or outside the temporary storage container.

6. Cleaned and maintained daily. The immediate area (10’) around the temporary storage container shall be inspected daily by the Contractor to ensure trash and debris are removed.

7. NOT used to store prohibited or illegal items, such as guns, chemicals, heaters, or materials that may require temperature control.

8. Removed within 15 days after the project closeout or the final invoice payment.

F. The Contractor shall secure all material, supplies, and equipment left on-site after working hours. All materials, tools, and equipment shall be labeled with the Contractors name and a point of contact. No materials or tools shall be left unattended outside the authorized construction site. The VA is not responsible for any theft of tools, equipment, or materials that are stored on-site or in the construction site. The following applies to materials and demolition material at the RLR VAMC:

1. All the Contractor’s materials, tools, and equipment shall be clean when transporting them through the facility. If the materials, tools, and equipment cannot be cleaned, then the Contractor shall transport them in a cleanable container or cart. Materials over 6’ long carried or hauled through the facility require a person to be in front of and behind the material or equipment ensuring the path of travel is safe.

2. The Contractor shall cover all loads of demolition material to prevent dust/debris from disrupting medical activities in the hospital. The Contractor shall be responsible for the proper disposal of all waste generated, including all items shown to be removed on the various demolition drawings. The Contractor shall provide a roll off dumpster for all applicable phases and coordinate with the COR for dumpster staging areas. The Contractor shall be responsible for the removal and relocation of the dumpster throughout the entirety of the project.

G. Upon completion of all work items, the Contractor shall conduct a walkthrough with the COR noting all punch list items. Once all punch list items are completed the final invoice will be approved.

H. The Richard L. Roudebush VAMC is an active Medical Center environment; therefore, work may be performed directly adjacent to active offices or patient care areas. The Contractor and all subcontractors shall act with professional behavior at all times, being cognizant of excessive noise and disruptions. If certain work tasks are expected to be especially disruptive, communicate with the COR for prior approval.

I. The VA is not responsible for variability in the price of goods or consumables used during demolition and construction of this project.

DELIVERABLES:

J. The Contractor shall provide the phase plan and schedule within five (5) business days from the contract award.

K. The Contractor shall submit a Site-Specific Safety Plan to the COR within ten (10) business days from the contract award. The plan must be approved by the COR before any work begins.

L. The Contractor shall submit all products for approval by the COR before beginning construction.

M. The Contractor shall submit daily logs to the COR on a weekly basis, at minimum.

N. The Contractor shall provide a two-week look-ahead to the COR on a weekly basis.

O. The Contractor shall comply with all aspects of contract specifications and submit a Request for Information (RFI) for clarification or additional information if the project documents are not clear.

P. The Contractor shall provide waste reports to the COR each month for the entire duration of the project. Refer to the Construction Waste Management Specification for instructions.

Q. The Contractor shall submit a list of all sub-contractors that will be working on the construction site.

R. The Contractor shall submit a list of all personnel planned to be onsite each week, one week in advance.

S. The Contractor shall provide a minimum fourteen (14) day notice to the COR before any utility shutdowns are required to allow for proper scheduling and notification. The Contractor shall verify all affected items due to an electrical panel shutdown and present them to the COR on the Utility Outage Permit.

T. The Contractor shall deliver a warranty and maintenance package prior to project close out. This package will include all applicable product(s) warranty information, manuals, and maintenance information for equipment installed during the project.

HEALTH AND SAFETY:

U. The Contractor shall have the responsibility for the safety of their own personnel. No physical work can begin until a Site-Specific Safety Plan is approved, governed by the Accident Prevention (FAR 52.236-13) clause. It is the responsibility of the Contractor to safeguard the public, Contractor personnel, etc. during construction. The VA will not intervene except when the safety of VA personnel or property is at risk, or imminent risk to life safety exists.

V. Provide appropriate signage, barricades, etc., as appropriate, and as directed by the COR.

The Contractor will dictate appropriate PPE for each work area and clearly indicate those requirements at all entrances to construction areas. The Contractor is to fill out and post the Construction Safety Poster with critical safety information at the main entrance door to the construction site.

W. The Contractor shall be thoroughly familiar will all rules and regulations governing safety. A 30-hour OSHA “Competent Person” shall be present for all work and all additional workers shall have a minimum of a 10-hour OSHA Certification. All “Skilled

Trades” workers including but not limited to welders, pipefitters, carpenters, electricians, etc. performing work must present a valid certification for their respective trade.

X. The Contractor shall comply with all VA regulations concerning Safety, Infection Control Requirements, Interim Life Safety Measure Requirements, Parking, Personnel Access, and proper removal/safe disposal of construction waste and debris as listed in the specifications and drawings. The Contractor shall abide by all ICRA requirements that are put into place by the VA infections prevention team. The COR shall provide requirements and forms to the Contractor.

Y. The Contractor shall perform all work in accordance with ICRA requirements, and it is the responsibility of the Contractor to keep the construction areas clean and to not damage the existing equipment. If equipment is damaged during the work, the Contractor will be responsible for any repairs/replacements that are required.

Z. The Contractor shall properly identify all chemicals with an OSHA GHS label and store them according to OSHA regulations. The Contractor shall keep all applicable OSHA GHS approved label and SDS sheets on the job site.

AA. The Contractor shall provide all necessary tools, equipment, Personal Protective Equipment (PPE), and all ICRA and safety related materials to perform the work in a safe, effective, and timely manner. The Contractor is responsible for providing digital negative air monitors for all Infection Control barriers requiring a negative air space. All tools, equipment, and PPE shall comply with the requirements of OSHA Standard 29 CFR 1910, Subpart I.

BB. The Contractor shall comply with OSHA Standard 29 CFR1926, Subpart AA for all confined space entry. A VA confined space permit shall be required prior to entry into confined spaces.

CC. The Contractor shall be responsible for insuring all their employees.

DD. The Richard L. Roudebush VAMC campus is a smoke-free facility. It is the Contractor’s responsibility to maintain compliance to this policy within the campus.

SECURITY:

EE. The Contractor, contractor personnel, and all subcontractors shall be subject to all Federal laws, regulations, standards, and VA Directives and Handbooks regarding information and information system security as delineated in this contract.

FF. The Contractor and all subcontractors shall wear a medical center badge at all times when on RLR VAMC property. General Contractor’s or subcontractor’s employees shall not enter the project site without an appropriate badge. Ensure all construction entry doors are locked at all times. Contractor personnel may be subject to inspection of their personal effects when entering or leaving the project site. Before starting work the General Contractor shall give two weeks’ notice to the COR so that security arrangements can be provided for employee badging.

GG. The Richard L. Roudebush VAMC is currently transitioning to an electronic key and coring system throughout the entire Medical Center. Most mechanical rooms have already been transitioned over to the electronic key and core system. The electronic key and coring system shall be fully implemented by the end of 2024. The Prime Contractor will be issued one electronic key once the contract has been awarded and the NTP has been issued. The Prime Contractor will only be given access to the rooms/spaces that work is required in to complete the contract. Any additional access shall be requested through the VA COR. The Contractor will be responsible for the electronic key during the entire duration of the project. The last invoice on the contract will not be paid until the electronic key is returned in good working condition to the COR. The Prime Contractor will be responsible for reimbursing the VA $125.00 if the electronic key is lost, stolen or damaged during the duration of the contract. The COR may at any time inspect the electronic key to ensure the key is in possession of the Prime Contractor. The electronic key will be required to be reprogrammed periodically to ensure updated access.

Currently the electronic key is set to be reprogrammed every four (4) days.

HH. The C&A requirements do not apply, and a Security Accreditation Package is not required.

PROJECT SPECIFIC INFORMATION

MATERIALS: Offeror materials consist of Request for Quote forms and any issued amendments which will be provided via email.

SUBMISSION REQUIREMENT:

The following documents are to be included in the proposal submission: one (1) original fully completed and signed SF 1442 Offer page, acknowledgment of all amendments either via entering data in block 19 of the SF1442 or completing blocks 15a, b, and c of the Amendment and attaching to the original SF 1442 Offer page; one (1) original completed bid schedule if one is provided, otherwise bid amounts are entered in block 17 of the SF1442 Offer page; one (1) original completed/wet ink signed SF 24 Bid Bond (if required, see block 13B) of the SF1442 Solicitation page; Offerors are responsible for ensuring and verifying their proposal and all required proposal documents are received at the email address designated in block 8 of the SF 1442 Solicitation and by the date and time specified in block 13A of the SF 1442 Solicitation (subject to amendment). Send quotation to Samuel.galbreath@va.gov. No physical quotes will be accepted

PROJECT INFORMATION

PROJECT TITLE AND NUMBER: Replace Degraded Hot Water Piping - Project Number:

583-25-518

PROJECT LOCATION: Richard L. Roudebush VA Medical Center (RLR VAMC) campus, located at 1481 West 10th Street, Indianapolis, IN 46202.

PROJECT SCOPE OF WORK: The Contractor shall replace damaged hot water supply and return lines in a mechanical chase within room C-2099A of the chaplain area as detailed in the Technical Requirements section, project bid drawings and documents, and VHA Master Construction Specifications. This project includes installation of new valves on both the supply and return lines, asbestos abatement for approximately 20 linear feet of pipe insulation, and insulating the new hot water piping.

Period of Performance shall be 45 days following Notice to Proceed (NTP). All work shall be performed to minimize outages and disruption to the RLR VAMC, including phasing. Work shall be performed during normal weekend VAMC business hours, which are 6 AM to 5 PM during the weekend. The hot water supply and return system shall be returned to service in one weekend, preferably one workday.

MAGNITUDE OF CONSTRUCTION: FAR 36.204 (a) Between $25,000 and $100,000.

TYPE CONSTRUCTION: Commercial and Institutional Building Construction

NORTH AMERICAN INDUSTRY CLASSIFICATION SYSTEM CODE: (NAICS): 237110

SMALL BUSINESS SIZE STANDARD: $45M

PERIOD OF PERFORMANCE: 45 calendar days from receipt of Notice to Proceed for Entire Project Scope.

AFFIRMATIVE ACTION GOALS AND GEOGRAPHICAL AREA (reference 52.222-23):

Goals for Minority Participation for each trade 4.4% Goals for Women Owned Business Participation for each trade: 6.9% The Geographical covered area for this solicitation (project) is Marion County, Indianapolis, IN.

LIQUIDATED DAMAGES: (__) YES or (X) NO (reference Contract Clause FAR 52.211-12)

RESTRICTION ON SUBMISSION AND USE OF EQUAL PRODUCTS: ( ) YES or (X) NO (Reference VAAR 852.236-90)

PERFORMANCE PERIOD: The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed,

(b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 45 calendar days from receipt of the Notice to Proceed for the entire project. The time stated for completion shall include final cleanup of the premises.

RESPONSIBILITY REQUIREMENTS: A responsibility check will be accomplished for the apparent awardee prior to award. Checks of the VIP database (to ensure apparently successful offeror is a verified Service Disabled Veteran Owned Small Business), System for Award Management (SAM) database, Online Representations and Certifications, and Excluded Parties List System to insure registrations are current, valid, and no debarment records exist, and Experian (to check Intelliscore Plus Score to insure it is below a risk value of 4). Any information retrieved or received by the Government that would be cause for negative or unsatisfactory responsibility rating may result in the offeror being determined ineligible for award.

WAGE DETERMINATION: IN20250002 01/17/2025

REQUESTS FOR INFORMATION (RFI): To obtain clarifications and/or additional information concerning the contract requirements, specifications and/or drawings, submit a written RFI utilizing the RFI Form attached to this Solicitation, send via email to samuel.galbreath@va.gov RFIs must be specific identifying section, paragraph and page no. of the specifications or cite the drawing number and must be in question format. All RFIs submitted shall include the solicitation number and title, contractor name, city, state, telephone, email address, date submitted, and the RFI question(s). RFI responses will be submitted via email. RFI due date is 03/14/2025, responses will be posted via amendment.

SECURITY

BACKGROUND INVESTIGATIONS: All contractor employees are subject to the same level of investigation as VA employees who have access to VA Sensitive Information. The level of background investigation is commensurate with the level of access needed to perform the statement of work. This requirement is also applicable to all subcontractor personnel requiring the same level of access.

Levels and associated types of Background Investigations:

If the project requires that workers have only limited physical access to the VA facility for a period of one year or less, a local flash badge with fingerprint check is issued.

If the project requires that workers require un-supervised, logical and/or physical access for 180 consecutive or aggregate days in a 365-day period, over a 3-year period, a background investigation is required (Special Agency Check (SAC)) which must be completed prior to being allowed access.

If the project requires that workers have un-supervised, full-time, logical, and/or physical access for more than 6 months or more than 180 aggregate days in a one-year period, a background investigation is required (Special Agency Check and National Agency Check with Written Inquiries (NACI)) and access is not allowed until a favorable SAC completion.

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO

BIDDERS/OFFERORS

2.1 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—

SECONDARY SITE OF THE WORK (MAY 2014)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.2 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO

ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION

(FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade

Goals for female participation for each trade

4.4 % 6.9 %

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action

Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is

(End of Provision)

2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—

CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

2.4 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) Site visits may be arranged during normal duty hours by contacting:

Name: Samuel Galbreath

Address: samuel.galbreath@va.gov

Telephone:

(End of Provision)

2.5 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY

REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

https://www.acquisition.gov/browse/index/far https://www.va.gov/oal/library/vaar/

FAR

Number

Title Date

52.204-7 SYSTEM FOR AWARD MANAGEMENT NOV 2024

52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE

REPORTING

AUG 2020

52.204-22 ALTERNATIVE LINE ITEM PROPOSAL JAN 2017

2.6 VAAR 852.239-75 INFORMATION AND COMMUNICATION

TECHNOLOGY ACCESSIBILITY NOTICE (FEB 2023)

(a) Any offeror responding to this solicitation must comply with established VA Information and Communication Technology (ICT) (formerly Electronic and Information (EIT)) accessibility standards. Information about Section 508 is available at http://www.section508.va.gov/.

(b) The Section 508 accessibility standards applicable to this solicitation are stated in the clause at 852.239–75, Information and Communication Technology Accessibility. In order to facilitate the Government’s determination whether proposed ICT supplies meet applicable Section 508 accessibility standards, offerors must submit appropriate VA Section 508 Checklists, in accordance with the checklist completion instructions. The purpose of the checklists is to assist VA acquisition and program officials in determining whether proposed ICT supplies, or information, documentation and services conform to applicable Section 508 accessibility standards. The checklists allow offerors or developers to self-evaluate their supplies and document—in detail—whether they conform to a specific Section 508 accessibility standard, and any underway remediation efforts addressing conformance issues.

(c) Respondents to this solicitation must identify any exception to Section 508 requirements. If an offeror claims its supplies or services meet applicable Section 508 accessibility standards, and it is later determined by the Government, i.e., after award of a contract or order, that supplies or services delivered do not conform to the described accessibility standards, remediation of the supplies or services to the level of conformance specified in the contract will be the responsibility of the Contractor at its expense.

REPRESENTATIONS AND CERTIFICATIONS

3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN

2025)

(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 237110.

(2) The small business size standard is $45 Million.

(3) The small business size standard for a concern that submits an offer, other than on a construction or service acquisition, but proposes to furnish an end item that it did not itself manufacture, process, or produce is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition—

(i) Is set aside for small business and has a value above the simplified acquisition threshold;

(ii) Uses the HUBZone price evaluation preference regardless of dollar value, unless the offeror waives the price evaluation preference; or

(iii) Is an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.

(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the provision at 52.204-7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:

[ ] (i) Paragraph (d) applies.

[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:

(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—

(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;

(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or

(C) The solicitation is for utility services for which rates are set by law or regulation.

(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.

(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation. This provision applies to all solicitations.

(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.

(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—

(A) Are not set aside for small business concerns;

(B) Exceed the simplified acquisition threshold; and

(C) Are for contracts that will be performed in the United States or its outlying areas.

(vi) 52.204-26, Covered Telecommunications Equipment or Services—Representation. This provision applies to all solicitations.

(vii) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations— Representation.

(viii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.

(ix) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.

(x) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.

(xi) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.

(xii) 52.219-1, Small Business Program Representations (Basic, Alternates I, and II). This provision applies to solicitations when the contract is for supplies to be delivered or services to be performed in the United States or its outlying areas, or when the contracting officer has applied part 19 in accordance with 19.000(b)(1)(ii).

(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.

(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.

(C) The provision with its Alternate II applies to solicitations that will result in a multiple-award contract with more than one NAICS code assigned.

(xiii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract is for supplies to be delivered or services to be performed in the United States or its outlying areas, or when the contracting officer has applied part 19 in accordance with 19.000(b)(1)(ii).

(xiv) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.

(xv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.

(xvi) 52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial products or commercial services.

(xvii) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of biobased products in USDA-designated product categories; or include the clause at 52.223-2, Reporting of Biobased Products Under Service and Construction Contracts.

(xviii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA-designated items.

(xix) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals— Representation. This provision applies to solicitations that include the provision at 52.204-7.

(xx) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.

(xxi) 52.225-4, Buy American—Free Trade…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .