36C25027Q0041.pdf

PDF 894 KB Posted

Attached to
6350--Upgrade Building Automation System
Solicitation number
36C25027Q0041
Issued by

About this file

Solicitation/Contract Summary

This is a Solicitation/Contract/Order for Commercial Products and Commercial Services (Standard Form 1449) issued by the Department of Veterans Affairs for the upgrade of a Building Automation System at the Richard L. Roudebush VA Medical Center in Indianapolis, Indiana. The solicitation number is 36C25027Q0041, issued on November 27, 2026, with an offer due date of January 5, 2027, at 10:00 AM EST. The contract is set aside 100 percent for Service-Disabled Veteran-Owned Small Business (SDVOSB) concerns eligible under the SDVOSB Program, with NAICS code 334513 and a size standard of 750 employees.

The statement of work requires the contractor to replace 39 Johnson Controls Facility Explorer FX90 supervisory controllers, replace six BAS workstations, and consolidate the existing building automation system onto a newer onsite Niagara N4 server. All work must be completed within 365 calendar days after contract award, including testing, correction of deficiencies, and final documentation. The contractor must provide equipment, software licenses, one year of manufacturer software maintenance, programming, integration, commissioning, documentation, and project management within a firm-fixed price. Key deliverables include a phased project schedule within 30 days of award, controller-by-controller bills of materials before ordering, verification of existing conditions and cutover plans before each replacement, monthly updated schedules, and comprehensive as-built documentation including network diagrams, controller inventories, point lists, configuration files, and warranty information before final acceptance. The contractor must also comply with numerous security, personnel vetting, and safeguarding requirements, including information system security planning, personnel background investigations, and adherence to VA directives on cybersecurity and privacy protection. Payment will be made electronically upon acceptance of items and completion of services as defined in the performance schedule.

View the file

Other files

File Type Posted
36C25027Q0041_1.docx DOCX document
ATTACHMENT I -JA JOHNSON CONTROLS DEVICES.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PAGE 1 OF 1. REQUISITION NO.

2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NO. 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE

a. NAME b. TELEPHONE NO. (No Collect Calls) 8. OFFER DUE DATE/LOCAL

TIME

9. ISSUED BY CODE 10. THIS ACQUISITION IS UNRESTRICTED OR SET ASIDE: % FOR:

SMALL BUSINESS

HUBZONE SMALL

BUSINESS

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

WOMEN-OWNED SMALL BUSINESS

(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

8(A)

NAICS:

SIZE STANDARD:

11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

12. DISCOUNT TERMS

13a. THIS CONTRACT IS A

RATED ORDER UNDER

DPAS (15 CFR 700)

13b. RATING

14. METHOD OF SOLICITATION

RFQ IFB RFP

15. DELIVER TO CODE 16. ADMINISTERED BY CODE

17a. CONTRACTOR/OFFEROR CODE FACILITY CODE 18a. PAYMENT WILL BE MADE BY CODE

TELEPHONE NO. UEI: EFT:

PHONE: FAX:

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED

SEE ADDENDUM

19. 20. 21. 22. 23. 24.

ITEM NO. SCHEDULE OF SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

(Use Reverse and/or Attach Additional Sheets as Necessary)

25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Govt. Use Only)

27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA ARE ARE NOT ATTACHED.

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN _______________ 29. AWARD OF CONTRACT: REF. ___________________________________ OFFER COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DATED ________________________________. YOUR OFFER ON SOLICITATION DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY (BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED SET FORTH HEREIN IS ACCEPTED AS TO ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (TYPE OR PRINT) 31c. DATE SIGNED

AUTHORIZED FOR LOCAL REPRODUCTION (REV. NOV 2021)

PREVIOUS EDITION IS NOT USABLE Prescribed by GSA - FAR (48 CFR) 53.212

7. FOR SOLICITATION

INFORMATION CALL:

STANDARD FORM 1449

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

583-27-2-663-0001

36C25027Q0041 11-27-2026

Stacie Hill (937) 268-6511 ext 4651 01-05-2027

10:00 EST

36C250 Department of Veterans Affairs Network Contracting Office 10 3140 Governor's Place Blvd Suite 210 Kettering OH 45409-1337

X 100

X

334513

750 Employees

N/A

X

Richard L. Roudebush VAMC 1481 W. 10th Street Indianapolis, IN 46202

36C250

Department of Veterans Affairs Network Contracting Office 10 3140 Governor's Place Blvd Suite 210 Kettering OH 45409-1337

Department of Veterans Affairs Financial Services Center Invoices To Be submitted electronically https://www.tungsten-network.com

877-489-6135

Upgrade Building Automation System

See PWS for additional details.

Quotes must be received by the contract specialist, via email, at stacie.hill@va.gov, by the date/time in block 8

583-3670162-663-855100-2670 0100501X3 x X

Luke A. Turner

VA-VHA-RPOC-2024-0076

36C25027Q0041

Table of Contents

SECTION A

A.1 SF 1449 SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS

AND COMMERCIAL SERVICES

SECTION B - CONTINUATION OF SF 1449 BLOCKS

B.1 CONTRACT ADMINISTRATION DATA

B.2 PRICE/COST SCHEDULE

ITEM INFORMATION

PERFORMANCE WORK STATEMENT

SECTION C - CONTRACT CLAUSES

C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS

AND COMMERCIAL SERVICES (OCT 2025) (DEVIATION)

C.2 52.219-27 NOTICE OF SET-ASIDE FOR, OR SOLE-SOURCE AWARD TO,

SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS (SDVOSB) CONCERNS

ELIGIBLE UNDER THE SDVOSB PROGRAM (NOV 2025) (DEVIATION)

C.3 52.222-90 ADDRESSING DEI DISCRIMINATION BY FEDERAL CONTRACTORS

(DEVIATION APR 2026)

C.4 52.240-91 SECURITY PROHIBITIONS AND EXCLUSIONS (NOV 2025)

(DEVIATION)

C.5 52.240-93 BASIC SAFEGAURDING OF COVERED CONTRACTOR

INFORMATION SYSTEMS (DEVIATION) (NOV 2025)

C.6 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)

C.7 852.204-72 PERSONNEL VETTING AND CREDENTIALING (OCT 2026)

(DEVIATION)

C.8 852.219-76 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—

CERTIFICATE OF COMPLIANCE FOR SUPPLIES AND PRODUCTS (OCT 2026)

(DEVIATION)

C.9 852.222-71 COMBATING ANTI-SEMITISM (OCT 2026)(DEVIATION)

C.10 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (OCT 2026)

(DEVIATION)

C.11 852.240-71 SECURITY REQUIREMENTS FOR INFORMATION TECHNOLOGY

RESOURCES (FEB 2023)

C.12 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

SECTION D - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS

SECTION E - SOLICITATION PROVISIONS

E.1 52.212-1 INSTRUCTIONS TO OFFERORS—COMMERCIAL PRODUCTS AND

COMMERCIAL SERVICES (OCT 2025) (DEVIATION)

E.2 52.240-90 SECURITY PROHIBITIONS AND EXCLUSIONS REPRESENTATIONS

AND CERTIFICATIONS (NOV 2025) (DEVIATION)

E.3 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT

2018)

E.4 852.239-75 INFORMATION AND COMMUNICATION TECHNOLOGY

ACCESSIBILITY NOTICE (OCT 2026) (DEVIATION)

E.5 852.233-70 AGENCY PROTESTS (OCT 2026) (DEVIATION)

E.6 852.240-72 INFORMATION SYSTEM SECURITY PLAN AND

ACCREDITATION (FEB 2023)

E.7 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB

1998)

E.8 52.212-2 EVALUATION—COMMERCIAL PRODUCTS AND COMMERCIAL

SERVICES (OCT 2025) (DEVIATION)

SECTION B - CONTINUATION OF SF 1449 BLOCKS

B.1 CONTRACT ADMINISTRATION DATA

1. Contract Administration: All contract administration matters will be handled by the following individuals:

a. CONTRACTOR:

b. GOVERNMENT: Contracting Officer 36C250

Department of Veterans Affairs

Network Contracting Office 10

3140 Governor's Place Blvd

Suite 210

Kettering OH 45409-1337

2. CONTRACTOR REMITTANCE ADDRESS: All payments by the Government to the contractor will be made in accordance with:

[x] 52.232-33, Payment by Electronic Funds Transfer—System For Award Management, or

[] 52.232-36, Payment by Third Party

3. INVOICES: Invoices shall be submitted in arrears:

a. Quarterly

b. Semi-Annually

c. Other

[x] Once items have been accepted by the government and as services are completed in accordance with the performance schedule.

4. GOVERNMENT INVOICE ADDRESS: All Invoices from the contractor shall be submitted electronically in accordance with VAAR Clause 852.232-72 Electronic Submission of Payment Requests.

ACKNOWLEDGMENT OF AMENDMENTS: The offeror acknowledges receipt of amendments to the Solicitation numbered and dated as follows:

AMENDMENT NO DATE

B.2 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM

NUMBER

DESCRIPTION OF

SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

39.00 EA _______________ _______________

FX90 JACE Controllers with License and SMA

6.00 EA ________________ _______________

BMS Workstations

1.00 EA ________________ _______________

BMS Server SMA

1.00 YR ______________ _______________

Technician Labor

GRAND TOTAL _______________

PERFORMANCE WORK STATEMENT

Upgrade Building Automation System

Richard L. Roudebush VA Medical Center 1481 West 10th Street, Indianapolis, Indiana 46202

1 Purpose and scope

The contractor shall replace the 39 supervisory controllers in Attachment A with new Johnson Controls Facility Explorer FX90 controllers, replace the six BAS workstations in Attachment C, and consolidate the existing building automation system onto the newer onsite server. Include removal, installation, licenses, specified expansion modules, programming, integration, commissioning, documentation and project management in the firm-fixed price.

The facility currently operates an older Niagara AX Version 3 server and a newer Niagara N4 server on a BAS network separate from the VA/OIT network. Migrate all remaining functions from the AX server to the newer server, preserve functions already on the newer server, and demonstrate that the AX server can be retired. Controllers outside Attachment A remain in place and shall remain operational and integrated.

2 Period of performance and scheduling

Complete all work within 365 calendar days after contract award, including testing, correction of project deficiencies and final documentation. Within 30 calendar days after award, submit a phased schedule identifying submittals, material delivery, controller replacements, server migration, workstation replacements, testing and closeout. Update the schedule monthly and when a material change occurs.

Some affected systems serve critical clinical areas. Coordinate work schedules and outages with the COR and affected departments and obtain written approval of each work window before proceeding. Some work may require evenings, nights, weekends or holidays to meet facility needs and maintain operations. Include associated labor costs in the firm-fixed price.

3 Equipment and software

Provide one new FX90, the device license capacity specified in Attachment A, and one year of manufacturer software maintenance for each of the 39 replacements. Include the scheduled expansion hardware.

The device capacities in Attachment A include allowance for future expansion. Provide the point capacity, drivers and communication interfaces needed to preserve all existing integrated devices, points and functions. Include required licenses in the firm-fixed price. Document purchased device and point limits, actual usage and remaining capacity at turnover.

Before ordering, submit a controller-by-controller bill of materials showing manufacturer part numbers, quantities, device and point limits, drivers and maintenance coverage. Provide a manufacturer-supported production release of Niagara N4/Facility Explorer software for the consolidated server and new FX90s. Submit exact versions and build numbers for VA approval before installation. Demonstrate compatibility with retained controllers, drivers, modules and BAS functions, and provide the BTL evidence required by Attachment B. Beta and unsupported releases are prohibited.

4 Existing conditions and outage planning

Before each replacement, field-verify controller location, connected equipment, served areas, communication trunks, remote I/O, power and shared control dependencies. Establish a current inventory from the operating system and physical inspection. Record discrepancies and resolve conditions affecting migration with the COR before work. The contractor shall verify existing conditions rather than rely on preliminary location information as an as-built record.

Record existing online status, point readings, alarms, overrides, schedules and equipment operation. Identify existing problems jointly with the COR before migration. Do not assume field controllers will maintain safe operation without their JACE or server.

Submit a cutover plan for each controller and for the server migration. Identify affected equipment and clinical areas, estimated interruption, work window, temporary operating and monitoring measures, staff coordination, backup method, rollback triggers and restoration procedure. Group cutovers only where their combined effect has been reviewed and approved.

Maintain facility-established environmental conditions in occupied areas. Where continued operation cannot be maintained, defer the interruption until the VA approves an operating contingency or area shutdown. Do not bypass safety interlocks or change approved sequences without authorization. Stop affected work, notify the COR and implement the approved restoration plan if unexpected loss of control or unacceptable conditions occur.

Create recoverable station and server backups before changes. Verify that files are readable and document the restoration method. Retain original configurations and removed controllers for rollback until the VA authorizes their release. Provide the temporary control and monitoring measures necessary to maintain operation during the work, as documented in the approved cutover plan.

5 Controller installation and migration

Install and label controllers and specified accessories in accordance with manufacturer instructions. Reconnect and verify all affected communication trunks, network connections, remote I/O and power connections. Identify each replacement by the existing facility tag.

Preserve existing control sequences, setpoints, point mappings, graphics, alarm priorities and routing, schedules, trends, user roles and integrations unless the VA approves a change.

Include conversion of station databases and correction of references, certificates and connections affected by the replacement.

Compare each completed installation with its recorded baseline. Correct failures introduced by the work at no additional cost. Document unrelated pre-existing deficiencies and refer them to the COR for separate maintenance coordination. Do not use undocumented overrides to conceal a failed function.

6 Access Security and Site Requirements

6.1 Independent BAS network and access control

The BAS server, controllers and six workstations operate exclusively on the dedicated Engineering network for HVAC BAS controls, separate from the VA/OIT network. Maintain that separation; connection to the VA/OIT network is not part of this work. Use access methods authorized by VA Engineering. Obtain written VA authorization before adding or changing remote access, internet or cloud connectivity, or connections to another network. Protect passwords and backups, document access changes, and remove temporary contractor accounts at turnover unless continued access is authorized. The C&A requirements do not apply and a Security Accreditation Package is not required.

6.2 Identification and badging

Contractor personnel shall wear visible identification showing their name, position and employer while onsite. Comply with applicable VA badging, check-in and escort requirements. Coordinate access arrangements with the COR before starting work.

6.3 Parking and site access

Park only in areas designated by the VA. Coordinate parking, deliveries, loading and equipment staging with the COR. Provide any necessary offsite parking and transportation for contractor personnel. Keep emergency routes, entrances and patient access clear. The VA will not reimburse parking fines or resolve contractor parking violations.

6.4 Smoking

Smoking is prohibited inside VA buildings and on VA grounds. Contractor personnel who smoke shall do so offsite.

6.5 Conduct privacy and emergency procedures

Weapons are prohibited on VA property. Tool kits and other containers are subject to inspection by authorized VA security personnel. Treat Veterans, their families, VA staff and other personnel with respect and courtesy. Follow facility emergency and evacuation procedures and coordinate work with affected departments through the COR.

This work does not require access to patient information. Do not access, photograph, copy or disclose Protected Health Information (PHI), Personally Identifiable Information (PII) or other sensitive information except as expressly authorized for contract performance. Protect any information encountered in accordance with applicable privacy requirements and VA policies.

Promptly report inadvertent access, disclosure or loss to the COR and follow VA incident-reporting instructions.

6.6 Infection prevention and housekeeping

Before physical work begins in each affected area, coordinate with the COR and VA Infection Prevention staff to obtain applicable infection-control requirements and any required infection control risk assessment (ICRA) or permit. Implement required controls before disturbing ceilings, walls, equipment enclosures or materials that may release dust. Ensure all workers understand and comply with the approved controls. Protect adjacent equipment and occupied areas.

Provide required containment, dust-control equipment and housekeeping unless the contract expressly identifies these items as Government-furnished. Coordinate any required barriers or negative air equipment through the COR before work. Refer requirements that change contract scope, price or time to the Contracting Officer before proceeding.

Keep work areas clean. Transport contractor-generated debris in sealed bags or covered carts and remove it from the premises. Do not use VA dumpsters. Retain removed controllers, computers and other Government equipment onsite for rollback or disposition as directed by the VA. Do not erase, dispose of or remove Government data or equipment without authorization.

Server consolidation

Use the existing newer onsite BAS server, currently running Windows Server 2022 and Niagara N4 version 4.14, as the consolidated host. Upgrade its BAS software to the approved production release under Section 3. Retain Windows Server 2022 unless a change is specifically approved.

Verify installed builds, hardware resources and licenses before migration and document the final configuration.

Back up both servers. Provide the server licenses, compatible drivers and retained-controller software updates needed for consolidation. Include all server software maintenance renewals and reinstatement necessary to perform the upgrade in the firm fixed price. Deliver documentation of resulting software entitlements and maintenance expiration dates. Verify sufficient processing, memory, storage and licensed capacity for the consolidated system.

Physical server replacement and hardware additions are excluded; report any hardware deficiency to the Contracting Officer before migration.

Migrate station references, graphics, alarms, schedules, trends, user access and integrations from the older server. Preserve historical records through migration or a VA-approved archive accessible without operating the old server. Document any format changes and demonstrate retrieval of archived records.

Verify migrated and previously connected controllers together. During an approved test, isolate the older server and demonstrate that required controls, graphics, alarms and data collection continue on the newer server. Retire the older server only after VA authorization. Retain it and its backups as directed until acceptance and disposition instructions are issued.

8 Functional testing and acceptance

Submit test procedures before cutovers. Test every replaced JACE, each connected device and all affected points and interfaces. Check displayed values and statuses against the existing source, verify mapping, and demonstrate commands, feedback, schedules, alarms and affected sequences using approved procedures. Coordinate disruptive tests to protect clinical operations.

Required check Acceptance evidence

Required check Acceptance evidence

Inventory and licenses All 39 replacements installed. Connected devices, imported points, drivers, ports and required licenses operate without capacity violations.

Equipment functions Affected readings, commands, feedback, schedules, sequences and graphics agree with the approved baseline and expected operation.

Alarms and records Demonstrated alarm generation, routing and acknowledgment; trends collect correctly and retained historical records are accessible.

Recovery Approved restart and communication-loss checks demonstrate recovery of control, communications and alarming.

Consolidated server Migrated and retained systems operate together with no required dependency on the older server.

Closeout Project deficiencies corrected, failed tests repeated, and required documentation, backups and access delivered.

BAS workstations All six workstations installed at the specified locations. Authorized BAS functions and access verified on the Engineering network; restart, network separation and recovery checks documented.

Record the controller or device, test date, expected result, actual result, exceptions and corrective action. Notify the COR before testing so the VA can witness selected checks.

Government review or witnessing does not relieve contractor responsibility. Final acceptance requires completed testing, correction of project-related deficiencies and delivery of all turnover items.

9 Qualifications and project coordination

Identify the controls firm and technical lead responsible for programming and commissioning. Submit with the offer the technical lead’s Niagara certification appropriate to the work, evidence of Facility Explorer experience, and examples of comparable controller and server migrations. The identified technical lead shall supervise programming and commissioning. These qualifications may be met by a named controls subcontractor; the prime contractor remains responsible for performance.

Provide current, verifiable documentation of authorized access to genuine Facility Explorer equipment, required software tools and licenses, manufacturer technical support, and warranty coverage. Documentation may include manufacturer confirmation or a documented authorized supply and support arrangement identifying the participating firms and their responsibilities.

Demonstrate that the firm performing programming and commissioning has the tools, qualifications, and support needed to complete that work. Authorization to purchase equipment alone does not satisfy this requirement.

Maintain the required qualifications and supply and support arrangements throughout the applicable work. Before substituting the controls firm or technical lead, submit documentation demonstrating that the replacement meets the same requirements. Notify the Contracting Officer of any loss or change of authorization that could affect performance, support, or warranty coverage.

Identify the parties responsible for manufacturer warranty claims and project warranty service. The prime contractor remains responsible for fulfilling the warranty obligations in Section 11. No exclusive relationship with the incumbent contractor is established by this PWS.

Provide supervision, coordination, material handling, labeling, and cleanup. Coordinate with the existing maintenance provider through the COR where necessary. Do not assume uncompensated assistance or charge project work to the maintenance agreement. Only the Contracting Officer may authorize changes to contract scope, price, or time.

10 Deliverables

When due Required deliverable

With offer

Proposed controls firm and technical lead; Niagara certification; Facility Explorer experience and comparable migration examples; documentation of authorized supply and support arrangements; identification of parties responsible for warranty service and claims.

Within 30 calendar days after award Phased project schedule and responsible project contacts.

Before substitution of the controls firm or technical lead

Updated qualification and support documentation demonstrating compliance with Section 9, submitted before the replacement performs affected work.

Before ordering Controller, server, and workstation bill of materials; license schedule; software compatibility review; BTL evidence; and manufacturer support and warranty documentation for the proposed equipment and software.

Before each cutover Verified inventory and existing conditions; outage plan; backups; rollback procedure;

and test procedure.

Monthly Updated schedule showing completed work, upcoming cutovers, and unresolved issues.

Before final acceptance and within the 365-day period

As-built network and wiring records; controller locations and served-equipment schedule; O&M manual; native editable station and configuration files; workstation inventory and recovery records; final controller/server backups and restoration instructions; test results; license and software-maintenance records; warranty coverage dates, contacts, and claim procedures; and administrator access through secure methods.

Deliver the detailed records in Attachments B and C before final acceptance. Provide usage rights needed for VA operation, backup, and maintenance, including use by VA-authorized service providers under applicable software licenses; manufacturer-owned source code is not required. Provide an operator walkthrough covering the consolidated system, records, backups, and warranty contacts.

11 Warranty and scope boundaries

Provide one year of parts-and-labor warranty from documented substantial completion or VA beneficial use, consistent with the final contract terms. Document the start and end dates and pass through longer applicable manufacturer warranties. Track software maintenance separately and document its activation and expiration for every replacement.

Protect applicable existing warranties by following manufacturer requirements. Notify the Contracting Officer before work that could affect existing coverage. Correct contractor-caused damage and loss of function at no additional cost. Project defects remain the responsibility of the project contractor and shall not be billed to the maintenance agreement.

Routine maintenance, unrelated existing equipment repairs, mechanical valve or damper replacement, and facility-wide testing and balancing are excluded. Functional testing of affected controls and correction of project-caused failures are included. Changed conditions requiring additional scope shall be referred to the Contracting Officer before proceeding.

Attachment A Controller replacement schedule

Replace each of the 39 listed controllers with one FX90, including migration, commissioning and one year of software maintenance. Provide 100-device capacity per controller except FX60-11, FX60-13, FX60-26 and FX80-28, which require 110 each (100 core plus 10 additional), and FX80-15 and FX60-23, which require 200 each. These are purchased capacities, not existing device counts. Field-verify locations and existing models. Tags define the replacement scope.

Abbreviations: MER mechanical room; EL electrical room; GEN generator; BSMT basement.

Existing tag Preliminary location Expansion hardware

FX60-01 A wing basement mechanical room None listed FX80-02 A wing basement mechanical room 1 dual RS485 module FX60-03 A wing 2nd floor mechanical room None listed FX60-04 A wing 3rd floor interstitial 1 dual RS485 module FX80-10 C-W 10TH FL MER 1 dual RS485 module FX60-11 A-6TH FL MER None listed FX60-12 E-W 2ND FLR COM None listed FX60-13 A wing 2nd floor mechanical room 1 dual RS485 module FX60-14 A-6THFL MER 1 dual RS485 module FX80-15 C-W 5TH FL MER 1 dual RS485 module FX60-16 C-W 6TH FL MER 1 dual RS485 module FX60-17 E-W 4TH FL E-4032 None listed FX60-19 Veterans House Coldspring Road None listed FX80-20 Building 23 switchgear 1 dual RS485 module FX60-21 C-W NE GEN 1 dual RS485 + 1 remote I/O module FX60-23 C-W SOUTH GEN 1 dual RS485 + 1 remote I/O module FX60-24 D-W GEN RM 1 dual RS485 + 1 remote I/O module FX80-25 C-W BSMT SWITCHGEAR 1 dual RS485 module

Attachment A Controller replacement schedule continued

Existing tag Preliminary location Expansion hardware

FX60-26 A-W 1ST FL A-1250 None listed; no RS485 card FX60-27 A-W 1ST FL A-1250 None listed FX80-28 Building 5 Engineering EN-123 1 dual RS485 module FX60-29 A-W 1ST FL EL A-1486 None listed FX60-30 Chiller plant 1 dual RS485 module FX60-31 C-W 3RD FL MER None listed FX60-32 C-W 4TH FL MER None listed FX60-34 C-W 10TH FL MER None listed FX60-35 A wing 7th floor A-7098 None listed FX60-36 A-W 8TH FL A-8098 None listed FX60-37 C wing 7th floor C-7045 1 dual RS485 module FX60-38 C-W 3RD FL EL C-3066 None listed FX60-39 C-W 4TH FL C-4050 None listed FX60-40 C-W 1ST FL EL C-1101 None listed FX60-41 D wing 2nd floor D-2020 None listed FX60-42 D-W 4TH FL D-4017 None listed FX60-43 D-W 7TH FL D-7019 None listed FX60-44 A-W GEN BSMT None listed FX60-45 B-W SUB BSMT None listed FX80-46 A wing A-8086 EN-121 None listed IJ-05 A wing 2nd floor A-2056 None listed

Separately procured replacements

FX60-05 and FX60-09 have already been purchased and are being replaced by Conserv under separate work. FX80-06 serves the chiller plant and is planned for separate expedited replacement before this project. Do not include purchase or physical replacement of these three controllers, or duplicate separately purchased licenses and accessories, in this contract.

Coordinate through the COR to confirm completion and obtain the installed models, software builds, licenses and backups for these three controllers. Preserve their operation and include their server integration, compatibility verification, applicable testing and turnover records in the consolidated system. Identify any additional integration work or retained-controller software updates in the preinstallation submittal. Do not make this project responsible for completing the separately procured replacements.

“None listed” means no separately scheduled expansion module. All controllers remain subject to the licensing and functional requirements in Section 3.

Identify exact expansion-module part numbers and channel counts in the equipment submittal.

Retain existing equipment connections and functions. Controllers not listed above remain in place and are included in server consolidation as applicable.

Attachment B System records and BACnet conformance

Provide the following records for all 39 replacements and their connected devices and points.

Include retained controllers and points represented on the consolidated server in the exported inventories and server network diagram. Field-verify replaced-controller locations and changed wiring; a new physical survey of every unchanged field sensor or concealed cable is not required.

Updated as-built drawings

Provide a BAS network diagram showing the consolidated server, six replacement workstations, supervisory controllers, switches, gateways, protocol trunks and interconnections. Provide verified replacement-controller locations and enclosure layouts, power sources, port assignments, expansion modules, remote I/O and wiring terminations changed by this work.

Label each drawing with its revision date. Deliver editable drawing files and PDF copies.

Controller and device inventory

Provide an Excel or CSV inventory linking each JACE to its connected devices, equipment tags, locations and served areas. Include manufacturer, model, JACE serial number and host ID, software version, protocol, network/trunk, applicable IP address, BACnet device instance or other protocol address, and communication status. Identify inactive, spare, duplicate or unresolved entries separately. Record inspection or export dates and distinguish field-verified information from system-exported information.

Point list and capacity report

Provide an Excel or CSV export of all points configured in each replaced JACE and all points mapped on the consolidated server. Include JACE, source device, equipment tag, point name and description, station path, protocol object or register address, point type, units or states, read/write status, alarm settings, trend settings and server mapping where applicable. Identify unavailable attributes. Include active device and imported point counts, actual licensed usage, purchased limits and remaining licensed capacity for each JACE. These lists need not include internal field-controller points that are not integrated into the BAS.

Configuration and recovery records

Deliver final native editable station databases, graphics and project configuration files; controller and server backups; restoration instructions; software/module versions and dependencies;

license and maintenance records; and a dated change log. Document sequences and shared dependencies affected by migration, including approved changes. Deliver VA-controlled administrator credentials and backup passphrases separately through a secure method.

Demonstrate that VA can open the files and access the delivered backups and administrative accounts.

BACnet conformance

New supervisory controllers shall be BTL-listed under the BACnet Building Controller (B-BC) profile. The consolidated Facility Explorer server software shall be covered by a BTL listing under the BACnet Advanced Operator Workstation (B-AWS) profile. Before ordering or upgrading software, submit applicable listings, available Certificates of Conformance and manufacturer Protocol Implementation Conformance Statements (PICS) for the exact products and software builds. Provide manufacturer or BTL documentation establishing coverage where a proposed build differs from the listed version. A listing for an earlier release does not by itself establish coverage of the proposed release. Resolve coverage and version compatibility before installation. BTL evidence does not replace functional testing or required non-BACnet drivers.

Attachment C BAS workstation replacements

Provide and install six new browser-access computers, one at each location below, exclusively for the Engineering HVAC BAS network. Include operating system licenses, configuration, migration, testing and warranty in the firm-fixed price. Apply the 365-day performance period and Section 11 warranty requirements.

Location Primary users

AC Shop AC mechanics

AC Shop Supervisor Office AC shop supervisor

AC Controls Office Facility controls technician

Chiller Plant Control Room Chiller plant operators

Chiller Plant Supervisor Office Operations manager

Energy Manager Office Energy manager Equipment and configuration

Provide new business-class desktop or mini PCs with a Windows 11-supported 64-bit processor with at least four cores, 16 GB RAM, a solid-state drive of at least 256 GB, licensed Windows 11 Pro, wired Gigabit Ethernet, TPM 2.0 and Secure Boot capability. Reuse of existing monitors, keyboards and mice; include compatible display connections and necessary adapters is acceptable. Submit proposed models and specifications for approval before ordering.

Install a supported browser compatible with the BAS front end. Configure authorized user access, required graphics, alarms, trends, schedules, reports and controls. These workstations require browser access only; dedicated Niagara engineering software is not required. Complete activation and configuration through VA-authorized methods so routine BAS access operates on the Engineering network without an internet connection. Deliver VA-controlled administrator credentials securely.

Migration and acceptance

Back up required files and settings before replacement and transfer needed BAS data and shortcuts. Coordinate replacements to maintain operator access during cutovers. Connect only to the Engineering BAS network; disable unused wireless interfaces and do not establish VA/OIT, internet, cloud or other network connections without written VA authorization under Section 6.

At each location, demonstrate login, graphics, current values, alarms, trends, reports and authorized commands as applicable to the assigned role. Verify operation after restart and document results. Retain removed computers onsite pending VA disposition instructions; do not erase or dispose of equipment without authorization.

Provide a workstation inventory with location, assigned role, manufacturer, model, serial number, asset tag, computer name, IP address, operating system, installed software and license details. Deliver recovery media or images, restoration instructions, configuration records and warranty contacts. Include all six workstations in the as-built network diagram.

SECTION C - CONTRACT CLAUSES

C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL

PRODUCTS AND COMMERCIAL SERVICES (OCT 2025) (DEVIATION)

(a) Definitions. The clause at Federal Acquisition Regulation (FAR) 52.202-1, Definitions, is incorporated by reference.

(b) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post acceptance rights—

(1) Within a reasonable time after the defect was discovered or should have been discovered;

and

(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.

(c) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.

(d) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.

(e) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause FAR 52.233-1, Disputes, which is incorporated in this contract by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.

(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence. Examples of occurrences include acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. When an excusable delay occurs, the Contractor shall—

(1) Notify the Contracting Officer in writing as soon as possible;

(2) Remedy the delay as quickly as possible; and

(3) Notify the Contracting Officer when the occurrence is over.

(g) Invoice. The Government will handle invoices according to the Prompt Payment Act (31 U.S.C. 3903) and 5 CFR part 1315. The Contractor shall submit invoices to the address designated in the contract to receive invoices. An invoice must include the information required by 5 CFR part 1315.9(b).

(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees, and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark, or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.

(i) Payment—

(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.

(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR part 1315.

(3) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date that appears on the payment check or the specified payment date if an electronic funds transfer payment is made.

(4) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall—

(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the—

(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);

(B) Affected contract number and delivery order number, if applicable;

(C) Affected line item or subline item, if applicable;

(D) Contractor point of contact; and

(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.

(5) Interest.

(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the

Treasury as provided in 41 U.S.C. 7109, which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.

(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.

(iii) Final decisions. The Contracting Officer will issue a final decision as required by FAR part 33 if—

(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;

(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or

(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see FAR part 32).

(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.

(v) Amounts shall be due at the earliest of the following dates:

(A) The date fixed under this contract.

(B) The date of the first written demand for payment, including any demand for payment resulting from a termination for cause.

(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on-

(A) The date on which the designated office receives payment from the Contractor;

(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or

(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.

(vii) The interest charge made under this clause may be reduced under the procedures for interest credits prescribed in FAR part 32 in effect on the date of this contract.

(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon—

(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or

(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.

(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.

(l) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.

(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. The Government will send a cure notice to the Contractor, unless the reason for the termination is late delivery. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.

(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.

(o) Warranty. The Contractor warrants and implies that the items delivered under this contract are merchantable and fit for use for the particular purpose described in this contract.

(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.

(q) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 40 U.S.C. chapter 37, Contract Work Hours and Safety Standards; 41 U.S.C.

chapter 87, Kickbacks; 49 U.S.C. 40118, Government-financed air transportation; and 41 U.S.C.

chapter 21 relating to procurement integrity.

(r) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:

(1) The schedule of supplies/services.

(2) The Disputes, Payments, Invoice, Compliance with Laws Unique to Government Contracts, and Unauthorized Obligations paragraphs of this clause;

(3) Other contract clauses incorporated in the solicitation or contract;

(4) Addenda to this solicitation or contract,

(5) Solicitation provisions incorporated in the solicitation.

(6) Other paragraphs of this clause.

(7) Other documents, exhibits, and attachments; and

(8) The specification.

(s) Unauthorized obligations.

(1) Except as stated in paragraph (s)(2) of this clause, when any supply or service acquired under this contract is subject to any End User License Agreement (EULA), Terms of Service (TOS), or similar legal instrument or agreement, that includes any clause requiring the Government to indemnify the Contractor or any person or entity for damages, costs, fees, or any other loss or liability that would create an Anti-Deficiency Act violation (31 U.S.C. 1341), the following shall govern:

(i) Any such clause is unenforceable against the Government.

(ii) Neither the Government nor any Government-authorized end user shall be deemed to have agreed to such clause by virtue of it appearing in the EULA, TOS, or similar legal instrument or agreement. If the EULA, TOS, or similar legal instrument or agreement is invoked through an “I agree” click box or other comparable mechanism (e.g., “click-wrap” or “browse-wrap” agreements), execution does not bind the Government or any Government authorized end user to such clause.

(iii) Any such clause is deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.

(2) Paragraph (s)(1) of this clause does not apply to indemnification by the Government that is expressly authorized by statute and specifically authorized under applicable agency regulations and procedures.

(t) Comptroller General examination of record. This paragraph applies if this contract was awarded using other than sealed bid procedures and is in excess of the simplified acquisition threshold on the date of award of this contract.

(1) The Comptroller General of the United States, or an authorized representative of the Comptroller General, shall have access to and right to examine any of the Contractor’s directly pertinent records involving transactions related to this contract.

(2) The Contractor shall make available at its offices, at all reasonable times, the records, materials, and other evidence for examination, audit, or reproduction, until 3 years after final payment under this contract or for any shorter period specified in FAR part 4, longer period required by statute, or periods specified in other clauses of this contract. If this contract is completely or partially terminated, the records relating to the work terminated shall be made available for 3 years after any resulting final termination settlement. Records relating to appeals under the disputes clause or to litigation or the settlement of claims arising under or relating to this contract shall be made available until such appeals, litigation, or claims are finally resolved.

(3) As used in this clause, records include books, documents, accounting procedures and practices, and other data, regardless of type and regardless of form. This clause does not require the Contractor to create or maintain any record that the Contractor does not maintain in the ordinary course of business or pursuant to a provision of law.

(u) Incorporation by reference. The Contractor’s representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.

(End of Clause)

ADDENDUM to FAR 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL

PRODUCTS AND COMMERCIAL SERVICES

Clauses that are incorporated by reference (by Citation Number, Title, and Date), have the same force and effect as if they were given in full text.