36C25026Q0572 0001.docx

DOCX document 20 KB Posted

Attached to
7230--Window Shades - New Bldg 05 (WTS Campus), IND
Solicitation number
36C25026Q0572
Issued by

About this file

This is an Amendment to Solicitation (Standard Form 30) issued by the Department of Veterans Affairs Network Contracting Office in Indianapolis, Indiana for solicitation 36C25026Q0572. The amendment extends the deadline for receipt of offers from June 15, 2026 to June 18, 2026 at 5:00 PM EDT, and provides background information, vendor questions and answers, and as-built drawings in PDF format for the First and Second floors of the building.

The solicitation requires commercial-grade roller shades for Building #5 (Richard L. Roudebush VA Medical Center) located in Indianapolis, Indiana, specifically addressing glare and temperature fluctuations on the first and second floors in the South-West section which contains the highest concentration of glass. The VA is requesting quotes for optimal window coverings without specifying particular fabric types, openness percentages, colors, or manufacturers, expecting vendors to recommend solutions based on observations from a required site visit. The amendment clarifies that as-built drawings are available only in PDF format, acknowledges that site conditions may require alternative mounting or products, and notes that vendor recommendations to address identified conditions are acceptable provided they do not increase costs. Vendors are permitted to discuss potential solutions for non-standard installation conditions with the contracting officer during the site visit.

View the file

Other files

File Type Posted
NEW BUILDING 5_FIRST FLOOR.pdf PDF
NEW BUILDING 5_SECOND FLOOR.pdf PDF
Parking Map Plan for Bldg 5_Site Visit 02.pdf PDF
36C25026Q0572.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 06-12-2026 583-26-3-663-0089 Department of Veterans Affairs Network Contracting Office 10 8888 Keystone Crossing Suite 325 Indianapolis

IN

46240 Department of Veterans Affairs Network Contracting Office 10 8888 Keystone Crossing Suite 325 Indianapolis

IN

46240 To all Offerors/Bidders

36C25026Q0572

X X X ** HOUR & DATE for Receipt of Offers is EXTENDED to: 06-18-2026 5PM EDT See CONTINUATION Page This amendment will provide details for the following:

1. Extend the solicitation date from 06/15/2026 to 06/18/2026, 5PM EST.

2. Provide background information, questions and answers submitted by vendors.

3. Attach The AS-Builts in PDF form for the First-Second floor of the building.

Christopher Gundy Contracting Officer

CONTINUATION PAGE

Background information:

The ongoing issue of glare and temperature fluctuations affects the first and second floors in the South-West section of the building, which contains the largest concentration of glass. During the building’s development, specifications indicated that high-performance glazing would admit light while minimizing heat transfer, and that window frames would be thermally broken to provide insulation comparable to standard walls. However, adjacent spaces continue to experience excessive heat in the summer and significant cold and afternoon glare in the winter.

Question 1: Could you provide any drawings or spec documents that would help us put a bid together?

We appreciate any help you can provide.

Answer: PDF is what I have available on the building, though it is the same plan as what was provided in SOW/initial solicitation. The site visit was planned to make aware the specific details of the constructed building as often the plans do not reflect what was physically constructed.

Question 2: Can you provide access to an AutoCAD drawing and any existing pictures of space?

Answer: The As-Builts are attached in PDF form.

Question 3: We understand the requirement is for commercial-grade roller shades; however, we did not see a specific fabric, openness percentage, color, or manufacturer listed in the notice.

Answer: The VA is requesting quotes for optimal window coverings. The site visit was intended to familiarize vendors with the interior and exterior factors, enabling them to recommend solutions that effectively address glare and solar gain.

Question 4: First, could you provide any additional guidance regarding the 1%, 3%, 5%, and 10% openness materials referenced in the specifications? We would like to better understand whether there are specific preferences or intended applications for the different openness factors throughout the project.

Answer: "The site visit was scheduled to assess the interior space and evaluate how exterior elements affect it. Based on these observations, the vendor can recommend solutions to address glare and solar gain.

Question 5: Additionally, during the walkthrough we identified a window where an existing structural element may impact a standard installation approach. Our installer has a potential solution and would appreciate the opportunity to discuss the condition with you to ensure our proposed approach aligns with the VA's expectations and project requirements.

Answer: That is acceptable. The planned site visit was intended to identify areas that may require different mounting or products to ensure consistency. Please account for these conditions in your bid. If your bid is accepted, we welcome suggestions or reviews, provided that any proposed solutions do not increase costs Question 6: Any guidance you can provide would be greatly appreciated. If a brief call would be helpful, we would be happy to coordinate at your convenience. Are you able to get us roller shade specs/selections? Also, is there any way we can get an actual set of plans? There is a screenshot with an outline of windows, but a full plan set would help ensure the scope and sizes are matched to the quantities provided. It seems you have specific conditions we would need to work around, and I don’t believe we can get accurate sizes with what has been provided

Answer: Access to the As-Built drawings is currently limited to PDF format. The site visit was scheduled to assess the interior space and to evaluate the impact of exterior elements. Based on these observations, the vendor can recommend solutions to mitigate glare and solar gain.

See attached document: NEW BUILDING 5_FIRST FLOOR.

See attached document: NEW BUILDING 5_SECOND FLOOR.

File details come from the government source that posted it. Updated .