36C25026Q0375 0001.docx

DOCX document 216 KB Posted

Attached to
Z2DA--Replace iDXA C211 539-26-505
Solicitation number
36C25026Q0375
Issued by

About this file

This is an Amendment to a Request for Quote (RFQ) issued by the Department of Veterans Affairs Network Contracting Office (NCO) in Cincinnati, Ohio for Solicitation Number 36C25026Q0375. The amendment was issued on March 27, 2026, and is effective April 20, 2026. The project involves replacing an iDXA unit in Room C211 at the Veterans Affairs Medical Center (VAMC) in Cincinnati, Ohio, with Project Number 539-26-505.

The amendment serves primarily to provide the Government's responses to five Requests for Information (RFIs) submitted by potential bidders. Key clarifications include: (1) the superintendent may serve as both the Site Safety and Health Officer (SSHO) and Construction Quality Control (CQC) System Manager without requiring a graduate degree, though the SSHO must have 30 hours of OSHA training and 3 years of dedicated construction safety experience; (2) Room C211 is the correct project location, with references to C214 in specifications being header errors only; (3) contractors should include only hazardous materials testing costs in their base bids, with any required abatement to be handled separately by the VA if identified during construction; (4) the existing fume hood has electrical power and medical gas connections that must be disconnected and capped, with no associated roof-mounted fan or ductwork requiring removal; and (5) there are no as-built drawings available for the fume hood, and bidders must work with the existing disconnected unit as shown in the provided photograph.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 04-20-2026 539-26-2-6074-0018 539-26-505 36C250 Department of Veterans Affairs Network Contracting Office (NCO) 10 260 E. University Avenue Cincinnati OH 45219 36C250 Department of Veterans Affairs Network Contracting Office (NCO) 10 260 E. University Avenue Cincinnati OH 45219 To all Offerors/Bidders

36C25026Q0375 03-27-2026

X X X

539-3660162-6074-854200-3223 23NRNR001

This amendment is issued to provide the following information:

-Post the Government's response to the RFI's (see page 2)

Continued on page two Ronald Heidemann Contracting Officer

NCO1015L3-0502

CONTINUATION PAGE

REPLACE iDXA C211

FOR THE

VETERANS AFFAIRS MEDICAL CENTER (VAMC)—CINCINNATI, OH

PROJECT NUMBER: 539-26-505

QUESTIONS AND ANSWERS (RFIs)

TO REQUEST FOR QUOTE (RFQ) NUMBER

36C25026Q0375

QUESTIONS AND ANSWERS

1. RFI #1 Question: Given the size of the project, is a dedicated SSHO and the CQ education requirements required? Typically, the Superintendent can be the SSHO and CQC on this size of project, and a superintendent is not going to be a graduate engineer.

1.9 A - 01 35

The Prime Contractor shall provide a minimum of one “Full-Time” SSHO at each project site, for each shift (with no other duties) that holds as current, a professional safety certification with at least 3 years of dedicated construction safety related experience.

3.4 B – 01 45

The CQC system Manager is required to be a graduate engineer, graduate architect, or a graduate of construction management, with a minimum of PM or SRE to determine qualifications based on project complexity at construction review 5 years construction.

Answer: The superintendent may serve as the SSHO and CQC System Manager. A graduate degree is not required. SSHO must be 30 hours of OSHA training (see spec 01 35 26 parts 1.5F).

2. RFI #2 Question: The solicitation and drawings reference Room C211, while portions of the specifications reference C214. Could you please confirm the correct room designation and whether all documents apply to C211?

Answer: The majority of contract documents, including the Statement of Work and full drawing set, identify Room C211 as the correct project location. The specifications, however, contain an incorrect header reference to C214. This appears to be an error in the header only; the specifications do not assign any scope to C214.

3. RFI #3 Question: The SOW indicates that hazardous material testing and abatement will be performed “if required.”

· Has a hazardous materials survey already been completed?

· Should bidders include abatement costs in the base bid, or will this be handled separately by the owner?

Answer: The Statement of Work requires the contractor to perform hazardous materials testing and abatement “if required.” No hazardous materials survey is included in the solicitation, and bidders are not directed to include abatement in the base bid. Contractors should therefore include testing only in their proposals. If hazardous materials are identified during construction, the VA will address any required abatement separately at that time.

4. RFI #4 Question: The drawings don’t describe anything about the fume hood for disconnecting. There is power and some other type of gas or air ports and controls on the hood. We need to know how the hood is connected and what is connected to it. Is there piping or conduit behind the hood to be capped and or removed. Is there a drawing of the hood to reference connections?

Answer: There are no existing as-built or construction drawings for this fume hood, and its installation date and project of origin are unknown.

The fume hood has electrical power and medical gas connections. These utilities must be disconnected and capped.

5. RFI #5 Question: Is there a fan on the roof? If so, does that need to be removed along with any duct in the walls?

Answer: There is no roof-mounted fan associated with this fume hood. The hood is not currently connected to any exhaust fan and does not have ductwork running to the roof or through the walls that would require removal therefore no fan removal is required.

See picture below of disconnected unit.

**END OF AMENDMENT**