This document contains an amendment to solicitation number 36C25023Q0882 issued by the Department of Veterans Affairs for a boiler life study at the Ann Arbor Veterans Affairs Medical Center. The amendment provides answers to questions submitted by offerors during the question period. It confirms that the scope of work requires in-depth useful life analysis of four boilers, a deaerator tank, and a condensate tank including consideration of ancillary equipment using expert judgment. While other boiler plant equipment is listed, the same level of analysis is not required. No further questions will be answered and offers are due by July 28, 2023 at 4:00 PM Eastern Time to the specified email address.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25023Q0882 0001.docx | DOCX document | |
| Attachment 1 - Wage Determination 2015-4833 REV 22.pdf | ||
| 36C25023Q0882.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7.
ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF
PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE
OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERE
D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED
STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF
CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF
SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 36C50 Department of Veterans Affairs Ann Arbor Healthcare System Network Contracting Office 10 2215 Fuller Road Ann Arbor MI 48105 36C50 Department of Veterans Affairs Ann Arbor Healthcare System Network Contracting Office 10 2215 Fuller Road Ann Arbor MI 48105 To all Offerors/Bidders
36C25023Q0882 07-07-2023
X X X Friday, July 28, 2023 - 4:00 PM EDT X Purpose of this solicitation amendment: provide answers to questions asked during the RFQ window for questions.
There are no additional changes to the terms and conditions of this RFQ as a result of this amendment.
No further questions will be answered for this RFQ.
All sub missions must be submitted to: john.mccallum3@va.gov no later than Friday, July 28, 2023, at 4:00 PM EDT.
John C. McCallum Contracting Officer
VA-VHA-RPOC-2023-0066
36C25023Q0882 – Questions and answers
Question:
Is the Useful Life Study on the 4 boilers and 2 tanks to be as outlined in section 6, 8, 9, 10, and 11 of SOW or is it to include ALL components as listed in the table in section 2?
Answer:
The section 2 table of equipment is a general list of our boiler plant equipment and their ages. The RFI is correct in stating that the SOW requires Boilers 1-4, DA Tank, and Condensate tank to be assessed in accordance with sections 6, 8, 9, 10, and 11. This same in-depth level of analysis is not required on all equipment listed in the section 2 table. However, Section 11, paragraph D. does require an “expert analysis of the condition of boilers/ancillary equipment and recommended extension to useful life in years.” The contractor’s useful life analysis, report, and recommendations on Boilers 1-4, DA Tank, and Condensate Tank should consider each’s ancillary equipment using expert judgement. It’s expected this expert judgement shows up in a brief narrative.
In short, analysis of the main 6 pieces of equipment should consider the plant’s ancillary equipment using expert judgement but not the same level of in-depth analysis.
END RFQ 36C25023Q0882 Q&A