Attachment II - Roof Report.pdf

PDF 2 MB Posted

Attached to
Z1DA--Repair Roof Building 1 - 610A4-24-208
Solicitation number
36C25023B0033
Issued by

View the file

Other files

File Type Posted
36C25023B0033 0001.docx DOCX document
36C25023B0033 0001_1.pdf PDF
Sign in Roster 06.20.2023.pdf PDF
Attachment VIII - RFI Form.pdf PDF
36C25023B0033_1a.pdf PDF
Attachment I - VA Northern Indiana.pdf PDF
Attachment VI - EMR Form.pdf PDF
Attachment III - Specifications.pdf PDF
Attachment VII - DBA-IN20230002.pdf PDF
Attachment IV - Reroof Drawing.pdf PDF
Attachment V - VHA Directive 1192.01.pdf PDF
36C25023B0033.docx DOCX document
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Infrared Roof Assessment Report VA VISN 10 Indiana Energy Audits

(VA Project Number 610-20-601) NIHCS Fort Wayne VA Medical Center

2121 Lake Avenue Fort Wayne, IN 46805

July 30, 2021 Terracon Project No. FR206170

Prepared For:

FFE Inc.

110 Boggs Lane, Ste 170

Springdale, OH 45246

Prepared By:

Terracon Consultants, Inc.

Cincinnati, OH 45226

Terracon Consultants, Inc. C incinnat i, OH 45226

P (513) 321 5816 F (513) 321 0294 terracon.com

EXECUTIVE SUMMARY

RE: Infrared Roof Assessment Report VA VISN 10 Indiana Energy Audits NIHCS Fort Wayne VA Medical Center 2121 Lake Avenue, Fort Wayne, IN 46805

Dear Mr. Weekly, Terracon Consultants, Inc. (Terracon) is pleased to provide this summary of findings of the Infrared Roof Assessment performed at the above referenced VA Medical Center on June 16th, 2021. The primary purpose of the assessment is to identify thermal anomalies in the Infrared (IR) thermograms captured that suggest areas of moisture within the roof system. Anomalies identified, to the best of our knowledge and belief, represent wet substrates.

The intent of this executive summary is to provide a quick reference of main findings for the VA Energy Managers convenience.

Unless otherwise indicated, the thermal anomalies indicated within the report suggest areas of moisture within the roof system. Other apparent thermal anomalies may be present within the photographs/IR images provided. However, based on Terracon’s experience and analysis these anomalies do not suggest areas of moisture within the roof system and instead are likely caused by a number of possibilities which may include: conduction of building materials, air exfiltration from mechanical equipment, and thermal shadowing.

Note, anomalies are qualitative in nature. Therefore, it is necessary to verify the presence of moisture with moisture meters and/or destructive testing to confirm these findings prior to remediation. This is not included within Terracon’s scope of services.

The following is a summary of the main findings by building.

n Building 1 – Main Hospital Building:

Several thermal anomalies observed. Refer to Photos 1 through 8 on pages 3 through 10.

n Building 2 – Maintenance and Repairs Several thermal anomalies observed. Refer to Photos 9 through 11 on pages 11 through 13.

n Building 16:

1 thermal anomaly. Refer to Photos 12 & 13 on pages 14 & 15.

n Building 17 – MRI:

No apparent thermal anomalies observed.

n Building T4, T5, & T6:

No apparent thermal anomalies observed.

Terracon Consultants, Inc. C incinnat i, OH 45226

P (513) 321 5816 F (513) 321 0294 terracon.com n Building GTE:

No apparent thermal anomalies observed.

Additional detailed information can be found within the attached report, prepared on behalf of, and exclusively for FFE (Client) under mutually agreed terms and conditions. Any other use or reliance upon this Report is prohibited without Terracon’s prior written consent.

We appreciate the opportunity to provide this report. If you have any questions, please do not hesitate to contact Zachary Rusu at 734.679.0203.

Respectfully, Terracon Consultants, Inc.

Zachary A. Rusu, AIA Senior Staff Architect Facilities Services

Jared B. Lawrence, NCARB Senior Architect Facilities Engineering Services https://na3.documents.adobe.com/verifier?tx=CBJCHBCAABAAyG1uzU4flZkeVSZRpU4pGE0lJilFX6Zj https://na3.documents.adobe.com/verifier?tx=CBJCHBCAABAAyG1uzU4flZkeVSZRpU4pGE0lJilFX6Zj

Infrared Roof Assessment NIHCS Fort Wayne VA Medical Center ■ Fort Wayne, Indiana Report Date: July 30, 2021 ■ Terracon Project No. FR206170

Responsive ■ Resourceful ■ Reliable Page | 1

INFRARED ROOF ASSESSMENT

This report is provided as a supplement to the VA VISN 10 Indiana Energy Audit Report initially provided to FFE on February 15, 2021. Delivery of this report was postponed so the Infrared Roof Assessment could be performed during the summer months when weather conditions are more appropriate for this service.

1.1 INTRODUCTION

Infrared thermography is the practice of capturing Infrared (IR) thermographic images that records the apparent surface temperature pattern of a subject low slope membrane roof. The images record a color pattern of temperature readings that provide a visual thermal signature of the roof.

The primary purpose of the non-destructive infrared roof assessment is to identify thermal anomalies that may be present in the thermograms captured that suggest areas of moisture within the roof system. Unless otherwise indicated, the thermal anomalies indicated within the report suggest areas of moisture within the roof system. Other apparent thermal anomalies may be present within the photographs/IR images provided. However, based on Terracon’s experience and analysis these anomalies do not suggest areas of moisture within the roof system and instead are likely caused by a number of possibilities which may include: conduction of building materials, air exfiltration from mechanical equipment, and thermal shadowing.

Note, anomalies are qualitative in nature. Therefore, it is necessary to verify the presence of moisture with moisture meters and/or destructive testing to confirm. This is not included within Terracon’s scope of services.

DESCRIPTION AND CONDITIONS

Terracon conducted an infrared roof assessment at the NIHCS Fort Wayne VA Medical Center facility located at 2121 Lake Avenue, Fort Wayne, IN 46805 on June 16th, 2021. Thermograms of each low slope membrane roof were captured. Select thermograms are provided in the following sections that provide a composite thermogram of each roof section as well as individual areas which contain thermal anomalies that suggest moisture within the roof assembly.

The VA site contact provided 100% bid document roof plans for Building One titled Replace Roof

– Building 1 – Fort Wayne, dated 5/28/2015. These drawings are used to indicate the locations of the images captured for Building 1 only. Reference to roof areas numbers are based on the roof areas indicated in these drawings. Roof plans were not provided for the remaining buildings, aerial images of the site are used to indicate the locations of the images captured for the remaining buildings.

Report Date: July 30, 2021 ■ Terracon Project No. FR206170

Responsive ■ Resourceful ■ Reliable Page | 2

Weather Conditions During Assessment n Cloud Conditions: Mostly Clear to Partly Cloudy n Temperature: High 77°F | Low 55°F | Avg. 67°F n Wind: Direction Varied (SE, E, SW) | High 6 mph | Low 0 mph | Gust 0 mph n Precipitation

§ 48 hours prior to assessment: 0.00 in § 24 hours prior to assessment: 0.00 in

Source: www.wunderground.com/history/daily/us/in/fort-wayne/KFWA

ASSESSED ROOF AREAS

Overview photos are typically provided in this section indicating the roof areas that were assessed via a DJI Mavic 2 Enterprise Advanced Unmanned Aircraft System equipped with an infrared (IR) thermal camera and digital camera. Close-up photos are also provided primarily to provide additional detail for roof areas that contained thermally anomalies. Aerial photos are provided to indicate the location and extents of the photographs taken.

This portion of the page has been intentionally left blank

Report Date: July 30, 2021 ■ Terracon Project No. FR206170

Responsive ■ Resourceful ■ Reliable Page | 3

3.1 BUILDING 1 – MAIN HOSPITAL

Roof Plan Reference

Photo 1 (IR Overview) - Anomalies observed, refer to Photos 2 & 3 below.

Extents of Photo 1

Roof Area 12 Extents of Photo 2

Roof Area 10 Extents of Photo 3 north

Report Date: July 30, 2021 ■ Terracon Project No. FR206170

Responsive ■ Resourceful ■ Reliable Page | 4

Photo 2 – Corresponding Digital Image

Photo 2 (IR Close Up) – Roof Area 12 apparent anomaly observed.

Report Date: July 30, 2021 ■ Terracon Project No. FR206170

Responsive ■ Resourceful ■ Reliable Page | 5

Photo 3 – Corresponding Digital Image

Photo 3 (IR Close Up) - Roof Area 10 apparent anomaly observed.

Report Date: July 30, 2021 ■ Terracon Project No. FR206170

Responsive ■ Resourceful ■ Reliable Page | 6

Roof Plan Reference

Photo 4 (IR Overview) – Anomalies observed, refer to Photos 6 & 7 below.

Extents of Photo 4

Roof Area 8 Extents of Photo 5

Roof Area 7 Extents of Photo 6

Report Date: July 30, 2021 ■ Terracon Project No. FR206170

Responsive ■ Resourceful ■ Reliable Page | 7

Photo 5 – Corresponding Digital Image

Photo 5 (IR Close Up) - Roof Area 8 apparent anomaly observed adjacent to parapet scupper.

Report Date: July 30, 2021 ■ Terracon Project No. FR206170

Responsive ■ Resourceful ■ Reliable Page | 8

Photo 6 – Corresponding Digital Image

Photo 6 (IR Close Up) - Roof Area 7 apparent anomaly observed at insulation cricket adjacent to parapet.

Report Date: July 30, 2021 ■ Terracon Project No. FR206170

Responsive ■ Resourceful ■ Reliable Page | 9

Roof Plan Reference

Photo 7 (IR Overview) – Anomalies observed, refer to Photo 8 below.

Extents of Photo 7

Roof Area 32 Extents of Photo 8

Report Date: July 30, 2021 ■ Terracon Project No. FR206170

Responsive ■ Resourceful ■ Reliable Page | 10

Photo 8 – Corresponding Digital Image

Photo 8 (IR Close Up) - Roof Area 32 apparent anomaly observed adjacent to curb mounted A/C condenser unit.

Report Date: July 30, 2021 ■ Terracon Project No. FR206170

Responsive ■ Resourceful ■ Reliable Page | 11

3.2 BUILDING 2 – MAINTENANCE AND REPAIRS

Aerial Photo Reference

Photo 9 (IR Overview) – Anomalies observed, refer to Photo 10 below.

Extents of Photo 9

Extents of Photo 10

Extents of Photo 11

Report Date: July 30, 2021 ■ Terracon Project No. FR206170

Responsive ■ Resourceful ■ Reliable Page | 12

Photo 10 – Corresponding Digital Image

Photo 10 (IR Close Up) - Apparent anomalies observed.

Report Date: July 30, 2021 ■ Terracon Project No. FR206170

Responsive ■ Resourceful ■ Reliable Page | 13

Photo 11 – Corresponding Digital Image

Photo 11 (IR Close Up) - Apparent anomalies observed.

Report Date: July 30, 2021 ■ Terracon Project No. FR206170

Responsive ■ Resourceful ■ Reliable Page | 14

3.3 BUILDING 16

Aerial Photo Reference

Photo 12 (IR Overview) – Anomalies observed, refer to Photo 10 below.

Extents of Photo 12

Extents of Photo 13

Report Date: July 30, 2021 ■ Terracon Project No. FR206170

Responsive ■ Resourceful ■ Reliable Page | 15

Photo 13 – Corresponding Digital Image

Photo 13 (IR Close Up) - Apparent anomaly observed. This anomaly may potentially be caused by heat from the apparent electrical line.

Report Date: July 30, 2021 ■ Terracon Project No. FR206170

Responsive ■ Resourceful ■ Reliable Page | 16

3.4 BUILDING 17 - MRI

Aerial Photo Reference

Photo 14 (IR Overview) – No apparent thermal anomalies observed.

Extents of Photo 14

Report Date: July 30, 2021 ■ Terracon Project No. FR206170

Responsive ■ Resourceful ■ Reliable Page | 17

3.5 BUILDINGS T4, T5, AND T6

Aerial Photo Reference

Photo 15 (IR Overview) – No apparent thermal anomalies observed.

Extents of Photo 15

Report Date: July 30, 2021 ■ Terracon Project No. FR206170

Responsive ■ Resourceful ■ Reliable Page | 18

3.6 BUILDING GTE

Aerial Photo Reference

Photo 16 (IR Overview) – No apparent thermal anomalies observed.

Extents of Photo 16

2021-07-29T08:44:30-0700