36C25023B0012 0003.docx
DOCX document 30 KB Posted
- Solicitation number
- 36C25023B0012
About this file
This document is an amendment to a solicitation for repair work at the Dayton Veterans Affairs Medical Center. The scope of work includes repairing and replacing sidewalks, manholes, paving, loading docks, curbs, steps, decks, ramps and landscaping. Dimensions, materials and other details are provided for each work item through attachments in response to questions from potential offerors. The bid opening date remains March 9, 2023 at 10:00 AM Eastern Time at the location specified in the original solicitation. The Department of Veterans Affairs is the contracting agency. Offerors are advised to acknowledge receipt of the amendment prior to the bid opening deadline.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Priority 5.6 Curb _ Gutter.jpg | JPG image | |
| Priority 5.2 Cut Sheet.png | PNG image | |
| Priority 5.8 B127 Deck.jpg | JPG image | |
| Priority 5.8 and 5.9 CHR 3.jpg | JPG image | |
| Priority 5.8 and 5.9 CHR 1.jpg | JPG image | |
| Priority 5.5 B302.jpg | JPG image | |
| Priority 5.4 CLC.png | PNG image | |
| Priority 5.8 and 5.9 CHR 2.jpg | JPG image | |
| Priority 5.3 Maine.jpg | JPG image | |
| Priority 5.9 B127 Ramp.jpg | JPG image | |
| Priority 5.8 B127 Step.jpg | JPG image | |
| 36C25023B0012 0002.docx | DOCX document | |
| 330 Dock v2.pdf | ||
| 552-22-203 Site-Visit Sign-In Roster.pdf | ||
| 36C25023B0012 0001.docx | DOCX document | |
| Massachusetts v2.pdf | ||
| 36C25023B0012_1.docx | DOCX document | |
| S02. Davis Bacon Wage Rates.docx | DOCX document |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7.
ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF
PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE
OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:
Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERE
D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED
STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF
CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF
SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 03/02/2023 552-22-203 Department of Veterans Affairs Network Contracting Office (NCO) 10 3140 Governor’s Place Blvd. Suite 210 Kettering OH 45409-1337 36C250 Network Contracting Office (NCO) 10 Department of Veterans Affairs Department of Veterans Affairs Governors Place Blvd. Suite 210 Kettering OH 45409-1337 To all Offerors/Bidders
36C25023B0012 01-30-2023
X X X
X
PROJECT 552-22-203 REPAIR SIDEWALKS, MANHOLE, and PAVING
The pupose for this amendment is to provide potential offerors/bidders responses to Requests for Information (RFIs).
Bid Open ing Date, Time remains March 9, at 10:00AM (ET).
Bid Opening Location remains unchanged.
Requests for Information (RFIs)
1. Question: Do you have drawings available for this project? We were told at the site visit today that there was additional documentation (drawings and specs) available.
VA Response: Please see attached PDF documents for Priority 5.1 (Massachusetts v2) and Priority 5.2 (330 Dock v2).
2. Question: Can the site visit sign-in sheet be shared?
VA Response: Please see attached - 552-22-203 Site-Visit Sign-In Roster
3. Question: At the site visit it was stated that a waterline underneath the stairs at building 127 (?) is being threaded/capped and backfilled with gravel. I did not see this in the scope of work. Can you provide clarity on this?
VA Response: Please see Priority 5.8 in the original scope or work.
4. Question: Do you (or someone you know) have a list of service-disabled, veteran owned small businesses that might be bidding this that you could share?
VA Response: Please see attached - 552-22-203 Site-Visit Sign-In Roster
NEW RFIs and Responses as of 03/02/2023
5. Question: For priority 5.2:
· Do you want the entire loading dock to be demolished and replaced with new concrete or just specific areas within the loading dock.
VA Response: concrete to be demolished and replaced at specific areas according to the PDF document Priority 5.2 (330 Dock v2). Which was posted with Amendment #1.
· What is the thickness of the existing concrete/what is the reinforcing?
VA Response:
· See Attached: Priority 5.2 Cut Sheet
6. Question: It appears we do not have the dimensions/area for the concrete sidewalks for Priorities 5.3, 5.4, & 5.5. Can this be provided on a drawing?
VA Response:
Priority 5.3 408’ x 5’ x 4” with 6” x 6” welded wire fabric (WWF).
New sidewalk is to be at same grade as existing curb height.
· See Attached: Priority 5.3 Maine
Priority 5.4 31’ x 4’ x 4” with 6” x 6” (WWF).
Slope of sidewalk is to meet existing road height, rounded off existing curb, with ADA tactile mat.
· See Attached: Priority 5.4 CLC
Priority 5.5 B302 centerline is 104’ at 4’ wide at 4” with 6” x 6” (WWF).
Corner will have a 4’ radius at the turn, connecting both existing sidewalks.
· See Attached: Priority 5.5 B302
7. Question: For priority 5.6, please provide details on the curb to be replaced. It says to match existing, however without a drawing or detail we have no way of knowing this until the curb is demolished.
VA Response:
· See Attached: Priority 5.6 Curb & Gutter
8. Question: For priority 5.8 –
· We do not have any dimensions on the steps and deck that are being replaced. Can this information be provided on a drawing?
VA Response: Deck is 7’11” x 9’1 ½” at 4” thick steps are 7 ¼” rise with 11” tread with minimum 4” depth (See handrail at 5.9)
· See Attached: Priority 5.8 Deck
· See Attached: Priority 5.8 Step
· Need to know existing dimensions of steps including thickness of concrete and material composition/thickness beneath concrete.
VA Response: The area is to be backfilled with gravel and dead water drain capped.
· Need to know how thick you want new steps / what type of reinforcing for steps.
VA Response: The Deck is to be reinforced with 6” x 6” (WWF) minimum #3 bar reinforcement in steps. (See response to Question 8 above).
· What type of handrail is desired? Material type? Finish? Installation method (cast in place or surface mount)? You say to match B320 – please provide this information so we are able to match it.
VA Response: Handrail is to be ADA compliant, aluminum continuous handrail, surface mount, black in color
· See Attached: Priority 5.8 and 5.9 CHR 1
· See Attached: Priority 5.8 and 5.9 CHR 2
· See Attached: Priority 5.8 and 5.9 CHR 3
9. Question: For priority 5.9 – VA Response: Match Priority 5.8 (see response to Question 8 above).
· Please provide dimensions of ramp to be removed. Please provide a drawing showing this.
VA Response:
Centerline measures 45’ x 6’ wide at 4”. Reinforce with 6” x 6” (WWF)
· See Attached: Priority 5.9 B127 Ramp
· Need to know how thick you want ramp / what type of reinforcing.
VA Response: See above.
· What type of handrail is desired? Material type? Finish? Installation method (cast in place or surface mount)? You say to match B320 – please provide this information so we are able to match it.
VA Response See response to Question 8 above.
10. Question: The Scope calls out to grade adjacent area with topsoil and hydro-seed, and to water until 3” high with no bare spots. Are you saying you want us to figure on sending someone and watering all areas of seeded areas every day until grass is 3” high? If so – we can include this – but need to know is there water readily available at all locations where grass will be planted, or do we need to figure on bringing in a water truck? This seems like something that may be better handled by the VA maintenance/grounds crew, but we can include this if you are confirming it DOES need to be included.
VA Response: Yes, the contractor is responsible for leaving the grass areas in the same condition as when the project starts. Water may be available at some locations.
*All dimensions are approximate and must be field verified by the contractor.
File details come from the government source that posted it. Updated .