This document is a presolicitation notice for a renovation project at a Veterans Affairs medical facility in Fort Wayne, Indiana. The project involves renovating the basement of Building 1 at the VA Northern Indiana Health Care System campus to modernize space for various departments including Environmental Management Services, Biomedical Engineering, Pharmacy, Mailroom, Engineering Services, Office of Information Technology, Graduate Medical Education, and Medical Imaging. The renovation will be conducted in three phases over a period of 780 days total according to design drawings. Phase I is scheduled for 300 days, Phase II for 210 days, and Phase III for 270 days. The project involves removal of asbestos and lead paint according to OSHA guidelines. The justification provided is that the renovation will help transform VA business operations by modernizing systems and focusing resources more efficiently to provide world-class customer service to veterans and employees. The solicitation for the project is scheduled to be posted on March 11, 2021 to the SAM.gov website.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contract Opportunity Presolicitation Notice
PRODUCT SERVICE CODE
SUBJECT
CONTRACTING OFFICE'S
ZIP-CODE
SOLICITATION NUMBER
RESPONSE
DATE/TIME/ZONE
ARCHIVE
DAYS AFTER THE RESPONSE DATE
RECOVERY ACT FUNDS
SET-ASIDE
NAICS CODE
CONTRACTING OFFICE
ADDRESS
POINT OF CONTACT
(POC Information Automatically Filled from User Profile Unless Entered)
DESCRIPTION
See Attachment
AGENCY'S URL
URL DESCRIPTION
AGENCY CONTACT'S EMAIL
ADDRESS
EMAIL DESCRIPTION
ADDRESS
POSTAL CODE
COUNTRY
ADDITIONAL INFORMATION
GENERAL INFORMATION
PLACE OF PERFORMANCE
Required Field Contract Opportunity Presolicitation Notice
Y1DZ
Renovate Basement, Building 1 610A4-19-104 43219 36C25021B0018 04-19-2021
1:00 PM
EASTERN TIME, NEW YORK, USA
N
SDVOSBC
236220 Department of Veterans Affairs Network Contracting Office (NCO) 10 2780 Airport Dr., Suite 340 Columbus, OH 43219 Yvonne Demorest, NCO 10 Contracting Officer VHA Northern Indiana Health Care System Fort Wayne, IN 2121 Lake St.
Fort Wayne IN 46805
STATEMENT OF WORK
Renovate Basement, Building 1 VHA Northern Indiana Health Care System – Ft. Wayne, IN Project: 610A4-19-104
Solicitation will be posted to beta.SAM.gov on or around March 11, 2021
Project Background:
The basement has not been renovated for decades, if at all, and is being renovated in this project to modernize the space.
Statement of Work:
Contractor will provide all labor, equipment, materials, and supervision necessary to Renovate Basement, building 1 at the Ft. Wayne campus of the VHA Northern Indiana Health Care System to include but not limited to the following:
Renovate space in the basement for Environmental Management Services, Biomed, Pharmacy, Mailroom, Engineering Services, Office of Information and Technology, Graduate Medical Education, and Medical Imaging by following the developed design and specifications.
Campus buildings are pre-1950 construction; asbestos containing material and lead based paint are present in the buildings and must be removed and handled per OSHA guidelines. VA shall provide most recent surveys of hazardous material. The design identifies hazardous locations and materials as applicable to complete the project.
The project is divided in three phases per the A/E’s drawings. As a working Hospital the adjacent spaces and functions will need to be maintained and a high degree of coordination, scheduling and phasing will be required to allow the continuation of the existing Hospital Services during the entire Construction Project. Each phase must have a punch list and a 30-day work stoppage between phases at no additional cost to the government to allow for internal moves. A Notice to Proceed (NTP) will be issued before the next phase may begin.
Phase I should take 300 days and the work will be conducted in rooms 15-26 and 45, 45A, & 45B.
Phase II should take 210 days and the work will be conducted in rooms 49A-59A and the east basement corridor.
Phase III should take 270 days and the work will be conducted in rooms 30-35 and 43, 44, & 44A and the west basement corridor.
All work to be completed at the VA Northern Indiana Health Care – Ft Wayne Campus, 2121 Lake Ave, Ft Wayne, IN 46805.
Justification of Work:
This project is designed to transform the VA’s business operations by modernizing systems and focusing resources more efficiently to be competitive and to provide world-class customer service to Veterans and its employees by; streamlining workflow, optimizing storage space, providing real-time electronic inventory tracking, and medication barcode verification to prevent dispensing errors at the Ft Wayne VA.