Addendum No.1 Description.pdf
PDF 47 KB Posted
- Attached to
- Y1DZ--Expand MRI Suite Project 541-CSI-103
- Solicitation number
- 36C25020B0043
About this file
This addendum provides revisions to specifications and drawings for an expansion of the MRI suite at the Louis Stokes Cleveland VA Medical Center. The project will add a third 3T MRI unit to the north of the existing suite and renovate connecting support spaces. Mechanical revisions include replacing and updating the systems integration specification and revising piping and clerical errors on drawings. Electrical revisions add panelboard schedules and clarify UPS requirements on drawings, and provide circuit breaker and panelboard description details.
The pre-solicitation notice provides an opportunity for a construction project to expand the MRI suite at the Louis Stokes VA Medical Center. The contractor will add a third 3T MRI, rework surrounding site, landscaping, sidewalks, and physical barriers. The period of performance is estimated at 548 calendar days from notice to proceed, with a project value between $1-5 million. The solicitation for this 100% Service Disabled Veteran Owned Small Business set-aside will be posted on June 5, 2020. The contractor must perform a minimum of 15% of construction work, and obtain necessary Ohio licenses and permits. Site visits, questions, and amendments will be handled through the Federal Business Opportunities and System for Award Management websites.
View the file
Other files
Show all 40
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
September 15, 2020
Louis Stokes Cleveland VA Medical Center
Cleveland, OH 44106
Attention: Kurt Rothermel
Regarding: MRI Addition
Addendum No. 1
Dear Mr. Rothermel, Please incorporate the following items in the upcoming addendum for the above referenced project.
Mechanical Items
1. Delete Specification Section 23 09 40 SYSTEMS INTEGRATION and replace with the attached
Specification Section 25 09 00 SYSTEMS INTEGRATION. The systems integration shall be the responsibility of the contractor for this project.
2. Refer to attached revised drawing M-202. Corrected graphical error of piping to CUH.
3. Refer to attached revised drawing M-701. Corrected some minor clerical errors.
Electrical Items
1. Refer to attached revised drawing E-301. Added panelboard schedule indicated and clarified UPS requirements in clouded area.
2. Refer to attached revised drawing E-302. Provided additional information regarding circuit breaker features and revised panelboard description indicated.
3. Refer to attached revised drawing T-301. Updated details to latest standard and added cable color detail.
END OF ADDENDUM NO. 1
Please contact me with any questions.
Sincerely yours, Fredrick, Fredrick & Heller Engineers, Inc
Leonard Hendrix, PE
Date 08/17/2020
Attachments:
1. Specification Section 25 09 00 SYSTEMS INTEGRATION.
2. Revised Mechanical Drawings M-202 and M-701.
File details come from the government source that posted it. Updated .