This document contains responses to five industry questions regarding a federal supply solicitation for Omnicell XT Supply Racks at Tulsa VAMC.

The procurement involves 10 units of the Omnicell XT Supply Rack, model SUP-OTH-001, compatible with the existing Omnicell rail system. Key clarifications from the government include: (1) the delivery date of 22 December 2026 (listed in the B.3 price/delivery schedule for CLIN 0001) governs over the January 8, 2027 date referenced in the Statement of Work; (2) the specification table header attributing model numbers to ILC Dover is inaccurate—the part is manufactured by Omnicell, not ILC Dover; (3) OEM authorization certification from Omnicell must be provided as a written statement confirming the vendor's authorized-distributor status with no specific required wording or form, and must be included in the quote PDF submitted by 6 November 2026 at 11:00 AM Central Time; (4) the technical questions deadline is 11:00 AM Central Time on Wednesday, 4 November 2026 (the reference to "Central Daylight Time" was a typographical error as this date falls within Central Standard Time); and (5) sustainability certification documents are not required for this single-item supply buy. All responses clarify ambiguities in the original solicitation to facilitate vendor compliance.

View the file

Other files

File Type Posted
Buy American Certificate 1.pdf PDF
36C24W27Q0013.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Responses to Industry Questions

1. Delivery date — SOW vs. price schedule. The Statement of Work states the contractor must deliver the products "no later than January 8, 2027," while the B.3 price/delivery schedule lists 22 December 2026 for CLIN 0001. Which date governs delivery, and which date should the self-certifying statement confirm ability to meet the project deadline reference?

A. The delivery date-the preferred date is 22 December 2026.

2. Specification table header “Model Numbers are from ILC Dover."

The specification table header attributes the model numbers to ILC Dover, while the item description and the rest of the solicitation identify the item as the Omnicell XT Supply Rack, model SUP-OTH-001, compatible with the existing Omnicell rail system at Tulsa VAMC.

Please confirm that SUP-OTH-001 (Omnicell) is the correct required model and that the ILC Dover header reference is an error.

A. Specification table header - I believe that header may be inaccurate, the part we are ordering is specifically manufactured by Omnicell. ILC Dover manufactures Omnicell but not this item.

3. OEM authorization certification — form and content. The solicitation requires written certification from Omnicell confirming authorization to supply XT Supply Racks. Please confirm: (a) must the certification letter name the quoter and the solicitation number and quantity (10 units, SUP-OTH-001);

(b) must it be included in the quote PDF submitted by 6 Nov 2026, 11:00 AM CST; and (c) is there any required wording or form beyond a written statement from Omnicell confirming authorized-distributor status for this requirement?

A. OEM authorization certification- We do not specify required wording or a particular form. A written statement from Omnicell confirming the vendor's authorized-distributor status is sufficient, provided it clearly demonstrates compliance with the solicitation requirement

4. Question deadline time zone. The technical-questions deadline is stated as "11:00 AM Central Daylight Time (CST), Wednesday November 4th, 2026." Daylight saving time ends 1 Nov 2026, so 4 Nov is Central Standard Time. Please confirm the deadline is 11:00 AM Central Time on Wednesday, 4 November 2026.

A. Question Deadline-The deadline for submission of questions is 11:00 AM Central Time on Wednesday, November 4, 2026. The reference to "Central Daylight Time (CST)" should be understood as a typographical inconsistency. November 4, 2026, falls within the Central Standard Time period.

5. Sustainability certification documents. The offer submittal instructions require "sustainability certification documents" in the quote PDF. For this single-item supply buy (10× SUP-OTH-001, no installation), which specific sustainability certification document(s) are required — e.g., a manufacture statement, a specific federal sustainability certification, or product-level documentation supplied by Omnicell?

A. Sustainability Certification- Do we need this? I don’t think we require it.