This is a Statement of Work (SOW) for design/build services to correct Mental Health Environment of Care Checklist (MHEOCC) deficiencies at the VA Tennessee Valley Healthcare System Nashville Campus, located at 1310 24th Avenue South, Nashville, TN 37212.

The contractor must provide comprehensive design and construction services within 120 calendar days, including final inspection, punch list corrections, testing, and closeout. Design and construction may overlap; however, VA-approved Construction Documents must be submitted within 60 days of Notice to Proceed. Key scope includes interior demolition, ligature-resistant hardware upgrades, patient room door modifications with windows and internal blinds for six specified rooms (A-476, A-475, A-474, A-472, A-449, A-445), anti-ligature self-closer devices for seclusion room A-461, complete replacement of two auto-opening door systems connecting patient care areas with 100% ligature-resistant mechanisms, nurse station modifications with security glazing (polycarbonate) extending from counter to ceiling for both PMU and non-PMU areas, environmental safety enhancements to eliminate climbable surfaces, sealant work, moisture intrusion mitigation, and all related interior construction activities. The contractor must comply with VA Mental Health Design Guide, MHEOCC requirements, applicable building codes, and all current VA specifications and standards. The A/E must provide Design Development, Construction Documents, and Construction Period Services with professionally licensed architects and engineers; all documents must be A/E stamped. The contractor bears sole responsibility for site investigation, accurate material takeoffs, cost estimation within budget limitations, quality control planning, and final inspection and testing. Work must minimize disruption to medical center operations, maintain fire protection and infection control standards (PCRA/ICRA/ILSM), and comply with strict temporary barrier requirements, security measures for psychiatric patients, and comprehensive cleaning to hospital standards upon completion.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MHEOCC COMPLIANCE

626-27-504

STATEMENT OF WORK

Department of Veterans Affairs - TVHS, Nashville Campus Requirements for Design/Build Services

Project 626-27-504 MHEOCC Compliance (Mental Health Deficiency

Repairs)

1. GENERAL SCOPE OF WORK:

Provide design and construction services to correct known Mental Health Environment of Care Checklist (MHEOCC) deficiencies at the Mental Health facility at Veteran’s Affairs (VA) Tennessee Valley Healthcare System, at the Nashville Campus of the VA Tennessee Valley Healthcare System, located at 1310 24th Avenue South, Nashville, TN 37212, in accordance with this statement of work, specifications and vendor equipment drawings.

Furnish labor, materials, supervision, and equipment necessary for a Design/Build project to properly prepare affected interior spaces for improved safety, function, and compliance.

Work includes interior demolition, industrial hygiene controls, architectural repairs, ligature-resistant hardware upgrades, sealant work, environmental safety enhancements, electrical adjustments, lighting corrections, wall protection, moisture intrusion mitigation, PCRA/ICRA/ILSM and all related interior construction activities.

The drawings used during field review (Reference Attachment 1) represent only VA’s preliminary understanding of deficiencies and shall not be relied upon as final design direction. The Contractor shall develop its own fully verified design solution in partnership with VA design reviewers. The design consultant shall provide the necessary architectural and engineering services required to prepare a complete design (stamped contract drawings, specifications, technical reports, cost estimates, inspections, quality assurance, testing, etc.) and construction period services to ensure the successful completion of the project. The contractor shall provide the VA with certifications and standard VA warranties.

During Design Development (DD) the contractor is responsible for independently analyzing conditions, needs, systems, and developing unique, optimal proposals to achieve project objectives. All design and construction work shall be complete within 120 calendar days, including final inspection, punch list corrections, testing, and closeout/ release of claims.

2. STATEMENT OF PROJECT OBJECTIVES:

The following objectives represent the known deficiencies documented by the Government within the project area. As this is a Design/Build project, the Design-Build Contractor shall verify all listed conditions and incorporate appropriate solutions into the design. The Contractor’s Architect/Engineer (AE) shall determine the specific corrective measures, materials, and construction details necessary to achieve compliance with VA standards, Mental Health Environment of Care requirements, and applicable building codes.

A. Safety Hardware Upgrades

Ensure all required tamper-resistant, ligature-resistant, and psych-safe hardware is incorporated into the design and installed on light switches, fixtures, doors/self-closers, access panels, and other identified components.

B. Patient room doors (clouded in red in attachment A).

1) Each door needs to be equipped with a window with an internal blind. If possible, the existing door, door frame, and hardware can be re-utilized in conjunction with a new window assembly that is mental health compliant, however a full door/frame replacement may be required to meet the intend of this objective. Doors that require addressing are doors between the patient room and the corridor for the following rooms: A-476, A-475, A-474, A-472, A-449, and A-445.

C. Door Hardware and Operational Modifications (clouded in blue in attachment A).

Design and implement required modifications to improve door function and safety.

1) Seclusion room A-461 door to hallway – self-closer device needs to be anti-ligature.

Door and door frame may need to be replaced along with self-closer hardware to meet the intent of the MHEOCC requirement and ligature-resistant compliance.

2) Two sets of double-doors separating that are utilized to divide mental health into two distinct patient care areas will need to be completely replaced (door, door frame, and self-closer devices). The self-closing and PIV activated opening is managed through an overhead door opener that is not ligature-resistant compliant.

D. Environmental/Behavioral Safety Enhancements (clouded in green in attachment A).

Identify and mitigate environmental risks such as climbable surfaces. Provide design recommendations and construction modifications to improve patient and staff safety.

1) Nurses station: Modify counter to eliminate climbable surfaces by designing and installing polycarbonate or other approved “glazing” from the nurse station counter to the ceiling, this applies to both nurse stations.

E. Code-Compliant and Constructible Solutions

Deliver solutions that meet current VA design standards, Mental Health Environment of Care requirements and applicable building codes while supporting constructability and operational continuity.

1) Ensure all repairs, replacements, and modifications integrate safely with existing systems, minimize operational disruption, meet required codes, and standards.

2) All new construction shall match the existing architecture to maintain the visual integrity of the campus.

3) All self-closures must be concealed and anti-ligature.

3. DESIGN:

All work shall be conducted with the guidance and oversight of the prime contractor.

The A/E shall work with VA design team to ensure VA satisfaction with design intent.

A. STATEMENT OF A/E TASKS:

1) The A/E shall develop design solutions for:

(a) The Nurse Station for PMU and non-PMU (security glazing ie polycarbonate – to extend from top of nurse station to ceiling).

(b) Doors to six patient rooms in non-PMU to be configured/replaced with doors that include windows and internal blind.

(c) The two sets of auto opening doors connecting the PMU to the non-PMU require a new door system that is connected to the PIV reader with keyed override, auto open/close, glazing to complement the existing condition, and to be 100% ligature resistant.

(d) Anti-ligature self-closer mechanism for seclusion room (door directly off hallway) and a replacement door to accommodate the self-closer mechanism. Existing lever assembly to be reused.

(e) All design work shall fully comply with the VA Mental Health Design Guide, MHEOCC requirements, and applicable VA clinical workflow and environmental safety standards. The A/E shall evaluate patient and staff circulation, visibility, elopement risks, ligature-resistant features, and behavioral health safety criteria, and shall incorporate all required modifications into the Design/Build construction documents.

2) The A/E shall furnish all services for a complete Design Development, Construction

Documents, and Construction Period Services (CPS) (including final inspection) by professionally licensed Architects and Engineers. The contractor will be required to have A/E stamped construction documents for all work. A/E will assist with providing necessary professional design services required to complete construction.

(a) Perform a complete site survey to include a thorough investigation of existing conditions, typical construction type and variations, finishes, verifying and analyzing utility systems for affected areas and utilities traversing through affected areas to accurately document and convey space dimensions on measured drawings. This information provides the necessary basis for preparation of Design Development.

3) The A/E shall provide cost estimation, project scheduling, phasing, and construction period services prior to beginning construction.

4) In addition to the prime contractor’s quality control efforts, the A/E shall develop and provide a quality control plan and services throughout construction. Quality control plans, inspection, observations, and tests shall be included in the closeout documents.

5) The A/E will be required to provide a complete set of contract documents and asbuilt documents (drawings in the current version of AutoCAD (.dwg) and specifications in paper and electronic formats (docx and pdf).

6) The contractor shall provide competent design and construction period services utilizing individuals who are adequately knowledgeable of the various design disciplines including but not limited to architectural and engineering of structural, civil, mechanical, electrical, mental health and special systems as required by the project. Changes in personnel from those who are proposed in negotiations and at kick-off meetings will not be allowed without VA approval. The services of an industrial hygienist familiar with hazardous materials will be utilized if these materials are found. The registered individuals who stamp the completed documents shall accomplish engineering design work.

7) Design in collaboration with equipment/product manufacturers and manufacturer recommendations.

8) Attachement A - the attached drawing is provided for reference and depicts the known deficiency locations. The A/E shall field-verify all conditions and identify any additional deficiencies not shown.

B. STATEMENT OF DESIGN BUILDER TASKS:

1) The intent is to fast-track the completion of the MHEOCC Compliance deficiency.

Design and construction activities may overlap; however, the Design-Build Contractor shall submit VA-approved Construction Documents (CDs) within 60 days of Notice to Proceed. Demolition (with VA approval), invasive investigation, or any preparatory work that may disrupt occupants or compromise patient safety shall not begin until the affected areas have been vacated, formally turned over to the contractor, and all required infection control and security measures are fully established and approved by the COR.

2) The Contractor shall furnish the following services for a complete design and construction period services including final inspection and testing:

(a) Contractor shall thoroughly investigate all areas to verify conditions, make accurate material takeoffs, and verify all details (break points, transitions, etc.)

and required patch-back. Contractor will may be permitted to take sample tear offs / demolition to verify resulting substrate conditions and required patch-back with written request and confirmation of request by CO/COR. It is the contractor’s sole responsibility to accurately investigate and accurately determine/estimate material and labor requirements for this project. Change orders will not be granted for supposed unforeseen substrate conditions. Since VA permits inspection / sample removals to determine conditions, any resulting conditions will not be considered as concealed or unforeseen. Licensed commercial contractors will be expected to be very familiar with their work/trade disciplines and should be able to accurately project this work given the level of exploration investigation being permitted by the VA. If a contractor is not confident with their projections / estimations, then they should not bid on this project. Contractors and subcontractors that submit pricing / bids will accept these conditions.

(b) Contractor shall comply with all manufacturers’ directions and instructions.

(c) Remove demolished utilities to nearest active line or source (i.e. panel for wire).

All abandoned utilities to be removed.

(d) The contractor will be expected to minimize the impact on the medical center.

Contractors shall coordinate and perform work so as to minimize disruptions to medical center operations. Some work may be performed after normal hours of operation if deemed necessary by the VA. Normal working hours for the VA are 7:00 AM – 3:30 PM CST. The contractor may be required to complete work outside of the normal working hours with VA COR approval to maintain schedule.

(e) Contractor is responsible for all temporary measures to enable work, including but not limited to coordination, detour/construction signs, temporary barriers, negative air, infection control, etc.

(f) Design and construct within the obligated project budget / funding limitations. The contractor and the contractor’s AE shall coordinate cost control measures to design within funding limits. Cost control alternatives shall be explored during Design Development (DD’s). The contractor shall employ a system of measures, such as timely estimates, cost control meetings, effective product and material selection, efficient management of labor/ trades, reduction of overall time/ critical path, etc.

(g) Develop and execute a quality assurance (QA/QC) plan that establishes the design/build team and method of review for the project submission packages, plans and specifications. The project QA/QC process shall be a rigorous, thorough review and coordination effort. QA/QC team members shall be led by a senior Mechanical, Electrical, and Architecture designer with oversight from a project QA project manager (who is not the project Superintendent or PM). The QA/QC plan shall be submitted to the VA along with the project schedule. Within 14 calendar days after receipt of Notice to Proceed (NTYP, the Contractor shall submit a detailed QA/QC plan describing each QA/QC task that will be taken during the development of the various design submission packages and the name of the A/E’s team member(s) responsible for QA/QC. The QA process shall produce deliverables included with each submission package, including but not limited to redline mark-ups and QA issue tracking sheets and a QA overview/narrative. Upon its completion, each task shall be initialed and dated by the responsible QA/QC team member. A 100% completed QA/QC plan, with all items resolved/initialed/dated shall be submitted with the final construction document submission package.

C. BASIS FOR DESIGN:

1) Department of Veterans Affairs standards may be obtained from the Internet.

http://www.cfm.va.gov/til/.

2) Design Guide for Inpatient Mental Health & Residential Rehabilitation Treatment Program Facilities. https://www.cfm.va.gov/til/dGuide/dgMH.pdf

3) Compliance with the standards listed in Guidelines and Standards will be reflected in the completed design and construction documents. Conflicting criteria shall be brought to the attention of VA.

4) Materials and Systems Guidelines can be found at, https://omh.ny.gov/omhweb/patient_safety_standards/guide.pdf

5) VHA DIRECTIVE 1167. https://www.navao.org/wp-content/uploads/2017/06/VHADirective-1167-MH-EOC-Checklist-for-MH-Units-Tx- Suicidal-Pts-5-12-17.pdf

D. DETAILED DESIGN SUBMISSION REQUIREMENTS:

1) Program Guide PG-18-15 establishes the guidelines for the A/E submissions. These guidelines indicate a minimum level for submission compliance, which may not be adequate for certain types of design. In some instances, in which critical decisions need to be made, sufficient and relevant information must be provided timely in order for the design to progress to meet certain milestone dates. The level of applicability of the program guide depends upon the scope of work and the exclusions, which are herein specified. Questions in regard to the applicability of specific requirements shall be resolved with the medical center staff prior to any submission deadline.

Where “days” are stated, this refers to “calendar” not “work” days.

2) At each of the following design meetings, all design material will be reviewed with the design team:

(a) Schematic Documents (SD)

(b) Design Development (DD)

(c) Construction Documents (CD)

3) Design Team Meetings: Contractor shall meet with design team consisting of key VA staff (engineering, key personnel, etc.) to conduct interviews to ensure that design will meet VA needs. Design team meetings are suggested after each submission.

The number of meetings may vary based on contractor experience and design progress.

4) VA submission review comments may be verbal, noted directly on review sets, or in writing. The contractor shall be responsible for compiling & addressing review comments. Contractor shall produce & distribute meeting notes or minutes for VA review immediately after each submission review or design meeting.

5) Final construction documents shall be reproduced as part of the contract. Provide 1 full size and 1 ARCH C size and 1 bound copy of the Specifications/Basis of Design/ etc shall be delivered to the Contracting Officer Representative for each submission.

6) Total time to accomplish design and submittals shall be within 60 calendar days from the issuance of the Notice to Proceed to reproduced Construction Documents. Each design submission will require 14 workdays for VA review, depending upon the contractor's responsiveness to previous VA comments and contractor quality control.

Design and construction may overlap. Contractor shall propose a submission schedule based upon their understanding of the design and their staffing workload.

The intermediate dates shall be developed by the contractor and submitted to the VA for acceptance. Design and construction shall be completed within 120 calendar days.

E. CONSTRUCTION PERIOD SERVICE REQUIREMENTS:

1) Review of Submittals: Contractor and COR shall review and approve all material submittals, shop drawings, test reports, etc previously submitted and approved by the A/E team. Submittal and submittal review copies shall be provided to VA Contracting Officer upon request.

2) Review Analysis of Requests for Information (RFI), Change Orders, and Costs:

Contractor shall provide prompt responses when required to review and provide analysis of construction, requests for information, change orders, etc.

3) Site Visits: Contractor shall conduct site visits during the construction. Prior to each design site visit, the contractor shall notify the VA Contracting Officer and the COR of the number and disciplines of contractor representatives participating in the site visit.

The Contractor shall invite VA Contracting Officer (and key VA representatives) to attend contractor/ architect site visits. The contractor shall observe the construction and advise the Contractor of any deviations or deficiencies and recommend appropriate corrective actions. The contractor shall promptly provide the VA Contracting Officer with documentation of inspections, deficiencies, recommendations, and evaluation/approval of corrective actions.

4) Contractor shall provide final inspection and testing of the new work and all building systems. Provide a copy of the final inspection report to the Contracting Officer and COR. In subsequent inspections, update of final inspection list (for the Contracting Officer and COR) to indicate corrective measures (and dates) until all Completion list items have been corrected. Signed and stamped testing documents shall be provided to the Contracting Officer.

5) “Record Documents / Drawings" Requirement: Contractor shall provide marked-up prints to the contractor showing actual construction and any changes which occurred during construction. Contractor shall revise the solicitation documents and provide a complete set of all drawings showing actual completed construction and reflecting any changes incorporated in the work on electronic media. Electronic media drawings shall be in AutoCAD 2020 or more recent (.DWG format) or Autodesk Architectural Building Systems. Compatibility means that data can be accessed directly without translation or processing of data files. Problems shall be corrected to the satisfaction of VA. VA will not accept electronic drawings with numbered or coded layer names (reference http://www.cfm.va.gov/til/projReq.asp), corrupted information resulting from translation/conversion, non-uniform drawing layers, colors, line-types, etc., and other issues that prevent easy reading and manipulation of the drawing/entities in AutoCAD 2020 or more recent. Electronic media specifications shall be in the latest version of Microsoft Word in use at VA. Provide closeout binders (3) with all certifications, warranties, test reports, product information, application data, MSDS and O&M manuals. All close-out information shall be provided within 14 days of acceptance of final inspection.

4. GUIDELINES AND STANDARDS:

A. Design and construction shall comply with current VA specifications, guidelines, design alerts, manuals, details, criteria, instructions, procedures, standards, etc. Refer to the VA Technical Information Library at http://www.cfm.va.gov/TIL/. The VA Design Manuals http://www.cfm.va.gov/til/dManual.asp are a good place to start. When series standards are not available or are incomplete for a specific function/space, contractor shall apply the standards/guidelines of another series for that specific function or a similar function.

B. Design shall be performed and submitted in accordance with VA Contractor Submission

Instructions for Minor and NRM Construction Program. Refer to www.cfm.va.gov/contract/ae/aesubmin.doc

C. Design and construct for accessibility. Refer to http://www.cfm.va.gov/til/accessibility.asp.

D. Comply with current applicable state, local, & federal building codes as well as codes from other recognized authoritative bodies; including but not limited to Associated Air Balance Council (AABC), American Concrete Institute (ACI), Acoustical and Insulating Materials Association (AIMA), American National Standards Institute (ANSI), American Society of Heating, Refrigeration, and Air-Conditioning Engineers (ASHRAE), American Society of Mechanical Engineers (ASME), American Society for Testing and Materials (ASTM), The Building Officials and Code Administrators International (BOCA), Gypsum Association (GA), International Building Code (IBC), NEC, NFPA, National Environmental Balancing Bureau (NEBB), National Standard Plumbing Code (NSPC), OSHA, Standard Building Code (SBC), Sheet Metal and Air Conditioning Contractors’ National Association (SMACNA), The Uniform Building Code (UBC), and Uniform Federal Accessibility Standard (UFAS), & American Disabilities Act (ADA).

E. Coordinate with manufacturers and comply with their instructions / recommendations.

F. Design for patient privacy and HIPAA compliance.

G. Design for patient privacy in accordance with VA directives.

H. Ensure proper life safety, including (but not limited to) egress, proper fire/smoke compartmentalization, fire alarm, sprinkler system, etc.

I. Provide a structural design and evaluation of the existing structure if necessary.

J. Comply with current Physical Security requirements in VA Physical Security Manual.

Physical Security and Resiliency Design Manual (va.gov)

5. GENERAL REQUIREMENTS:

A. Contractor is responsible for removing and properly disposing of debris and items being demolished daily. Debris shall always be contained in acceptable containers.

B. Materials, installation methods, routing, and exact locations of new items shall be coordinated with the Contractor’s Superintendent and contractor designer prior to proceeding with work.

C. Provide proper layout and support for entire project, including necessary structural design services and work as needed. During construction, if layout or structural support is not detailed, noted, or specified, Contractor shall submit a viable layout plan or support detail to COR for approval at no additional cost.

D. It is the Contractor’s responsibility to thoroughly investigate the site to verify conditions

(both exposed and concealed) prior to pricing the job, during design, and throughout construction. Contractors are responsible for providing their own comprehensive inspection and unforeseen conditions should be restricted to issues found where only destroy inspection would have exposed the issue.

E. When installing utilities, priority shall be given to trades in the following order to prevent conflicts and optimize system installations: mechanical, plumbing, sprinkler, and electrical.

F. Contractors shall not rely on scaled dimensions and measurements. Contractors shall take actual measurements in the field (for material takeoffs, etc.).

G. Where items (architectural, equipment, fixtures, devices, etc.) are being removed, remove all appurtenances (associated architectural items, utilities, wire, conduit, pipe, etc) related or connected to (in, on, attached, or associated with) items indicated to be removed or demolished. Utilities shall be removed back to the source or active main / branch.

H. Protect installed items, equipment, finishes, etc. Repair / replace / restore conditions that are damaged, marred, disturbed, etc., as a result of work. This includes (but is not limited to) patching holes in partitions after items are demolished, capping utilities after removing branches, replacing damaged doors, replacing cracked glass or damaged windowsills etc.

I. Materials shall resist flame spread and smoke generation.

J. Contractor is responsible for coordinating between trades. Coordinate utilities, so they are installed in an orderly and uniform manner.

K. Contractor shall design around, coordinating, and installing all VA provided, expendable equipment i.e. soap dispenser, glove box, hand gel dispenser, sharps receptacle, paper towel dispenser, toilet paper dispenser, thermometer etc.

L. Contractor is responsible for designing around all VA provided / non-expendable equipment. Contractor shall assist in coordinating the installation of all VA provided / VA installed, non-expendable equipment. All building service equipment shall be provided by Contractor.

M. VA will remove existing equipment and furniture. Contractor shall remove any utilities or utility branches that will not be reworked/modified for the new equipment. Unused utilities shall NOT be abandoned.

N. Incorporate the attached “Misc. Comments for VA Master Spec (baseline)” into the VA

Master Spec sections.

O. Some of the work may be done after-hours or on weekends. Coordinate with COR for access during non-standard work hours.

P. Comply with facility infection control standards. Coordinate and perform a risk assessment (PCRA/ICRA/ILSM). Maintain temporary measures, such as negative air.

6. TYPICAL WORK CONDITIONS/CONTRAINTS:

A. Contractor must request (in writing) access to a work area 2 weeks before the date they wish to commence work. If conditions prevent the VA from turning over the requested work area, the VA shall notify the contractor.

B. Work shall be performed to minimize the disruptions to medical center operations and functions.

C. Unless noted otherwise on the drawings or otherwise coordinated, the contractor shall assume that work will be performed from 7am to 4pm and on weekends with the VA’s approval. VA may grant the contractor permission to work outside these normal project hours (as requested on a case-by-case basis).

D. Once construction starts, there shall be no lapse in work or days/shifts taken off until the area is complete. Sections/segments of a work area (including corridors) shall not appear to be setting inactive; there shall be substantial progress made each day/shift.

Coordinate areas of work and phases of construction with COR. Contractor shall professionally clean space and return it to normal VA operation at the end of each.

E. Contractor shall conform to the VA Medical Center’s Infection Control Policy (see

General Requirements Section 01 00 00). Contractor shall cover/bag supply diffusers, returns, and exhaust grilles. Contractor shall provide negative air machine(s) to ensure each partitioned workspace is negative. Contractor shall take the HEPA filtered negative air to the outside using rigid or flex duct. If the contractor cannot acquire outside access, or the flex run is greater than 75 feet, the contractor may flex the clean air to a general (non-medical treatment/suite) corridor. All elements must confirm to facility PCRA/ICRA/ILSM and be tailored to for mental health security concerns.

F. The contractor shall maintain fire protection throughout the entire construction space during renovation to maintain equivalent level of protection. The construction space temporary heat detector alarms shall be announced through the Medical Center Fire Alarm system. Any work or outages on the existing Medical Center Fire Alarm system must be coordinated with the COR and comply with VA Interim Life Safety Measure requirements and NFPA requirements. Also, Fire Alarm impact shall not be performed on Mondays or Fridays.

G. A minimum of 7 days is required for notification of shutdowns, outages, interruptions or fire alarm impact.

H. Contractor is responsible for all temporary measures & access (penetrations, patch back, window removal, rigid/sealed blank-offs, temporary barriers, etc.)

I. The interior of the medical center shall not be left open or exposed to outside / exterior weather, elements, bugs, vermin etc.

J. Contractor is responsible for providing and maintaining all temporary, dust proof partitions to segregate areas of work from surrounding areas, people, and VA property (furniture, supplies, equipment, etc.). Hard drywall with metal stud barriers (secured with safety head screws on all exposed fasteners) will be expected all areas of work.

For short duration work – less than a shift with 100% supervision the following option may be available with COR approval; Plastic / Poly (minimum 6 mil, black, fire rated) will be permitted for short term work (not more than an evening or weekend).

K. The VA will not be providing storage or a laydown area for this project.

L. Contractor is responsible for all cleaning and housekeeping. All flooring in construction areas must be protected with Ram Board or similar floor protection product, multiple layers may be required. The flooring in this area of the hospital is likely discontinued.

Each area shall be thoroughly cleaned to hospital standards before it is turned back over to the VA. Sheet vinyl cleaned / polished (sheet vinyl) according to the manufacturer’s recommendations and to match adjacent similar VA areas. Coordinate cleaning methods with EMS and Interior Designer. No dust, streaks, marks, or residue shall be left on any surface. Final dusting shall be done using a HEPA vacuum.

M. The TVHS campus is a full-service medical center offering a variety of inpatient, outpatient, and psychiatric care. Contractor shall plan and execute the work based on this occupancy.

N. Test and certify all systems upon completion, prior to requesting VA final inspection.

O. Contractor is completely responsible for ensuring the safety of the visitors, staff, and patients (including psychiatry patients) during this project. Contractor shall take all necessary steps and provide all temporary measures to eliminate hazards and control risks, including but not limited to barriers, blockades, fences, tape, signs, ramps, railings, covers, etc.

1) Temporary measures shall be coordinated with COR and in place prior to the beginning of demo/construction.

2) Contractor shall not leave tools/equipment unattended.

3) In unrestricted areas (i.e. locations accessible to patients, visitors, and non-engineering staff), contractor shall limit site supplies to manageable quantities of working materials that are actively being installed.

4) Contractor is responsible for inspecting and maintaining proper safety measures and temporary provisions.

5) Temporary measures shall prevent patient/staff/visitor access to construction areas, especially when construction sites are unattended.

6) Do not significantly inhibit visitor/staff/patient traffic in adjacent public corridors.

Contractor shall maintain easily accessible routes to medical center services.

Minimize effects of construction on walkways, pathways, routes, etc.

7. INDEX OF ATTACHMENTS

Attachment 1: Conceptual Drawing

8. RECORDS MANAGEMENT OBLIGATIONS

1. Applicability This clause applies to all Contractors whose employees create, work with, or otherwise handle Federal records, as defined below, regardless of the medium in which the record exists.

2. Definitions "Federal record" as defined in 44 U.S.C. § 3301, includes all recorded information, regardless of form or characteristics, made or received by a Federal agency under Federal law or in connection with the transaction of public business and preserved or appropriate for preservation by that agency or its legitimate successor as evidence of the organization, functions, policies, decisions, procedures, operations, or other activities of the United States Government or because of the informational value of data in them. The term Federal record:

I. Includes Veterans Health Administration (VHA)/VA Tennessee Valley

Healthcare System (VA TVHS) records.

II. Does not include personal materials.

III. Applies to records created, received, or maintained by Contractors pursuant to their VHA contract.

IV. May include deliverables and documentation associated with deliverables.

3. Requirements

I. Contractor shall comply with all applicable records management laws and regulations, as well as National Archives and Records Administration (NARA) records policies, including but not limited to the Federal Records Act (44 U.S.C. chs. 21, 29, 31, 33), NARA regulations at 36 CFR Chapter XII Subchapter B, and those policies associated with the safeguarding of records covered by the Privacy Act of 1974 (5 U.S.C. 552a).

II. In accordance with 36 CFR 1222.32, all data created for Government use and delivered to, or falling under the legal control of, the Government are Federal records subject to the provisions of 44 U.S.C. chapters 21, 29, 31, and 33, the Freedom of Information Act (FOIA) (5 U.S.C. 552), and the Privacy Act of 1974 (5 U.S.C. 552a), and must be managed and scheduled for disposition only as permitted by statute or regulation.

III. Contractor shall maintain all records created for Government use or created in the course of performing the contract and/or delivered to, or under the legal control of the Government, in accordance with Federal law. Electronic records and associated metadata must be accompanied by sufficient technical documentation to permit understanding and use of the records and data.

IV. Records may not be removed from the legal custody of VA TVHS or destroyed except in accordance with agency records schedules and with the written concurrence of the Head of the Contracting Activity. Any unlawful or accidental removal, defacing, alteration, or destruction of records must be reported to VA TVHS.

V. The Contractor shall immediately notify the Contracting Officer upon discovery of any inadvertent or unauthorized disclosures of information, data, documentary materials, records, or equipment. The Contractor shall not remove material from Government facilities or systems without express written permission of the Head of the Contracting Activity.

VI. The Contractor shall obtain Contracting Officer approval prior to engaging any subcontractor requiring disclosure of information, documentary material, and/or records generated under this contract.

VII. The Contractor shall use Government IT equipment only for purposes specifically tied to or authorized by the contract.

VIII. The Contractor shall not create or maintain records containing non-public VHA information not specifically tied to or authorized by the contract.

IX. The Contractor shall not retain, use, sell, or disseminate copies of any deliverable containing Privacy Act-protected information or information otherwise exempt from FOIA disclosure.

X. VHA/VA TVHS owns the rights to all data and records produced under this contract. All deliverables are the property of the U.S. Government, for which VHA shall have unlimited rights to use, dispose of, or disclose data as determined to be in the public interest.

XI. Training. All Contractor employees who create, work with, or otherwise handle records under this contract are required to complete VHA-provided records management training, including initial and any required refresher training.

STATEMENT OF WORK