36C24925R0061_1.docx

DOCX document 172 KB Posted

Attached to
Z1LB--626A4-26-203 Design Build (DB)-Main Entrance Traffic Improvements
Solicitation number
36C24925R0061
Issued by

About this file

This document is a Request for Proposal (RFP) for a Design-Build project for the Department of Veterans Affairs Tennessee Valley Healthcare System. The solicitation (36C24925R0061) seeks a Service-Disabled Veteran-Owned Small Business (SDVOSB) to provide design and construction services for Main Entrance Traffic Improvements at the Alvin C. York Campus in Murfreesboro, TN. The project involves installing traffic signaling mast arms, control wires, a right turn lane, engineered fill, curbing, striping, storm water piping, and related infrastructure improvements, with a total project magnitude between $500,000 and $1,000,000.

Key requirements include obtaining Tennessee Department of Transportation (TDOT) and City of Murfreesboro permitting, developing complete contract drawings and specifications, and performing construction within 365 calendar days after Notice to Proceed. Proposals are due on 11/06/2025 at 1:00 PM CT and will be evaluated using a Lowest Price Technically Acceptable (LPTA) method. Contractors must be certified in the SBA database as an SDVOSB, have relevant experience with similar healthcare facility projects, provide key personnel resumes, and submit past performance references. The project is specifically set aside for Service-Disabled Veteran-Owned Small Businesses under NAICS code 237310 with a size standard of $45 million.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C24925R0061

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5.

REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE

DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL

SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C24925R0061 X 626-26-1-4209-0001 626A4-26-203 Department of Veterans Affairs Network Contracting Office 9 (90C)

NCO 9

1639 Medical Center Parkway, Suite 204 Murfreesboro TN 37129 Department of Veterans Affairs Network Contracting Office 9 (90C)

NCO 9

1639 Medical Center Parkway, Suite 204 Murfreesboro TN 37129 Michael.R Brown 615-225-5939 Contractor shall provide design and construction services for Project 626A4-26-203, Design Build-Main Entrance Traffic Improvements. This project will involve a Design/Build Contractor to provide Architectural, Engineering and Construction services that, at a minimum, include the demolition, design, and construction to install mast arms, control wires and the expansion of turning lane in accordance the statement of work at the TVHS Alvin C. York Campus, 3400 Lebanon Pike, Murfreesboro, TN 37129. This project requires the contractor to furnish labor, materials, supervision and equipment necessary for a Design/Build project to properly prepare the site for improved exit and turning lane of the main entrance.

NAICS Code: 237310 Highway, Street, and Bridge Construction. The small business size standard is $45M.

PSC Code: Z1LB Maintenance Of Highways/roads/streets/bridges/railways

FAR 52.236-27 identifies date and time of Site Visit. There will only be one (1) site visit on this project scheduled for 10/10/2025 at 10:00 am CT, location BLDG 6 front steps.

To obtain clarifications and/or additional information concerning the contract requirement, specifications and/or drawings, submit a written Request for Information (RFI) via email to Michael R. Brown, Contracting Officer at Michael.brown1305@va.gov. RFI's must be specific in identifying section, paragraph, and page number and must be in question format. A form is attached for use. All RFIs submitted shall include the project number and title, contractor name, city and state, phone number, and email address, datesubmitted and RFI question(s). Questions received after 10/15/2025 at 1300CT will not be answered unless it is determined to be in the best interest of the government as deemed by the CO. Telephone requests will NOT be accepted.

In accordance with Public Law 109-461, this acquisition is 100% set-aside for Service-Disabled Veteran Owned Small Business (SDVOSB) concerns. In order to be eligible to receive an award under this solicitation, the SDVOSB contractor must be listed and viewable in the Small Business Search (SBA) located at https://search.certifications.sba.gov/ at of the time if offers due and at time award.

Offerors are advised that the fast-track reverification program ended September 30, 2012. Consequently, offerors in reverification status will not be eligible to submit offers for this project. In accordance with FAR

52. 204-7 System for Award Management (SAM), all prospective offerors must have an active SAM's registration at the time of offer and at the time of award.

This project is procured under FAR 15.101 Best value continuum. Evaluation Factors are listed in solicitation.

Submit one (1) electronic copy to Michael.brown1305@va.gov before the proposal due date/time in block 13.

Submit one (1) electronic copy of bid bonds before the proposal due date/time. No Exclusion to the solicitation is acceptable. Proposal must include the the entire solicitation 36C24925R0061 in the exact order posted.

X X 52.211-10 X 1 Electronic 13:00

CST

11-06-2025 X 120 Calendar Days

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE

NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND

TITLE OF PERSON AUTHORIZED TO SIGN OFFER

20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN

COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

Base Offer 1:

The Offeror must provide an offer response to the base offer. Failure to do so will result in a rejection of the offer.

626-3660162-4209-854200-3223 23NRNR000

90C Network Contracting Office 9 Department of Veterans Affairs Network Contracting Office (90C) 1639 Medical Center Parkway Suite 204 Murfreesboro TN 37129 90C FSC e-Invoicing Payment http://www.fsc.va.gov/fsc/einvoice.asp Invoice Setup Information 1-877-489-6135 Invoice must be submitted electronically

Setup 1-877-489-6135 Michael R.

Brown Contracting Officer

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
A.3 PRICE/COST SCHEDULE6
ITEM INFORMATION6
A.4 GENERAL INFORMATION7
A.5 STATEMENT OF WORK2
A.6 EVALUATION FACTORS11
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS15
2.1 52.201-1 ACQUISITION 360: VOLUNTARY SURVEY (SEP 2023)15
2.2 52.216-1 TYPE OF CONTRACT (APR 1984)15
2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)15
2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)16
2.5 52.228-1 BID GUARANTEE (SEP 1996)17
2.6 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021)17
2.7 52.233-2 SERVICE OF PROTEST (SEP 2006)18
2.8 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)18
2.9 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)18
2.10 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)19
2.11 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)19
2.12 PARTNERING20
REPRESENTATIONS AND CERTIFICATIONS21
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2025) (DEVIATION FEB 2025)21
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)25
3.3 52.204-29 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—REPRESENTATION AND DISCLOSURES (DEC 2023)27
3.4 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)29
3.5 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021)30
GENERAL CONDITIONS33
4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014)33
4.2 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB COVERED ENTITIES (DEC 2023)33
4.3 52.204-30 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—PROHIBITION (DEC 2023)34
4.4 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)39
4.5 52.219-28 POSTAWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JAN 2025)40
4.6 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020)43
4.7 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010)43
4.8 52.222-42 STATEMENT OF EQUIVALENT RATES FOR FEDERAL HIRES (MAY 2014)45
4.9 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)45
4.10 SUPPLEMENTAL INSURANCE REQUIREMENTS50
4.11 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)51
4.12 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020)52
4.13 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION)54
4.14 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)57
4.15 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)58
4.16 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)59
4.17 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)59
4.18 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020)59
4.19 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)61
4.20 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)61
4.21 VAAR 852.246-75 WARRANTY OF CONSTRUCTION—GUARANTEE PERIOD SERVICES (OCT 2018)62
DESIGN BUILD SPECIFICATIONS64
4.22 GENDER64
4.23 CONTRACTOR'S COST BREAKDOWN64
4.24 SCHEDULE OF PAYMENTS FOR DESIGN SERVICES64
4.25 OWNERSHIP OF ORIGINAL DOCUMENTS64
4.26 RETENTION OF REVIEW DOCUMENTS64
4.27 CONTRACT DRAWINGS AND SPECIFICATIONS GOVERNMENT FURNISHED PLANNING INFORMATION65
4.28 COORDINATION WITH MEDICAL CENTER65
4.29 RESPONSIBILITY OF THE DESIGN-BUILD CONTRACTOR65
SECTION D - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS67
5.1 RFI_626A4-26-203-DB Main Entrance Traffic Improvements 02.67
5.2 Contractor EMR Certification Form.67
5.3 UEI _ TAX ID.67
5.4 Specifications.67
5.5 Drawings_Sitework Concept 1.67
5.6 Drawings_Sitework Concept 2.67
5.7 P07_Wage Determination_2015-4647- 07-08-2025.67

A.3 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1.00
EA
__________________
__________________

The contractor shall provide all necessary architectural and engineering services as required to prepare complete contract drawings, specifications, technical reports, and cost estimates, including services throughout construction for "Main Entrance Traffic Improvements" at the historic Alvin C. York Campus of the VA Tennessee Valley Healthcare System, 3400 Lebanon Pike, Murfreesboro, TN 37129. The purpose of this project is to improve the flow and safety of egress from Veteran's Circle onto Highway 231. This will be accomplished by installing a right-hand turning lane and other measures determined by Tennessee Department of Transportation (TDOT) signal warrant analysis conducted March 6, 2025. Period of Performance is 365 calendar days after the Issuance of the Notice to Proceed (NTP) PRINCIPAL NAICS CODE: 237310 - Highway, Street, and Bridge Construction PRODUCT/SERVICE CODE: Z1LB - Maintenance of Highways, Roads, Streets, Bridges, and Railways

LOCAL STOCK NUMBER: 626A4-26-203

GRAND TOTAL
__________________

Page 1 of

A.4 GENERAL INFORMATION

The following documents must be included in the solicitation submission in the formats as stated:

-Note: The complete Solicitation 36C24925R0061 shall be returned in the same page order as posted in SAM with all attached documents. Failure to do so will be evaluated as non-responsive.

- One (1) electronic copy (only) of an original, fully completed and signed and dated SF 1442 Offer page (‘wet ink signature’), acknowledgment of all amendments issued by either completing block 19 of the SF1442 or completing blocks 15a, b, and c of the Amendment(s) and providing them with the SF 1442 Offer page.

- One (1) electronic copy of an original completed and signed SF 24 Bond or other allowable Security. Any missing elements of the bond submission could render the offeror ineligible and their offer will not be considered.

Offerors are responsible for insuring and verifying their offer and all required solicitation documents are received at the office and point of contact designated in block 8 of the SF 1442 and by the date and time specified in block 13A of the SF 1442 (subject to amendment).

The due date for proposals is 11/06/2025, at 1:00PM CT

PROJECT TITLE AND NUMBER: 626A4-26-203-DB Main Entrance Traffic Improvements PROJECT LOCATION: Tennessee Valley Healthcare System, Alvin C. York Campus, located at 3400 Lebanon Pike, Murfreesboro, TN 37129 MAGNITUDE OF CONSTRUCTION: $500,000.00 to $1,000,000.00 NORTH AMERICAN INDUSTRY CLASSIFICATION SYSTEM CODE: (NAICS): 237310 Highway, Street, and Bridge Construction SMALL BUSINESS SIZE STANDARD: $45 Million

TYPE OF SET-ASIDE: This solicitation is a 100% set-aside for SERVICE-DISABLED

VETERAN OWNED SMALL BUSINESS (SDVOSB).

Federal Holidays. Federal law (5 U.S.C. 6103) establishes the following public holidays for Federal employees: New Year’s Day, Birthday of Martin Luther King, Jr., Washington’s Birthday, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, and Christmas Day. Please note that most Federal employees work on a Monday through Friday schedule. For these employees, when a holiday falls on a non-workday -- Saturday or Sunday -- the holiday usually is observed on Monday (if the holiday falls on Sunday) or Friday (if the holiday falls on Saturday).

All contractors are required to complete the VA Privacy Training for Personnel without Access to VA Computer Systems or Direct Access or Use to VA Sensitive Information. A copy of the signed training must be submitted to the COR and uploaded into VA Talent Management System (TMS). Contractor employees shall not be considered government employees for any purpose under this contract. Changes to any resultant contract may only be made by a written modification which is formally executed by the contractor and the Contracting Officer.

DATABASE REGISTRATION INFORMATION

SYSTEM FOR AWARD MANAGEMENT (SAM) REGISTRATION: The Small Business Administration (Small Business Search) at website located at https://search.certifications.sba.gov/ and The Small Business Administration (Small Business Search) at website located at https://search.certifications.sba.gov/is the Official U.S. Government system that consolidated the capabilities of the Central Contractor Registration (CCR including FedReg), Online Representations and Certifications Application (ORCA), and the Excluded Parties List System (EPLS). Federal Acquisition Regulations require that federal contractors wishing to do business with the Government and bid on work shall have an active registration in SAM. If the Offeror does not have an active registration in the SAM database at the time of offer submission and are the apparently successful low offeror, the Contracting Officer shall prescribe a time within which the offeror shall have an active registration in SAM; otherwise, the Contracting Officer shall deem the offeror’s proposal non-responsive to the solicitation requirements and proceed to award to the next lowest offer.

THE EXCLUDED PARTIES LIST SYSTEM (EPLS): To ensure that the individuals or businesses providing services under the contract have not engaged in fraud or abuse regarding Sections 1128 and 1128A of the Social Security Act regarding federal health care programs, the contractor is required to check the Excluded Parties List System (EPLS) located at https://sam.gov for each person or business providing services under this contract. During the performance of this contract the Contractor is prohibited from using any individual or business listed on the List of Excluded Individuals/Entities.

VETS-4212 REPORTING REQUIREMENT: Contractors are required to submit a required annual Form VETS-4212, Federal Contractor Veterans' Employment Report in all cases where the contractor or subcontractor has received an award of $150,000 or more in any fiscal year.

Contracting Officers are prohibited from awarding a contract to a contractor that has not submitted a required VETS-4212 Report with respect to the preceding fiscal year if the contractor was subject to the reporting requirement of 38 U.S.C. 4212(d). Submit this report as soon as possible, if not already submitted, to avoid delays in the contract award process. For more information on this requirement and/or for completing the web-based reporting form, visit the following website https://www.dol.gov/agencies/vets/programs/vets4212. See FAR provision 52.222-38, Compliance with Veterans' Employment Reporting Requirements (FEB 2016) under the Representations, Certifications and Other Statements of Offerors, and FAR clause 52.222-37, Employment Reports on Veterans (FEB 2016) under the General Conditions.

28.203-2.

PERFORMANCE AND PAYMENT BONDS: In accordance with Contract Clause 52.228-15, and FAR 28.102, Contractors are reminded that any amount awarded over $35,000.00 shall require a Payment Bond (SF 25A), and awards exceeding $150,000.00 shall require both Payment and Performance Bonds (SF 25). Payment and Performance bonds are due no later than 10 days after notification of award. Bonds must be provided with original ‘wet ink’ signatures - no white-outs or other corrections are allowable. Copies and facsimiles of bonds shall not be accepted.

SECURITY

BACKGROUND INVESTIGATIONS: All contractor employees are subject to the same level of investigation as VA employees who have access to VA Sensitive Information. The level of background investigation is commensurate with the level of access needed to perform the statement of work. This requirement is also applicable to all subcontractor personnel requiring the same level of access.

Levels and associated types of Background Investigations:

. If the project requires that workers have only limited physical access to the VA facility for a period of one year or less, a local flash badge with fingerprint check is issued.

. If the project requires that workers require un-supervised, logical and/or physical access for 180 consecutive or aggregate days in a 365-day period, over a 3-year period, a background investigation may be required (Special Agency Check (SAC)) which must be completed prior to being allowed access.

. If the project requires that workers have access to a VA Network (such as the Building Management System) or un-supervised, full-time, logical, and/or restricted physical access for more than 6 months or more than 180 aggregate days in a one-year period, a background investigation is required (Special Agency Check and National Agency Check with Written Inquiries (NACI)) and access is not allowed until a favorable SAC completion.

All costs for SAC and NACI checks are borne by the contractor. The VA may at its discretion make deductions against the contract in order to recoup the investigation costs. The estimated cost for a SAC is $30.00 per employee and the estimated cost for a NACI check is $408.00 per employee (subject to change at any time).

MEDICAL CENTER ACCESS: Anyone participating in the site visit, or for any other reason that involves visiting the medical center related to this solicitation, must have a valid ID on their person and their vehicle must be properly registered and insured. Visitors are prohibited from possessing weapons while on a federal installation (See 18 USC 930 – Possession of Firearms and Dangerous Weapons in Federal Facilities). Handheld cellphone usage or texting while driving is also prohibited. All VA Medical Centers and associated properties are Federal Property.

PRIVACY TRAINING: All workers regardless of project length must take VA Privacy Training which will be coordinated after project award with the Contracting Officer’s Representative.

E-VERIFY SYSTEM: Companies awarded a contract with the federal government shall enroll in E-Verify within 30 days of the contract award date. They shall also begin using the E-Verify system to confirm that all of their new hires and their employees directly working on federal contracts are authorized to legally work in the United States. E-Verify is an Internet-based system that allows an employer, using information reported on an employee's Form I-9, to determine the eligibility of that employee to work in the United States. There is no charge to employers to use E-Verify. (FAR 52.222-54).

PRIME CONTRACTOR INFORMATION- SAFETY OR ENVIRONMENTAL VIOLATIONS AND

EXPERIENCE MODIFICATION RATING INFORMATION

All Offerors/Offerors shall submit information pertaining to their past Safety and Environmental record (using the attached EMR information/data form). The information must contain a certification that the offeror/offeror has no more than three (3) serious, or one (1) repeat or one

(1) willful OSHA or any EPA violation(s) in the past three years. If such certification cannot be made, a Offeror/Offeror shall explain why and submit as much information as possible regarding the circumstances of its past safety and environmental record, including the number of EPA violations and/or the number of serious, repeat, and/or willful OSHA violations, along with a detailed description of those violations.

All Offerors/Offerors shall submit information regarding their current Experience Modification Rate (EMR). This information shall be obtained from the Offerors/Offeror’s insurance carrier and be furnished on the insurance carrier’s letterhead. If a Offeror/Offeror’s EMR is above 1.0, Offeror/Offeror must submit a written explanation of the EMR from its insurance carrier furnished on the insurance carrier’s letterhead, describing the reasons for the elevated EMR and the anticipated date the EMR may be reduced to 1.0 or below.

Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc.

(NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI.

Note: Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and Puerto Rico shall obtain their EMR rating from their state-run worker’s compensation insurance rating bureau. If the NCCI cannot issue an EMR because the Offeror/Offeror lacks insurance history, Offeror/Offeror shall submit a letter indicating so from its insurance carrier furnished on the insurance carrier’s letterhead and include a letter from the NCCI indicating that it has assigned Offeror/Offeror a Unity Rating of 1.0. The above information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases, will be used to make an initial Determination of Responsibility.

This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.

CONFORMANCE WITH ENVIRONMENTAL MANAGEMENT SYSTEMS: The Contractor shall perform work under this contract consistent with the relevant policy and objectives identified in the agency, organizational, or facility Green Environmental Management System (GEMS) applicable for the contract. The Contractor shall perform work in a manner that conforms to all appropriate Environmental Management Programs and Operational Controls identified by the agency, organizational, or facility GEMS, and provide monitoring and measurement information as necessary for the organization to address environmental performance relative to the environmental, energy, and transportation management goals. In the event an environmental nonconformance or noncompliance associated with the contracted services is identified, the contractor shall take corrective and/or preventative actions. In the case of a noncompliance, the Contractor shall respond and take corrective action immediately. In the case of a nonconformance, the Contractor shall respond and take corrective action based on the time schedule established by the facility GEMS Coordinator. In addition, the Contractor shall ensure that their employees are aware of the roles and responsibilities identified by the environmental management system and how these requirements affect their work performed under this contract.

All on-site contractor personnel shall complete yearly EPA sponsored environmental training specified for the type of work conducted on-site. Upon inclusion in the contract, the Contracting Officer's Representative will verify that all contractor personnel have acquired EMS Awareness Training at their appropriate site or location.

REFERENCES TO VA ENGINEER, RESIDENT ENGINEER, SENIOR RESIDENT ENGINEER,

OR PROJECT MANAGER: Any reference contained within contract specifications and/or drawings to the “VA Engineer”, “Resident Engineer”, “Senior Resident Engineer”, “Project Manager”, or their abbreviations are to be replaced with “Contracting Officer’s Representative

(COR)”.

PAYMENT FOR MATERIALS STORED OFF-SITE: Payment in advance of installation for materials stored off-site is not authorized under this contract unless otherwise approved by the Contracting Officer.

SCHEDULE OF MATERIAL SUBMITTALS: The submittals contemplated by FAR 52.236-5, Material and Workmanship, are listed on the Schedule of Material Submittals in the Specifications, if provided. The schedule is for reference only – the selected contractor is responsible to provide all submittals required by the contract.

REVIEW REQUIRED REGISTRATION WITH CONTRACTOR PERFORMANCE

ASSESSMENT SYSTEM (CPARS)

As prescribed in Federal Acquisition Regulation (FAR) Part 42.15, the Department of Veterans Affairs (VA) evaluates contractor past performance on all contracts that exceed $750,000 and shares those evaluations with other Federal Government contract specialists and procurement officials. The FAR requires that the contractor be provided an opportunity to comment on past performance evaluations prior to each report closing. To fulfill this requirement VA uses an online database, CPARS, which is maintained by the Naval Seal Logistics Center in Portsmouth, Virginia. CPARS has connectivity with the Past Performance Information Retrieval System (PPIRS) database, which is available to all Federal agencies. PPIRS is the system used to collect and retrieve performance assessment reports used in source selection determinations and completed CPARS report cards transferred to PPIRS. CPARS also includes access to the federal awardee performance and integrity information system (FAPIIS).

FAPIIS is a web-enabled application accessed via CPARS for contractor responsibility determination information.

Each contractor whose contract award is estimated to exceed $750,000 is required to register with CPARS database at the following web address: www.cpars.csd.disa.mil. Help in registering can be obtained by contacting Customer Support Desk at 207-438-1690.

Registration should occur no later than thirty days after contract award and must be kept current should there be any change to the contractor's registered representative.

For contracts with a period of one year or less, the contracting officer will perform a single evaluation when the contract is complete. For contracts exceeding one year, the contracting officer will evaluate the contractor's performance annually. Interim reports will be filed each year until the last year of the contract, when the final report will be completed. The report shall be assigned in CPARS to the contractor's designated representative for comment. The contractor representative will have thirty days to submit any comments and re-assign the report to the VA contracting officer.

Failure to have a current registration in the CPARS database, or to re-assign the report to the VA contracting officer within those thirty days, will result in the Government's evaluation being placed on file in the database with a statement that the “contractor failed to respond.”

NATIONAL ARCHIVES AND RECORDS ADMINISTRATION RECORDS POLICIES

1. Contractor shall comply with all applicable records management laws and regulations, as well as National Archives and Records Administration (NARA) records policies, including but not limited to the Federal Records Act (44 U.S.C. chs. 21, 29, 31, 33), NARA regulations at 36 CFR Chapter XII Subchapter B, and those policies associated with the safeguarding of records covered by the Privacy Act of 1974 (5 U.S.C. 552a). These policies include the preservation of all records, regardless of form or characteristics, mode of transmission, or state of completion.

2. In accordance with 36 CFR 1222.32, all data created for Government use and delivered to, or falling under the legal control of, the Government are Federal records subject to the provisions of 44 U.S.C. chapters 21, 29, 31, and 33, the Freedom of Information Act (FOIA) (5 U.S.C. 552), as amended, and the Privacy Act of 1974 (5 U.S.C. 552a), as amended and must be managed and scheduled for disposition only as permitted by statute or regulation.

3. In accordance with 36 CFR 1222.32, Contractor shall maintain all records created for Government use or created in the course of performing the contract and/or delivered to, or under the legal control of the Government and must be managed in accordance with Federal law. Electronic records and associated metadata must be accompanied by sufficient technical documentation to permit understanding and use of the records and data.

4. The Government and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Records may not be removed from the legal custody of the Government or destroyed except for in accordance with the provisions of the agency records schedules and with the written concurrence of the Head of the Contracting Activity (HCA). Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. In the event of any unlawful or accidental removal, defacing, alteration, or destruction of records, the contractor must report it to Government Contracting Officer. The agency must report promptly to NARA in accordance with 36 CFR 1230.

5. The Contractor shall immediately notify the appropriate Government Contracting Officer upon discovery of any inadvertent or unauthorized disclosures of information, data, documentary materials, records or equipment. Disclosure of non-public information is limited to authorized personnel with a need-to-know as described in the [contract vehicle]. The Contractor shall ensure that the appropriate personnel, administrative, technical, and physical safeguards are established to ensure the security and confidentiality of this information, data, documentary material, records and/or equipment is properly protected. The Contractor shall not remove material from Government facilities or systems, or facilities or systems operated or maintained on the Government’s behalf, without the express written permission of the Head of the Contracting Activity. When information, data, documentary material, records and/or equipment is no longer required, it shall be returned to the Government’s control, or the Contractor must hold it until otherwise directed. Items returned to the Government shall be hand carried, mailed, emailed, or securely electronically transmitted to the Contracting Officer who awarded the contract. Destruction of records is EXPRESSLY PROHIBITED unless in accordance with Paragraph (4).

6. The Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under, or relating to, contracts.

The Contractor (and any sub-contractor) is required to abide by all Government guidance for protecting sensitive, proprietary information, classified, and controlled unclassified information.

7. The Contractor shall only use Government IT equipment for purposes specifically tied to or authorized by the contract and in accordance with the project location VA Medical Center’s written policy.

8. The Contractor shall not create or maintain any records containing any non-public Government information that are not specifically tied to or authorized by the contract.

9. The Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected from public disclosure by an exemption to the Freedom of Information Act.

10. The Government owns the rights to all data and records produced as part of this contract.

All deliverables under the contract are the property of the U.S. Government and shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest. Any Contractor rights in the data or deliverables must be identified as required by FAR 52.227-11 through FAR 52.227-20.

11. Training. All Contractor employees assigned to this contract who create, work with, or otherwise handle records are required to take VHA-provided records management training, Talent Management System (TMS) Item #3873736, Records Management for Records Officers and Liaisons. The Contractor is responsible for confirming training has been completed according to agency policies, including initial training and any annual or refresher training. All training shall be coordinate with the Contracting Officer’s Representative assigned to the contract.

Project 626A4-26-203 Design/ Build Main Entrance Traffic Improvements

Page 1 of

A.5 STATEMENT OF WORK

1. GENERAL SCOPE OF WORK:

Provide design and construction services to “Main Entrance Traffic Improvements” at Veteran’s Affairs (VA) Tennessee Valley Healthcare System, Alvin C. York Campus, located at 3400 Lebanon Pike, Murfreesboro, TN 37129, in accordance with this statement of work, specifications and vendor equipment drawings.

Furnish labor, materials, supervision, and equipment necessary for a Design/Build project to properly prepare the site for improved exit and turning lane of the main entrance. Work includes site and utility prep per manufacturer’s requirements to install system and provide testing/certification for proper operation. VA will maintain all medical center operations during this work. Temporary measures will be provided by contractors to maintain medical center operations including, but not limited to, entry and exit to the facility Work includes, but is not limited to, demolition, industrial hygiene, structural, civil, paving, storm water, lighting, traffic controls, electrical power & systems, etc.

The conceptual drawings represent the VA’s intent for this space (Reference Attachment 1). The VA project concept is included for clarification and to delineate the project objectives/constraints. The Contractor shall not rely on the preliminary VA concept as a final design. Contractor shall develop a design with a VA design team to ensure all needs and project objectives are met. The design consultant shall provide the necessary architectural and engineering services required to prepare a complete design (stamped contract drawings, specifications, technical reports, cost estimates, inspections, quality assurance, testing, etc.) and construction period services to ensure the successful completion of the project. The contractor shall provide the VA with certifications and standard VA warranties. During Design Development (DD) the contractor is responsible for independently analyzing conditions, needs, systems, and developing unique, optimal proposals to achieve project objectives. All design and construction work shall be complete within 365 calendar days, including final inspection, punch list corrections, testing, and closeout/ release of claims.

2. STATEMENT OF PROJECT OBJECTIVES:

A. Install “Mast Arm(s)” traffic signaling at intersection US Highway 231 and Veterans Circle. (Two mast arm base/ poles will likely be necessary, with a total of 3 mast arms).

B. Install a control wire(s)/ fiber and all necessary appurtenances from new traffic signal back to intersection of Compton/W Thompson Ln and US Highway 231 and fully integrate the new traffic signal to the City of Murfreesboro traffic management system (approx. 1,500 LF). Directional/ Horizontal boring will be required to connect the new poles with electricity and control wiring under roadways. Consult with local and state engineering for conduit and conductor sizing. The signal wiring may be installed overhead between intersections (Compton Rd to Veterans Circle), if approved by the City of Murfreesboro and MTEMC, if not approved overhead, signal wire may be installed underground per specification. Wiring between new/proposed mast arms (intersection of Hwy 231 and Veterans Circle) will be installed underground and ran through pole bases.

C. Install a right turn lane for egress out of Veterans Circle onto US Highway 231 per TDOT Standards for local streets (Typical: 8” subbase- 3” BM binder, 2” D topping for new lanes) approx. 250 L.F. X 12’ Width. This item will be a deduct alternate. Lane length will be shortened to 75’ X12’ as deduct alternate.

D. Install approximately 150 cubic yards of engineered fill (6” minus @ 98% compaction) as needed to widen the turning lane.

E. Install all necessary curbing and Thermoplastic/ Reflective striping (per TDOT Standards).

F. Install all necessary storm water piping and structures (per TDOT specification).

G. All lighting, sidewalks, curbing, flower beds, flagpole bases, etc. that are removed or damaged to accommodate new signals and turning lane shall be reinstalled in kind per VA specifications.

H. Turning lanes shall include bollard pockets to limit access when required. Contractor shall provide associated bollards and bollard storage stands to VA.

I. Contractor shall locate all utilities before construction (Tennessee One Call/ 811) and protect utilities during construction. Utilities on the VA Campus may not be under the jurisdiction of Tennessee One Call and the contractor shall hire a 3rd party utility locating contractor to identify any utilities on the VA Campus. All utilities shall be protected from damage during construction. It is the responsibility of the contractor to repair any damaged utilities/conduit back to VA, State, and/ or Local specifications.

J. All new construction shall match the existing architecture to maintain historical integrity of the campus.

K. The contractor shall coordinate and provide all necessary permitting requirements from the Tennessee Department of Transportation (TDOT) and the City of Murfreesboro. The Architect/Engineer (A/E) will work for the Prime Contractor and must be on the approved list of both the City of Murfreesboro and TDOT for the traffic work listed above in this Scope of Work. It will be the responsibility of the A/E to coordinate and confirm approval of this design from the City of Murfreesboro and State of Tennessee Engineering Departments.

3. DESIGN:

A. All work shall be conducted with the guidance and oversight of the prime contractor. A/E shall work with VA design team to ensure VA satisfaction with design intent.

B. The A/E shall have be accredited or have personnel that are on the approved list for traffic/signal design for the City of Murfreesboro and TDOT.

C. STATEMENT of A/E TASKS:

1) The A/E shall furnish all services for complete design development, construction documents, and construction period services (including final inspection) by professionally licensed Architects and Engineers. The contractor will be required to have A/E stamped construction documents for all work. A/E will assist with providing the necessary professional design services required to complete construction

a. Perform a complete site survey to include a thorough investigation of existing conditions, typical construction type and variations, finishes, verifying and analyzing utility systems for affected areas and utilities traversing through affected areas to accurately document and convey space dimensions on measured drawings. This information provides the necessary basis for the preparation of Design Development.

2) The A/E shall provide cost estimation, project scheduling & phasing, and construction period services prior to beginning construction.

3) In addition to the prime contractor’s quality control efforts, the A/E shall develop and provide a quality control plan and services throughout construction. Quality control plan, inspection / observations and tests shall be included in the closeout documents.

4) The A/E will be required to provide a complete set of contract documents and as built documents (drawings in AutoCAD (.dwg) and specifications in paper and electronic formats (.docx and pdf).

5) The contractor shall provide competent design and construction period services utilizing individuals who are adequately knowledgeable of the various design disciplines including but not limited to architectural and engineering of structural, civil, mechanical, electrical, and special systems as required by the project. Changes in personnel from those who are proposed in negotiations and at kick-off meetings will not be allowed without VA approval. The services of an industrial hygienist familiar with hazardous materials will be utilized in the event that these materials are found. The registered individuals who stamp the completed documents shall accomplish engineering design work.

6) Design in collaboration with equipment manufacturers and manufacturer recommendations.

7) TDOT and the City of Murfreesboro must give approval to begin work in the Right of Way (ROW). The contractor shall coordinate with VA COR at a minimum of 2-weeks prior to commencement of work.

8) Attached concept sketches 1 & 2 are conceptual in nature and do not reflect the exact location(s) of where the City/ State will require the mast style pole bases to be located. The TDOT approved engineer will coordinate with the local and state authorities to get exact mast arm locations, stop bar locations, etc.

D. STATEMENT OF DESIGN BUILDER TASKS:

1) The intent is to fast-track (expedite) the completion of the signaling for Ingress and Egress Safety. Design and construction can overlap but must have VA approved CDs within 60 days of notice to proceed. Demolition and construction in space may begin when the project construction documents CDs have been reviewed and approved by the COR.

2) The Contractor shall furnish the following services for a complete design and construction period services including final inspection and testing:

a. The contractor shall thoroughly investigate all areas to verify conditions, make accurate material takeoffs, and verify all details (break points, transitions, etc.) and required patch-back. Contractor will be permitted to take sample tear-offs / demolition to verify resulting substrate conditions and required patch-back. It is the contractor’s sole responsibility to accurately investigate demo, substrate, and patch-back conditions and accurately determine/estimate material and labor requirements. Change orders will not be granted for supposed unforeseen substrate conditions. Since VA permits inspection / sample removals to determine conditions, any resulting conditions will not be considered as concealed or unforeseen. Licensed commercial contractors, with CIVIL experience, will be expected to be very familiar with their work/trade disciplines and should be able to accurately project this work given the level of exploratory investigation being permitted by the VA. If a contractor is not confident with their projections / estimations, then they should not bid on the work. Contractors and subcontractors that submit pricing / bids will accept these conditions.

b. The contractor shall comply with all manufacturers’ directions and instructions.

c. Remove demolished utilities to nearest active line or source (i.e. panel for wire, branch main, etc.). All abandoned utilities to be removed.

d. Contractors will be expected to minimize the impact to the medical center. Contractors shall coordinate and perform work so as to minimize disruptions to medical center operations. Some work may be performed after normal hours of operation if deemed necessary by the VA. Normal working hours for the VA are 7:00 AM – 5:00 PM CST.

e. The contractor is responsible for all temporary measures to enable work, including but not limited to coordination, detour and construction signs, temporary barriers, negative air, infection control, etc.

f. Design and construct within the obligated project budget / funding limitations. Contractor and the contractor’s AE shall coordinate cost control measures to design within funding limits. Cost control alternatives shall be explored during Design Development (DD’s). The contractor shall employ a system of measures, such as timely estimates, cost control meetings, effective product and material selection, efficient management of labor/ trades, reduction of overall time/ critical path, etc.

g. Develop and execute a quality assurance (QA/QC) plan that establishes the design/build team and method of review for the project submission packages, plans and specifications. The project QA/QC process shall be a rigorous, thorough review and coordination effort. QA/QC team members shall be led by a senior mechanical and electrical designer with oversight from a project QA project manager (who is not the project Superintendent or PM). The QA/QC plan shall be submitted to the VA along with the project schedule. Within 14 calendar days after receipt of Notice to Proceed, the Contractor shall submit a detailed QA/QC plan describing each QA/QC task that will be taken during the development of the various design submission packages and the name of the A/E’s team member(s) responsible for QA/QC. The QA process shall produce deliverables included with each submission package, including but not limited to redline mark-ups and QA issue tracking sheets and a QA overview/narrative. Upon its completion, each task shall be initialed and dated by the responsible QA/QC team member. A 100% completed QA/QC plan, with all items resolved/initialed/dated shall be submitted with the final construction document submission package.

E. BASIS FOR DESIGN:

1) Department of Veterans Affairs standards may be obtained from the Internet. http://www.cfm.va.gov/til/.

2) Tennessee Department of Transportation TDOT https://www.tn.gov/tdot/engineering-division

3) City of Murfreesboro TN traffic division rbalachandran@murfreesborotn.gov

4) Compliance to standards listed in Guidelines and Standards will be reflected in the completed design and construction documents. Conflicting criteria shall be brought to the attention of VA.

F. DETAILED DESIGN SUBMISSION REQUIREMENTS:

1) Program Guide PG-18-15 establishes the guidelines for the A/E submissions. These guidelines indicate a minimum level for submission compliance, which may not be adequate for certain types of design. In some instances, in which critical decisions need to be made, sufficient and relevant information must be provided timely in order for the design to progress to meet certain milestone dates.

This is the start of the file's text. The full file is on GovTribe.