This document is an amendment to a solicitation for fire and smoke damper inspection and testing services at multiple Department of Veterans Affairs medical campuses. The key services required include conducting technical and visual inspections of all fire and smoke dampers and associated equipment at two campuses comprising a total of 15 buildings, and mechanically operating dampers to test functionality. The quote deadline is extended to August 14, 2023 at 1:00 pm CST by this amendment. Drawings of some buildings are available while others are still being located. A prior inspection report and list of any inaccessible dampers from 2017 will be provided to the awarded contractor. Questions were submitted and answered relating to qualifications, onsite presence, and scope of work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24923Q0504_1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7.
ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF
PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE
OF YOUR
ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERE
D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED
STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF
CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF
SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) Department of Veterans Affairs Network Contracting Office 9 (90C)
NCO 9
1639 Medical Center Parkway, Suite 400 Murfreesboro TN 37129 90C Network Contracting Office 9 Department of Veterans Affairs Network Contracting Office (90C) 1639 Medical Center Parkway Suite 400 Murfreesboro TN 37129 To all Offerors/Bidders
36C24923Q0504 08-04-2023
X X X
See CONTINUATION Page This amendment is set forth as follows:
1. The purpose of this RFQ amendment is to extend the quote deadline to August 14th, 2023 at 1:00 pm CST.
2. Contractor Questions and the Government's Response to date are found on the attached pages.
3. The questions submission period in the solicitation remains unchanged.
Jennifer Harper Contracting Officer
CONTINUATION PAGE
Vendor Questions/Government Answers
1. Is there a current drawing showing location of dampers?
Government Response: We have SOC drawings from 2017 Bowling Campus and buildings 1, 2, 3, 4, 16, 17, 25, 27, 28, 29 at Sousley campus. Bldgs. 201, 202 and 206 are new buildings and as of 8/4/2023 we are trying to locate those drawings.
2. Is there a list of dampers that could not be inspected due to access issues?
Government Response: We have a list from 2017 inspections that shows one damper at Sousley campus that could not be inspected. Keep in mind construction projects have taken place over the past 6 years and could change this number.
3. Can you provide the last Damper inspection report?
Government Response: Yes we can provide when contract is awarded.
4. Are there any minimum qualifications for the Fire Protection Engineer?
Government Response: Must have certification as a Professional Engineer and specializes in fire safety, protection, prevention, and suppression technologies.
5. Is the Fire Protection Engineer required to be onsite for the inspection?
Government Response: Fire protection engineer is not required to be onsite for inspections.
6. How many dampers are known to need repairs at this time?
Government Response: Zero are known at this time.
7.How many buildings containing dampers for inspection does each campus comprise of?
Government Response:
1. Troy Bowling Campus- 2 buildings
2. Franklin R Sousley Campus- 13 buildings 8.How many of the total dampers will need building alterations (wall or ceiling, etc.) in order for us to access and inspect?
Government Response: We have a list from 2017 inspections that shows one damper at Sousley campus that could not be inspected. Keep in mind construction projects have taken place over the past 6 years and could change this number.
9. Will complete damper location drawings be provided for each floor from each building, prior to start of project?
Government Response: We have SOC drawings from 2017 Bowling Campus and buildings 1, 2, 3, 4, 16, 17, 25, 27, 28, 29 at Sousley campus. Bldgs. 201, 202 and 206 are new buildings and as of 8/4/2023 we are trying to locate those drawings.
10.Will the prior damper inspection and testing reports be provided?
Government Response: Yes we can provide when contract is awarded.
11.How many dampers were labeled as “inaccessible” per each facility?
Government Response: We have a list from 2017 inspections that shows one damper at Sousley campus that could not be inspected. Keep in mind construction projects have taken place over the past 6 years and could change this number.
12.What repairs (if any) are included in the project’s scope of work?
Pertaining to fire and smoke dampers this contract is for inspect and test only. Conduct technical, visual inspections and test (mechanically operate) all fire and smoke dampers and associated equipment.
13. Is the FPE required for damper testing and inspection? It seems like this maybe a copy/paste error from a previous solicitation. An FPE is not required to test dampers. Please clarify.
Government Response: Fire protection engineer is not required to be onsite for inspections but must be obtained for documentation, accuracy of inspection, testing and all reports.
The purpose of this RFQ amendment is to extend the quote deadline to August 14th, 2023 at 1:00 pm CST and to post contractor questions with the Government’s response.