36C24922B0031 0001.docx

DOCX document 761 KB Posted

Attached to
Z1DA--626-23-1-4274-0001 - 626-21-103 - Apheresis Photopheresis Unit
Solicitation number
36C24922B0031
Issued by

About this file

This document contains questions and answers related to a federal solicitation for construction services. The solicitation is to construct an apheresis photopheresis unit at a Department of Veterans Affairs medical center. It involves renovating existing spaces and constructing new walls, doors and casework. Submittals are due within 30 days of award and work must be completed within 180 days of receiving notice to proceed, with the potential for time extensions depending on material lead times. The responses provide additional details on fixture types, construction phasing, work hours in occupied areas, fire alarm device relocation and ceiling lift engineering requirements.

View the file

Other files

File Type Posted
Color Board.pdf PDF
36C24922B0031.pdf PDF
Specs Apheresis Photopheresis Unit 626-21-103.pdf PDF
WD TN20220178 09022022.pdf PDF
Drawings Apheresis Photopheresis 626-21-103.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7.

ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF

PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE

OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:

Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERE

D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED

STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF

CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF

SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 626-23-1-4274-0001 626-21-103 90C Department of Veterans Affairs Network Contracting Office 9 (90C)

NCO 9

1639 Medical Center Parkway, Suite 400 Murfreesboro TN 37129 90C Network Contracting Office 9 Department of Veterans Affairs Network Contracting Office (90C) 1639 Medical Center Parkway Suite 400 Murfreesboro TN 37129 To all Offerors/Bidders

36C24922B0031 11-22-2022

X x x

** HOUR &

DATE for Bids is NOT extended

626-3630162-4274-854200-3220 23NR0JA16

x The purpose of this amendment is to provide Questions (RFIs) and Answers received during the RFI period.

Michael Brown Contracting Officer Questions and Answers 36C24922B0031 – Construct Apheresis Photopheresis Unit

RFI 001: Will STARC Panels be allowed for ICRA Temporary Barriers?

ANSWER - Yes

RFI 002: Contractor is concerned with the 180 POP regarding material procurement. Specifically, the lead time for Power coated Stainless steel casework, signage, availability of specific colors of flooring, HM/AL door frames and wood door slabs, etc.

Would the government consider delaying the start of the POP until submittals are approved, and lead times are established, or long lead materials are onsite?

ANSWER - 180 days POP total. Suspension of work may be permitted depending on material lead times. All submittal time to be subtracted from total POP days (ie if submittals take 30 days and suspension of work issued due to extensive lead times on materials, remaining POP is 150 days).

RFI 003: Sheet AD102 Note 3 in Toilet rooms calls for removal of plumbing fixture. Detail 3/PD101 graphically represents a bathtub.

Is this a plastic or cast-iron fixture?

ANSWER - Cast-iron

RFI 004: Sheet AD103 denotes areas of work to support 4th floor utility connections.

What are the working hours for the contractor in these areas?

ANSWER - In areas outside of the denoted construction area, work should be completed between 4:00 pm to 7:30 am.

RFI 005: Applies to Rooms C460, C459, and C458. Detail 4/A101 graphically shows two procedure lights (1) Exam 409 and (1) Exam 411. 2/E103 indicates that these procedure lights are existing.

Can the Government confirm that these are existing fixtures?

ANSWER - These are new lights; the lights are government furnished equipment, but the mounting structure is to be engineered and provided by the contractor.

RFI 006: If the procedural lights in C460, C459, C458 are existing fixtures do they remain in place or is the government removing and reinstalling the fixtures?

ANSWER - NA

RFI 007: A601 Note C calls for terminated stops on all new frames.

Can Government verify that Hospital Stops with 45 deg angle are require for all new HM Frames?

ANSWER - They are required at all frames, unless noted otherwise.

RFI 008: A601 Note K door slab finish color shall match the same color as adjacent doors.

What is the color of the adjacent doors?

ANSWER - Typical laminated finish for door slabs is Bannister Oak

RFI 009: A601 is there a minimum STC rating for the sliding doors?

ANSWER - 45 (see spec sheet 08 11 13-3)

RFI 010: Detail 12/I-201 illustrates a patient lift system.

Which room(s) is this to be installed?

ANSWER - One of the MOHS rooms will require a lift – I need to verify with the doctor which room will get the lift.

RFI 011: On sheet 1-201 Detail (12) Typical Ceiling Lift Mounting Detail. The Note Calls out for “SUPPORTS AND ANCHORAGE FOR LIFT SYSTEMS ARE THE RESPONSIBILITY OF THE CONTRACTOR AND MANUFACTURER AND MUST BE DESIGNED BY A STRUCTURAL ENGAGED BY THE MANUFACTURER.

Will these drawings and design require an engineering stamp?

ANSWER - Yes

RFI 012: Phasing Requirements.

Will there be any phasing requirements for the project?

ANSWER - The project was not designed to be worked in phases.

RFI 013: If phasing is required how much delay should the contractor anticipate between phases?

ANSWER - NA

RFI 014: Will a Pre-TAB be required for the project?

ANSWER - YES

RFI 015a: Detail (1) on Sheet A-102 requires a new door C-458A to be installed into an existing wall. During the site visit it was observed that there is currently a fire strobe and audible device in the location.

Will the Fire device need to be relocated for installation of the new door?

ANSWER - Yes, the fire device would need to move to the left or the right of the new door but should not be located above the door.

RFI 015b: For door C-458A is the contractor to assume there is any electrical or plumbing in the wall?

ANSWER - There will be some MEP in the wall, locate the door to minimize conflict with existing MEP. Verify with COR once wall is opened from within the room.

RFI 016: During the site visit access to Room C-481 Photopheresis was not available.

Can the government please provide pictures of the interior of room C-481?

ANSWER - See pics below

RFI 017: Will the demolition of the existing Med Gas require recertification of the system?

ANSWER - Yes

RFI 018: Is night shift or afterhours work anticipated?

ANSWER - There should be minimal afterhours or night shift work. Work with the COR to complete as much work as possible during normal business hours.

RFI 019: Economic Price Adjustment for Labor and Material Due to the fact that this solicitation requires us to “hold” our pricing for 120 calendar days for acceptance and given the recent uncertainty in materials and labor costs; would the government consider including the FAR Clause 52.216-4, Economic Price Adjustment for Labor and Material in this solicitation?

52.216–4 Economic Price Adjustment— Labor and Material. As prescribed in 16.203–4(c), when contracting by negotiation, insert a clause that is substantially the same as the following clause in solicitations and contracts when the conditions specified in 16.203–4(c)(1)(i) through (iv) apply (but see 16.203–4(c)(2)). The clause may be modified by increasing the 10-percent limit on aggregate increases specified in subparagraph (c)(4), upon approval by the chief of the contracting office.

ECONOMIC PRICE ADJUSTMENT—LABOR AND MATERIAL (JAN 1997)

(a) The Contractor shall notify the Contracting Officer if, at any time during contract performance, the rates of pay for labor (including fringe benefits) or the unit prices for material shown in the Schedule either increase or decrease. The Contractor shall furnish this notice within 60 days after the increase or decrease, or within any additional period that the Contracting Officer may approve in writing, but not later than the date of final payment under this contract. The notice shall include the Contractor’s proposal for an adjustment in the contract unit prices to be negotiated under paragraph (b) below, and shall include, in the form required by the Contracting Officer, supporting data explaining the cause, effective date, and amount of the increase or decrease and the amount of the Contractor’s adjustment proposal.

(b) Promptly after the Contracting Officer receives the notice and data under paragraph (a) above, the Contracting Officer and the Contractor shall negotiate a price adjustment in the contract unit prices and its effective date. However, the Contracting Officer may postpone the negotiations until an accumulation of increases and decreases in the labor rates (including fringe benefits) and unit prices of material shown in the Schedule results in an adjustment allowable under subparagraph (c)(3) below. The Contracting Officer shall modify this contract (1) to include the price adjustment and its effective date and (2) to revise the labor rates (including fringe benefits) or unit prices of material as shown in the Schedule to reflect the increases or decreases resulting from the adjustment. The Contractor shall continue performance pending agreement on, or determination of, any adjustment and its effective date.

(c) Any price adjustment under this clause is subject to the following limitations:

(1) Any adjustment shall be limited to the effect on unit prices of the increases or decreases in the rates of pay for labor (including fringe benefits) or unit prices for material shown in the Schedule. There shall be no adjustment for

(i) supplies or services for which the production cost is not affected by such changes,

(ii) changes in rates or unit prices other than those shown in the Schedule, or

(iii) changes in the quantities of labor or material used from those shown in the Schedule for each item.

(2) No upward adjustment shall apply to supplies or services that are required to be delivered or performed before the effective date of the adjustment, unless the Contractor’s failure to deliver or perform according to the delivery schedule results from causes beyond the Contractor’s control and without its fault or negligence, within the meaning of the Default clause.

(3) There shall be no adjustment for any change in rates of pay for labor (including fringe benefits) or unit prices for material which would not result in a net change of at least 3 percent of the then-current total contract price. This limitation shall not apply, however, if, after final delivery of all contract line items, either party requests an adjustment under paragraph (b) above.

(4) The aggregate of the increases in any contract unit price made under this clause shall not exceed 10 percent of the original unit price. There is no percentage limitation on the amount of decreases that may be made under this clause.

(d) The Contracting Officer may examine the Contractor’s books, records, and other supporting data relevant to the cost of labor (including fringe benefits) and material during all reasonable times until the end of 3 years after the date of final payment under this contract or the time periods specified in subpart 4.7 of the Federal Acquisition Regulation (FAR), whichever is earlier.

ANSWER – FAR 52.216-4, Economic Price Adjustment-Labor and Materials will not be included in this solicitation.

RFI 020: 01 00 00, Section 1.25 Photographic Documentation requires the contractor to electronic index, documentation shall combine indexing and navigational system that shall utilize AUTOCAD.

Can the Contractor’s Superintendent take progress photos and save them to Procore for the VA’s use?

ANSWER - The contractor should take daily photos and include them as part of their daily reports, these reports can be uploaded to Procore, Submittal Exchanged or emailed to the COR – Daily.

RFI 021: 01 00 00, 1.26 VA TRIRIGA CPMS section requires the contractor to use this software for the project. This software is no longer available.

Does the contractor need to use this software?

ANSWER - No image5.jpeg image6.jpeg image1.png image2.png image3.jpeg image4.jpeg