STATEMENT OF WORK
Department of Veterans Affairs Upgrade Electrical Paralleling System Project # 626-18-203
I. GENERAL SCOPE OF WORK
The A/E shall provide all necessary architectural and engineering services as required to prepare complete contract drawings, specifications, technical reports, and cost estimates, including construction period services for "Upgrade Electrical Paralleling System” at the VA Tennessee Valley Healthcare System, Nashville Campus, 1310 24th Avenue South, Nashville, TN 37212. This project will correct the inadequate capacity of the emergency power paralleling switchgear and obsolete control system feeding Buildings 1 and ACRE. Design work includes professional design services of Architects, Structural, Mechanical, Plumbing, and Electrical Engineers. Construction work includes but is not limited to electrical, low voltage and control systems, fire alarm, mechanical, plumbing, architectural, and structural.
II. STATEMENT OF PROJECT OBJECTIVES
It is the intent of the Department of Veterans Affairs to have the A/E fully survey, investigate and document the existing space and utility systems in order to gain the knowledge and insight necessary to prepare quality, accurate construction documents in a professional and competent manner. The project objectives are as follows:
A. Replace existing 2500-amp paralleling switchgear with new sized to existing (4) generators capacity plus future expansions. Switchgear shall consist of generator control sections, distribution sections, and master control section.
B. Replace existing master control system with new PLC establishing ATS load shedding schemes.
C. Evaluate and replace Existing ATS’s past their life expectancy.
D. Extend building to accommodate additional switchgear.
E. Replace existing Power Logic System on existing generators for proper monitoring and load shedding.
F. Phase project to minimize disruption to Medical Center G. Provide options on one large sized switchgear versus equivalent (2) smaller sets for redundancy.
H. Address safety and security issues bringing the Emergency Power Feed into compliance with VA Physical Security and National Electric Code requirements.
III. JUSTIFICATION
A. Existing emergency 2500-amp paralleling switchgear is at maximum capacity during peak loads requiring load shedding to maintain emergency power to facility.
B. Existing ATS’s are past life expectancy.
C. Existing master control section is outdated/old technology and parts are no longer available.
D. All building service equipment & utilities/distribution shall be sized for 15% to 20% future.
IV. STATEMENT OF A/E TASKS
A. The A/E shall furnish all services for a complete design development, construction documents and construction period services as specified in the contract.
1. Necessary site survey work such as verifying existing conditions, verifying record drawings and verifying and analyzing utility systems shall be accomplished in conjunction with preparation of Design Development.
2. The complete site survey work shall include a thorough investigation of existing conditions to accurately document and convey space dimensions for measured drawings, all utilities for affected areas and utilities that traverse through affected areas, typical construction type and variations and finishes. This information provides the necessary base drawings for the Schematic Development phase of Design Development.
B. The A/E shall provide cost estimation, project scheduling and phasing, bid period and construction period services as further described in the contract.
C. The A/E shall provide bid document preparation in quantities as specified in the contract.
D. The A/E will coordinate with leading industry equipment manufacturers/vendor(s) to ensure proper layout and support of equipment according to manufacturer’s requirements. However, design drawings and specifications shall be generic to promote fair and open competition.
E. The A/E shall provide design and construction period services utilizing individuals of the various design disciplines including but not limited to architectural and engineering, structural and electrical as required by the project. Changes in personnel from those who are proposed must be approved in writing by the Contracting Officer. The services of an industrial hygienist familiar with asbestos abatement will be utilized in the event that asbestos is found present and would impact the work. The registered individuals who will stamp the completed documents shall accomplish engineering design work.
V. BASIS FOR DESIGN
A. Department of Veterans Affairs standards may be obtained from the internet at http://www.cfm.va.gov/TIL/
B. Compliance to these standards, National Fire Codes, Uniform Building Codes and OSHA Standards will be reflected in the completed design and construction documents.
C. The A/E design and estimate shall identify 20% of the total construction budget as viable deductive construction alternates. A single award will be made subject to the availability of funds.
D. Compliance with the Physical Security design manuals for VA Facilities. http://www.cfm.va.gov/til/spclRqmts.asp#PHS
E. Comply with VA TIL, PG-18-15, A/E Design Submissions and Review. http://www.cfm.va.gov/til/aeDesSubReq.asp
F. A/E shall design within funding limitations. A/E shall coordinate cost control measures with COR to design within funding limits. Cost control alternatives shall be explored in Design Development.
G. Comply with current applicable state, local and federal building codes as well as codes from other recognized authoritative bodies; including but not limited to Associated Air Balance Council (AABC), American Concrete Institute (ACI), Acoustical and Insulating Materials Association (AIMA), American National Standards Institute (ANSI), American Society of Heating, Refrigeration, and Air-Conditioning Engineers (ASHRAE), American Society of Mechanical Engineers (ASME), American Society for Testing and Materials (ASTM), The Building Officials and Code Administrators International (BOCA), Gypsum Association (GA), International Building Code (IBC), NEC, NFPA, National Environmental Balancing Bureau (NEBB), National Standard Plumbing Code (NSPC), OSHA, Standard Building Code (SBC), Sheet Metal and Air Conditioning Contractors’ National Association (SMACNA), The Uniform Building Code (UBC), and Uniform Federal Accessibility Standard (UFAS), & American Disabilities Act (ADA), and other applicable codes.
VI. DETAILED SUBMISSION REQUIREMENTS
Program Guide PG-18-15, establishes the guidelines for the A/E submissions. Design shall be performed and submitted in accordance with VA A/E Submission Instructions for Minor and NRM Construction Program. Refer to http://www.cfm.va.gov/til/aeDesSubReq.asp, which may not be adequate for certain, types of design. In some instances in which critical decisions need to be made, sufficient and relevant information has to be provided timely in order for the design to progress to meet certain milestone dates. The level of applicability of the program guide depends upon the scope of work and the exclusions, which are herein specified. Questions in regards to the applicability of specific requirements shall be resolved with the COR prior to any submission deadline. Where “days” are stated, this refers to “calendar” not “work” days.
A. At each submission, all drawings and support material shall be dated and appropriately labeled above the title block:
| Work Element |
| Copies |
| Duration |
Design Kick-off Meeting
1 day
| Design Development 1 |
| 3 |
| 28 days |
Gov’t Review
10 days
| Design Development 2 |
| 3 |
| 28 days |
Government Review
10 days
| Construction Document 1 |
| 3 |
| 28 days |
Government Review
10 days
| Construction Document 2 |
| 3 |
| 28 days |
Government Review
10 days
| Final 100% Documents |
| 3 |
| 7 days |
| Government Review |
| 3 |
| 5 Days after receipt of 100% Final Documents |
B. For each submission review comments may be verbal, noted directly on review sets, or written list. The A/E shall be responsible for compiling and addressing review comments. A/E shall produce and distribute meeting notes or minutes for VA review immediately after each submission review meeting.
C. For each submission, furnish electronic files in the latest version of Microsoft Office and Microsoft Word and/or AutoCAD 2013. PDF’s of the specifications will not be acceptable. Submit 2 hardcopies of all drawings. The 100% construction document submission will include a full set of construction documents including all disciplines/packages and will be sealed and signed by the Architects and Engineers of Record.
D. The final construction documents submission package will incorporate all VA supplied comments from the earlier submission package reviews.
E. If the final construction documents submission package is not complete, the contractor must resubmit the package in its entirety.
F. Project specifications shall include specifications for all products, materials, equipment, methods and systems shown on the construction drawings in accordance with standard professional practice and the resulting contract. The specification submitted for review shall include: name of the manufacturer, product name, model number or other identification as appropriate to clearly identify the product that will be used in the construction of the project.
G. Final bid documents shall be reproduced as part of the contract. Two 2 full sets and two 2 half sets of the Construction Bid Documents are to be delivered to the COR. Electronic files of the Construction Bid Documents will be provided to the COR and Contracting Officer.
H. The required stamp of the licensed architect or engineer of record will be considered as certification of compliance with the contract requirements.
I. Total time to accomplish DDs and CDs through final reproduced bid documents shall be 165 days from the issuance of the Notice to Proceed. Each submission will require maximum ten 10 calendar days for VA review. A/E shall prepare a project schedule so that the timeframes in the above schedule are met.
VII. CONSTRUCTION PERIOD SERVICE REQUIREMENTS
A. Review of Submittals: A/E shall review all material submittals, shop drawings, test reports (as applicable), etc. Reviews shall be completed and submittals returned to the COR within 15 calendar days from the A/E's receipt of the submittal.
B. Review Analysis of Requests for Information, Change Orders and Costs: A/E shall provide prompt response when contacted by the Contracting Officer or COR to review and provide analysis of construction contractor requests for information or change orders.
C. Site Visits: A/E shall provide 30 site visit “units” during the construction period when requested by the Contracting Officer, in addition to two contractor pre-bid meetings, a final structural inspection and report and final inspection. A site visit “unit” is defined as a visit to the site by one individual for 3 hours. On this job, a site visit may require the use of multiple “units” when more than one individual or an extended period of time is needed to inspect an area of work. The COR has the prerogative to determine the professional discipline(s) required for each site visit. The A/E shall notify the COR of their presence on site before any work is performed in order to document the number of individuals who are making the site visit. The A/E shall observe the construction, advise the COR of any deviations or deficiencies and recommend appropriate corrective actions.
D. "Record Drawings" Requirement: A/E shall revise the solicitation documents if necessary and provide a complete set of all drawings showing actual, completed construction and reflecting any changes incorporated in the work on hard (bond) copy and on electronic media. Electronic media drawings shall be in AutoCAD 2013 and always electronically stamped. A/E shall load and demonstrate full AutoCAD compatibility at VA site. Compatibility means that data can be accessed directly by target system without translation or processing of data files. Problems shall be corrected to satisfaction of VA. Final electronic media specifications shall be in Microsoft Word 2010 Format.
VIII. MATERIALS TO BE FURNISHED TO THE A/E BY THE VA
The following items will be furnished to the A/E when requested:
A. Prints and available electronic media of the station utility drawings, site plans and building floor plans (if station has on-file), will be made available. The accuracy of drawings is not guaranteed and shall be used for general information only. Actual conditions shall be field verified by the A/E.
B. Vulnerability Assessment Report – Tennessee Valley Healthcare System – Nashville Campus