PWS Draft for RFI.docx
DOCX document 39 KB Posted
- Solicitation number
- 36C24827Q0143
About this file
This is a Performance Work Statement (PWS) for annual cathodic protection inspection and testing services at the Orlando VA Medical Center's steam and condensate piping system. The contractor shall perform annual inspections and testing of the existing galvanic cathodic protection system serving underground coated steel steam and condensate pipelines at the Lake Nona Campus. Key testing responsibilities include locating and inspecting up to 24 accessible cathodic protection test stations, measuring "ON" potentials and "InstantOff" potentials using calibrated instruments, measuring anode current output across calibrated shunts, recording depolarized potentials after minimum 4-hour shutdown, documenting inaccessible or damaged test stations, and issuing a comprehensive annual report with results, analysis, as-built updates, and recommendations. The system consists of double-wall steel piping with galvanic anodes (32 magnesium anodes totaling 17 pounds each) and 24 test stations designed to protect against corrosion; soil resistivity measures 11,500 ohmcm. All work must follow NACE procedures and be performed by NACE-certified cathodic protection technicians, technologists, or specialists using calibrated reference electrodes.
Mandatory deliverables include the final annual CP testing report, updated as-built drawings, instrument calibration certificates, deficiency list with recommended corrections, and updated test station inventory, all due electronically within 7 calendar days of completing on-site testing. Testing shall occur once per fiscal year during the October-March window to ensure consistent soil and moisture conditions. The contractor must comply with VA Orlando safety rules, OSHA requirements, VA security and escort procedures, and maintain records for three years after contract completion. Acceptance criteria require InstantOff potentials showing 100 mV polarization shift or -850 mV polarized potential, measurable anode currents, location and measurement of all accessible test stations, and complete data quality with calibrated devices. The contracting vehicle involves the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 8 (VISN 8), with the related sources-sought notice referencing NAICS code 541380 (Testing Laboratories and Services) with an $19.0 million size standard.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24827Q0143.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (PWS)
ANNUAL TESTING OF GALVANIC CATHODIC PROTECTION SYSTEM
VA ORLANDO MEDICAL CENTER – STEAM & CONDENSATE PIPING
1. Introduction:
This is a non-personal service contract for annual Cathodic Protection inspection and testing. Such service providers shall be accountable solely to the contractor, who is responsible to the Government. The contractor shall provide all the labor, materials, equipment, and transportation necessary to conduct the survey, collect information, perform analysis, and produce the required deliverables.
The Orlando VA Healthcare System (OVAHCS) Facilities Management Service (FMS), located at 13800 Veterans Way, Orlando, FL 32827, mission is to provide, operate, and maintain a "state of the art" facility service program in support of our Veterans Health Care System. It is responsible for the Health, Safety, and Well-Being of the Staff, Patients, and Veterans at the OVAHCS hospitals and Outpatient Clinics.
2. Background:
The Orlando VA Healthcare System (OVAHCS) is seeking a new recurring service contract with a licensed vendor to provide annual Cathodic Protection Inspections and Testing. The contract provides annual reports required for compliance with federal regulations and is crucial to monitoring the steam & condensate underground lines for corrosion and integrity. It provides for the inspection and testing with specialized equipment that requires knowledge and certifications that the VA does not have. The contractor shall employe NACE certified Cathodic Protection Engineers who are trained personnel who provide the expertise to service this system and assess the overall lifecycle of protection and identify shortfalls needed to recommend remedial actions as required by VA regulations.
3. SCOPE
The Contractor shall perform annual inspecting, testing and evaluation of the existing galvanic cathodic protection (CP) system serving the underground coated steel steam and condensate pipelines at the Orlando VA Medical Center, Lake Nona Campus. The purpose of this testing is to verify continued compliance with NACE cathodic protection criteria, ensure electrical isolation integrity, check anode performance, and document all monitoring results in a comprehensive annual report.
Annual testing responsibilities include:
1. Locating and inspecting all accessible CP test stations (up to 24).
2. Measuring “ON” potentials for steam and condensate lines using calibrated instruments.
3. Measuring anode current output across each calibrated shunt.
4. Recording “Instant‑Off” potentials immediately after current interruption.
5. Recording depolarized potentials after a minimum 4‑hour shutdown.
6. Documenting inaccessible, missing, or damaged test stations.
7. Issuing a complete Annual CP Testing Report including results, analysis, as‑built updates, and recommendations.
4. System Description and History The VA Orlando steam and condensate distribution system consists of double‑wall steel piping with outer jackets exposed to soil. Galvanic CP systems were installed to mitigate corrosion due to coating degradation, soil resistivity, and operating conditions. Annual CP testing is required to ensure system health, confirm protection levels, and detect deficiencies before they affect system reliability. As part of construction, the new buildings were provided with new utilities. These utilities included underground steam and condensate lines. The steam and condensate piping were constructed of double wall steel, with thermal insulation between the carrier and the jacket. Since the steel jackets are exposed to the soil, they will be subject to corrosion. As a primary means of corrosion control, the metallic piping jackets were afforded an excellent quality factory applied coating. Factory supplied kits were also used to coat the field weld joints. Unfortunately, no coating is 100% perfect. Small coating flaws called holidays existed right from the factory. As the pipe was transported and installed additional coating damage occurred. Even after installation, coatings are subject to damage by soil stress, tree roots, rocks in the backfill and even burrowing rodents. As a result, a small percentage of the structure surface is exposed to the soil. For thermal systems, such as steam and condensate the long-term coating loss can approach 2%. To protect the exposed metal at these coating flaws, a cathodic protection system was required under specification section 26-42-00. Per this document, a galvanic cathodic protection system was designed and installed for metallic steam/condensate piping. Design calculations were submitted for the pipelines based on coating quality and soil resistivity measurements. The soil has a resistivity of 11,500 ohm⋅cm. A total of thirty-two (32) 17-lb magnesium galvanic anodes and eighteen (18) test stations were required to protect the original steam & condensate lines. The design life of the anodes exceeded the specified 25 years. Layout and detail drawings of the cathodic protection system are provided in appendix B. It is important to note that the new piping must be electrically isolated from the buildings and other utilities. This was accomplished by installing dielectric gaskets, maintaining separation from the rebar in the concrete building and valve pit walls, and having at least 12 inches of separation between the new pipes and other utilities.
4.1 Galvanic Anodes
Magnesium sacrificial anodes supply protective current to exposed steel at coating holidays.
4.2 Electrical Isolation
Dielectric gaskets and insulating components ensure isolation at building risers, vaults, and piping transitions.
4.3 Test Stations
24ea. CP test stations contain:
· Pipe lead wires
· Anode leads
· Terminal boards
· Calibrated 0.1‑ohm shunts for current measurement See attached as-builts for locations and maps. And historical reports for data.
5.0 CONTRACTOR TASKS
5.1 Annual Testing Tasks
The Contractor shall perform all annual test measurements described in Section 1.0, using calibrated equipment, and document all readings in a clear, traceable format.
TEST PROCEDURES (sample)
To determine the effectiveness of the cathodic protection system, potential measurements were recorded on the steam and condensate piping. These measurements were recorded using a Fluke Model 87 high impedance digital voltmeter capable of 0 to 1000 VAC and 0 to 1000 VDC scales and a M. C. Miller Model RE5C copper sulfate reference cell or equivalent that meets NACE -850mV energized criteria. Prior to testing, the voltmeter and reference cell were calibrated and found to be accurate. Tests were conducted by placing the reference cell in the soil at the bottom of each test station. An insulated cable with a special submersible adapter was then used to connect between the cell and the negative terminal of the voltmeter. A second insulated cable with a clip was used to connect from the positive voltmeter terminal to the lead wire terminals in the test station. The voltmeter was then placed on the 2,000 millivolt scale and turned on. A stable potential indicated good cell to soil contact. All locations with dry soil, water was poured into the test station. The anode current output was measured by reading the voltage drop across the calibrated shunt at each test station. One of the voltmeter lead wires was clipped to each of the shunt prongs. The voltmeter was then set on the 200-millivolt scale and turned on. The reported value in millivolts was multiplied by 10 to obtain milliamperes.
Example Test Procedure:
1: Open the test station 2: Connect the positive voltmeter test lead to the pipe lead in the test station.
3. Connect the negative or common voltmeter test lead to the permanent copper-sulfate reference cell lug or to a portable cell at the base of the test station.
4: Turn the voltmeter to the DC volt scale and allow the reading to stabilize.
5: Record the reading displayed by the voltmeter in appropriate data sheet.
6. Repeat this procedure for each test station.
5.2 Corrective Recommendations
The Contractor shall provide written recommendations for any deficiencies identified, including:
· Damaged or missing test leads
· Low potentials
· Lack of isolation
· Inactive anodes
· Damaged or shorted dielectric flanges
6.0 PERFORMANCE REQUIREMENTS
· Testing must follow accepted NACE procedures.
· All potentials must be measured using calibrated reference electrodes.
· Data must be traceable to test station identifiers.
· Reporting must be complete and require no further correction to be accepted.
7.0 SUBMITTALS
1. Annual CP Testing Report
2. Updated Test Station Map
3. Instrument Calibration Certificates
4. Recommended Corrective Actions
5. Updated As‑Built Drawings showing station locations, anodes, cable routing, and identifiers.
8.0 QUALITY ASSURANCE
All work must be supervised or performed by personnel certified as NACE Cathodic Protection Technician, Technologist, or Specialist. The Contractor must maintain quality control and provide complete documentation.
9.0 SAFETY REQUIREMENTS
Contractors shall adhere to all VA Orlando safety rules and OSHA requirements, especially when working in confined spaces, energized utility areas, or valve vaults. Coordinate with COR for local conditions prior to work.
10.0 GOVERNMENT FURNISHED INFORMATION
VA will provide:
· Existing drawings
· Historical CP testing documentation
· Required site access and escort
· Information on known CP system deficiencies
11.0 ACCEPTANCE CRITERIA
11.1 Polarization & Potential Criteria
· Instant‑Off potentials must show ≥100 mV polarization shift or ≥ –850 mV polarized potential.
· ON potentials must reflect active protective current.
11.2 Anode Performance
· All anode currents must be measurable.
· Inactive anodes must be documented and explained.
11.3 System Integrity
· All accessible test stations must be located and measured.
· Missing/damaged stations must be documented with photos and coordinates.
11.4 Data Quality
· All measurements must be taken with calibrated devices.
· Report must include complete data tables, calculations, and interpretations.
12.0 ANNUAL TESTING SCHEDULE
12.1 Frequency
Testing shall occur once per fiscal year.
12.2 Recommended Window
October - March to ensure consistent soil and moisture conditions.
12.3 Submittal Timeline
Annual report must be delivered within 7 calendar days following completion of onsite testing.
12.4 Coordination
Contractor shall coordinate with VA Facilities Management Service for access to steam vaults, manholes, and test stations.
12.0 DELIVERABLES
12.1 Mandatory Deliverables
1. Final Annual CP Testing Report
2. Updated As‑Built Drawings
3. Calibration Certificates
4. Deficiency List & Recommended Corrections
5. Updated Test Station Inventory
12.2 Delivery Requirements
All deliverables must be submitted electronically to the COR and Contracting Officer.
13.0 VA CONTRACTING CLAUSES
13.1 Applicable FAR Clauses
· FAR 52.212‑4 – Contract Terms and Conditions
· FAR 52.212‑5 – Statutory Implementation Terms
· FAR 52.243‑4 – Changes
· FAR 52.232‑25 – Prompt Payment
13.2 Applicable VAAR Clauses
· VAAR 852.236‑88 – Contract Changes, Supplement
· VAAR 852.219‑75 – Subcontracting Plans
· VAAR 852.203‑70 – Commercial Advertising
· VAAR 852.211‑70 – O&M Manuals
13.3 COR Authority
The COR monitors performance, verifies deliverables, and certifies invoices. COR decisions do not change contract terms.
13.4 Invoicing Requirements
Invoices must:
· Reference contract and obligation numbers
· Be submitted after COR acceptance
· Follow VA electronic invoicing procedures
13.5 Period of Performance
Work shall occur within the funded task order’s PoP. No work may begin without a written, funded task order.
14.0 ADDITIONAL CONTRACTUAL CONSIDERATIONS
14.1 Records Retention
Contractor shall retain test data and calibration logs for three years after contract completion.
14.2 Access Requirements
Contractor must comply with VA security, escort procedures, and badging.
14.3 Non‑Disclosure
Sensitive facility information shall not be shared outside contract performance.
15.0 QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)
15.1 Purpose
This QASP provides the Government’s method for monitoring contractor performance to ensure compliance with the PWS.
15.2 Roles
· CO: Ensures compliance and makes final determinations.
· COR: Conducts surveillance, documents findings, certifies invoices.
· FMS Staff: Provides access and operational support.
15.3 Performance Requirements Summary Table (PRST)
| Task ID |
| Performance Objective |
| Standard |
| AQL |
| Surveillance Method |
| Incentive / Remedy |
| 1 |
| Complete annual CP testing for all accessible stations |
| All readings recorded using calibrated instruments |
| 100% |
| COR 100% inspection; site spot‑checks |
| Payment only upon acceptance |
| 2 |
| Record ON / Instant‑Off / Depolarized potentials |
| Must meet NACE polarization criteria |
| 100% |
| COR review of report data |
| Re‑test required if unmet |
| 3 |
| Measure anode current output |
| All anodes measured or documented if inaccessible |
| 100% |
| COR inspection |
| Payment withheld until complete |
| 4 |
| Identify deficiencies |
| All issues documented with photos/notes |
| 100% |
| COR verification |
| Payment contingent on thorough documentation |
| 5 |
| Submit final Annual CP Report |
| Complete, accurate, compliant |
| 100% |
| 100% review |
| Non‑acceptance delays payment |
| 6 |
| Submit updated as‑built drawings |
| All stations and components shown |
| 100% |
| COR field & drawing review |
| Payment contingent on acceptance |
15.4 Surveillance Methods
· 100% Inspection: COR reviews all deliverables.
· Periodic Observation: COR may observe testing activities.
· Random Sampling: Spot checks for accuracy.
· Validated Complaints: Investigated and documented.
15.5 Performance Rating
· Exceeds Requirements
· Meets Requirements
· Does Not Meet Requirements (requires correction at Contractor expense)
15.6 Payment Milestones
Milestone 1 – Completion of Field Testing No payment; testing must first be verified.
Milestone 2 – Draft Report Submission No payment until final acceptance.
Milestone 3 – COR Acceptance of Final Report & As‑Built Drawings Full payment released after COR acceptance.
Milestone 4 – Administrative Closeout No payment; part of contract closeout.
15.7 Documentation Requirements
COR maintains surveillance logs, deficiency reports, and acceptance documentation as part of official contract records.