Chiller Plant #2 Repairs - Amendment Questions and Answers Federal contract opportunity
Solicitation number
36C24825Q0874
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 8

About this file

This document is an Amendment (Mod 0002) to a solicitation for Chiller Plant #2 Repairs at the C.W. Bill Young VA Medical Center, containing questions and answers from potential bidders. The amendment extends the solicitation closing date from 07/18/2025 to 07/22/2025 at 2:00pm EDT and provides clarifications on several technical aspects of the project, including painting specifications for pipes (two-part epoxy recommended), hangar materials (galvanization preferred for corrosion protection), and crane placement and coordination requirements. Key technical details addressed include pipe coating specifications, hanger material recommendations, lock-out/tag-out (LOTO) responsibilities, and crane placement procedures during weekday business hours, with all coordination to be done through the site safety office.

View the file

Other files for this federal contract opportunity

Other files attached to Chiller Plant #2 Repairs - Amendment Questions and Answers, newest first.
File Type Posted
VA NOTICE HANDBOOK.pdf PDF
S02 - SOLICITATION.docx DOCX document
App A PO Comments.doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 2

0002 07-17-2025

516-25-3-5105-1093

36C248

Department of Veterans Affairs

Network Contracting Office 8 (NCO 8)

10,000 Bay Pines Blvd

Bay Pines FL 33744

36C248

Department of Veterans Affairs

Network Contracting Office 8 (NCO 8)

C.W. Bill Young VA Medical Center

10000 Bay Pines Blvd.

Bay Pines FL 33744

To all Offerors/Bidders

36C24825Q0874

X

X X

** HOUR & DATE for Receipt of Offers is EXTENDED to: 07-22-2025 2:00pm EDT

See CONTINUATION Page

516-3650162-5105-854100-2580 010050192 x

A - The purpose of Amendment 0002 is to provide answers to questions received and extend the closing due date from 07/18/2025 at 2:00pm to 07/22/2025 at 2:00pm EST.

SEE CONTINUATION PAGE

Karina Miranda

Contracting Officer

QUESTIONS AND ANSWERS

Q 1. Since the Site Visit was cut short due to lightning, will there be another?

A 1. No, other site visits will not be scheduled.

Q 2. The painting of the pipe was discussed. In the previous RFI I asked for a spec on the enamel and was provided with an answer. During the site visit it was discussed that the piping was to be coated with a two-part EPOXY vs the ENAMEL Specified. Please clarify the painting requirement.

A 2. Refer to VHA spec 230511, section 3.7 painting. Ensure pipes are relabeled with painted on stencils in terms of supply and return after painting.

Q 3. The solicitation requested that Spring Type Hangars and Clevis Hangers be replaced. Please advise if industry standard black steel is acceptable or if galvanized materials are needed for corrosion protection.

A 3. Galvanization would be best. Anything that can help reduce failure from corrosion.

Q4. Please confirm that the VA will isolate and lock out/tag the cooling tower for the removal and replacement of the 14 in section of pipe and the control valve/actuator.

A 4. VHA will not be responsible for LOTO of equipment they are not working

on. Responsibility of the contractor to LOTO all systems that could pose a safety risk to the contractors’ employees or sub-contractors. VHA will LOTO components of the system they do not want on while the cooling tower is offline. i.e. the fan.

Q 5. Is there any time restriction on locating a crane adjacent to the building to lift material and equipment onto the roof?

A 5. No, it shall be done during the week days and during normal business hours. Coordination of crane lifts needs to be done through the safety office on site and through construction safety coordinator.