SOW Rust removal and repair piping and tank.doc
DOC document 654 KB Posted
- Attached to
- J047--Pipe and Fuel Tank Painting/Resurfacing
- Solicitation number
- 36C24825Q0026
About this file
This document is a Performance Work Statement (PWS) and Solicitation for a federal contract opportunity issued by the Department of Veterans Affairs (VA) for pipe and fuel tank painting/resurfacing services.
The key details are: The VA Medical Center in West Palm Beach, FL has a requirement for rust removal and repair of gas, fuel oil piping, and two 12,000 gallon fuel oil tanks. The work includes removing rust, applying rust-resistant coatings, and providing a 2-year warranty. The solicitation is set-aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSBs). Quotes are due by October 11, 2024. The contract will be awarded as a firm-fixed-price contract to the responsible contractor whose proposal represents the best value to the government, considering price, technical factors, and past performance. The applicable NAICS code is 332919 Other Metal Valve and Pipe Fitting Manufacturing with a size standard of 750 employees.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24825Q0026 0001.docx | DOCX document | |
| Gas Piping 3.jpg | JPG image | |
| Fuel oil piping.jpg | JPG image | |
| Gas Piping.jpg | JPG image | |
| Gas Piping 2.jpg | JPG image | |
| tank picture 2.jpg | JPG image | |
| 36C24825Q0026.docx | DOCX document | |
| Tank picture.jpg | JPG image |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REPAIR GAS, FUEL OIL PIPING AND FO TANK
1.
Overview:
The gas and fuel oil piping has high amount of rust and without the pipes being repaired immediately. Location of the task and piping is front and side of boiler plant at 7305 North Militay Trail, West Palm Beach, FL 33410 2.
Materials and Equipment:
The work shall include, but shall not be limited to the following (not necessarily in the order indicated):
a. Contractor shall remove all surface rust on gas piping located on side of boiler plant beside beside temp boiler and apply (2) coats of Superior Coating Solutions-Rust Grip (Paint should be same color with black label identifying either supply or return and direction of flow as existing paint pipes)
b. Contractor shall remove all surface rust on fuel oil piping located beside the two above ground fuel oil tanks and apply (2) coats of Superior Coating Solutions-Rust Grip (Paint should be same color with black label identifying either supply or return and direction of flow as existing paint pipes)
c. Contractor shall scrap any damaged paint and texture off of both above ground 12000 gal fuel oil tanks and apply (2) coats of Superior Coating Solutions-Rust Grip of same color of unit.
d. Contractor shall notify COR of any damaged pipes that cannot be repaired.
e. Contractor shall provide an On-site Supervisor
f. Contractor shall provide a 2 year warranlty on work.
3.
Requirements:
a.
Prior to any worker for the contractor begins work, the contractor shall ensure that equipment located need piping is protected for rust removal. Contract is to condinate with COR during each step. COR shall inspect piping before primer and paint is applied.
4.
Time of Completion:
a.
The project shall be completed within 12 weeks after contract award and notice to proceed is issued contingent on lead time on materals order 5.
Contractor Quality Control:
a.
The Job Site Superintendent will:
i.
Inspect the quality of work performed daily.
ii.
Certify the completed work for payment and other purposes.
6.
POC:
a.
The Contracting Officer’s Technical Representative (COR) for this project is: Philip Coleman, Facilities Management Service (FMS) USRO Supervisor, VA Medical Center West Palm Beach, Florida.
7.
Project completion:
a.
The piping shall be restored, free of rust, primed and painted.
b.
Haul away & dispose of all debris and waste to an approved disposal site.
c.
Thoroughly clean up the work area at the end of each day’s work, and at completion of the project. Leave the premises clean and free of waste, scrap, used equipment, or other material intentionally or incidentally delivered to the site by Contractor or Contractor’s personnel.
d.
Contractor shall coordinating with the COR before work begins.
8.
Delivery:
This service contractor will perform work starting on a weekday or weekend at 7:00 AM - 5:30 PM and completing all necessary work, if contractors need to extend the work hours, a request will be submitted for approval by the COR before starting work.
9.
Warranty:
All work performed shall have a minimum of a two-years warranty covering material and labor.