Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

36C248

Department of Veterans Affairs Network Contracting Office 8 (NCO 8) Orlando VA Healthcare System 13800 Veterans Way Orlando FL 32827

36C248

Department of Veterans Affairs Network Contracting Office 8 (NCO 8) Orlando VA Healthcare System 13800 Veterans Way Orlando FL 32827

To all Offerors/Bidders 36C24822Q0689

03-31-2022 X

X

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning _____1_ ____ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified. April 07, 2022 at 16:00 x 1

The purpose of this amendment is to extend the response time of this solicitation to April 07, 2022 at 16:00 and to answer questions based on the RFQ. No additional questions will be entertained.

Q: What are the foundation requirements for the building?

A: N/A. Slab is already in place. See attached picture.

Q: Where will the building be located on campus? (Impacts crane costs, site prep, etc) A: In the same palace as the old one behind bld 517.

Q: Is Contractor to connect the fire alarm system to the existing VA campus fire alarm system?

A: As stated in the SOW, the contractor is responsible for purchasing the building and putting in place. No other work is requested.

Q: Is Contractor to provide power to the unit? If so, what are the exterior electrical power panel requirements? If so, where is the nearest electrical connection feed point? If so, are existing beakers in existing panels available and sufficient for electrical feed to the new unit?

A: As stated in the SOW, the contractor is responsible for purchasing the building and putting in place. No other work is requested.

Q: Is the unit to be anchored or fastened down? If so, what are the requirements?

A: As stated in the SOW, the contractor is responsible for purchasing the building and putting in place. No other work is requested.

Q: Please provide a map showing the location the building will be placed.

A: See attached picture. Container will go where red circle is drawn.

Q: Is there an existing concrete slab to work off or will this need to be provided?

A: Slab already in place.

Q: Please clarify where the power for the building will come from along with electrical as-builds.

A: As stated in the SOW, the contractor is responsible for purchasing the building and putting in place. No other work is requested.

Q: Is the contractor to provide all electrical connections to the building?

A: As stated in the SOW, the contractor is responsible for purchasing the building and putting in place. No other work is requested.

Q: Is the VA willing to accept a prefabricated container instead of a metal building?

A: Yes. A prefab with the stated characteristics is what we are looking for.

Q: Will bollards need to be installed around the building?

A: As stated in the SOW, the contractor is responsible for purchasing the building and putting in place. No other work is requested.

File details come from the government source that posted it. Updated .