About this file

36C24820Q0270 0001 Amendment 0001- Responses and PriceCost Schedule.docx

View the file

Other files for this federal contract opportunity

Other files attached to FY20: VACHS Cable Drops Installation Services, newest first.
File Type Posted
36C24820Q0270-0001004.docx DOCX document
36C24820Q0270-0001006.docx DOCX document
36C24820Q0270-074.docx DOCX document
36C24820Q0270-073.docx DOCX document
36C24820Q0270-076.docx DOCX document
36C24820Q0270-075.docx DOCX document
36C24820Q0270-072.docx DOCX document
36C24820Q0270-077.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:

Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 01-10-2020 672-20-1-544-

NONE

36C248 Department of Veterans Affairs Network Contracting Office 8 (NCO 8)

VA

Caribbean

HCS (

Admin

Bldg #10 Calle Casia Suite #4M440 San Juan PR 00921-3201 36C248 Department of Veterans Affairs Network Contracting Office 8 (NCO 8)

VA

Caribbean

HCS (

Admin

Bldg #10 Calle Casia Suite #4M440 San Juan PR 00921-3201 To all Offerors/Bidders

36C24820Q0270 01-02-2020

X X X JANUARY 16, 2020 at 1:00PM AST See CONTINUATION Page X This amendment is hereby issued to:

a) change Solicitation closing date and time from January 15, 2020, 10:00 AM AST to January 16, 2020 at 1:00PM AST

b) Amend Performance Work Statement (PWS) and Price/Cost Schedule

c) Provide response to Questions submitted by vendors.

Rafael Rodriguez, Contracting Officer

AMENDMENT No. 1 SOLICITATION No. 36C24820Q0270 VACHS Cable Drops Installation Services

EXTENSION OF DUE DATE TO SUBMITT QUOTES

Solicitation 36C24820Q0270 due date for quote submittal is hereby extended from January 15, 2020 at 10:00 AM AST until January 16, 2020 at 1:00PM AST.

PERFORMANCE WORK STATEMENT (PWS) AMENDMENT

Performance Work Statement is hereby Amended to correct the following information of Section 4.1 Contractor Responsibilities Part B., the term Educators Technology Assessment Tubing has been replaced with electrical tubing/conduit. See attached PWS for details.

PRICE/COST SCHEDULE AMENDMENT

Price/Cost schedule is hereby amended as follow: line item has been added to account for the St Thomas and St Croix locations separated from the Puerto Rico locations. See attached Price/Cost Schedule.

RESPONSE TO VENDOR QUESTIONS AND REQUEST FOR INFORMATION

Q. We must be Veterans to participate on this bid?

A. This solicitation is set-aside based on an order of priority as established in 38 U.S.C. 8127. TIERED EVALUATIONS INCLUDING SMALL BUSINESS CONCERNS: This solicitation is being issued as a tiered evaluation for SDVOSB concerns, or in the alternative, a tiered evaluation for VOSB concerns, or in the alternative, a set-aside for other small business concerns. See combined synopsis document for details.

Q. All the drops of cables will be on one location? If so, where is the address?

A. See PWS Performance Location and Hours Section.

Q. That location is new building?

A. Location is the existent VA Caribbean Healthcare System facility in San Juan Puerto Rico and associated Community Based Outpatient Clinics, see PWS Performance Location and Hours Section for details.

Q. Do you have any drawing or layout?

A. Layout and/or blue prints will be provided upon Award.

Q. The RFP requires Orange Coded Fiber which is 62.5-micron Fiber. 50-micron OM3 fiber is currently used in VA’s for interconnecting their closets. Does the VA anticipate upgrading the 50-micron fiber to 62.5 micron?

A. The need to upgrade is not currently foreseen since the VA Caribbean Healthcare System (VACHS) in San Juan, PR already has 62.5-micron fiber. In the event the need arise it will be done independently from this contract.

Q. Solicitation mentions SC connectors, VA’s typically use LC connectors? Can the government confirm which connector type we should include in our quote?

A. The Government need for the VACHS is to use SC connectors as mentioned on PWS.

Q. Can the government confirm what is the Educators Technology Assessment Tubing?

A. It should be electrical tubing/conduit preferably of 1 ½”, PWS Section 4.1 item B has been amended to reflect this correction.

Q. Can the government provide clarification on what is considered an emergency that will require the 24 hours response?

A. An emergency would be any data and voice cabling damages and/or malfunction that affect facility direct patient care operations.

Q. The Performance Work Statement. Item 2.1.1 paragraph 2 were it states” the contractor shall have certified SYSTIMAX technicians to included design, installation and maintenance”. We do not see this as a requirement for this PWS?

A. The Government has carefully evaluated this need prior to publishing the solicitation and understands it is in its best interest to include this evaluation factor as part of the requirement.

Q. The location sites include St Thomas and St Croix clinics. Do we quote you the cabling price for labor and materials and the cost of flying and lodge will be invoice apart or should it be part of the cabling cost?

A. The contract awarded will be firm fix price therefore, an all-inclusive price should be quoted. A line item has been added to cost/price schedule to separate the USVI St Thomas and St Croix locations from the Puerto Rico locations. See Amended Cost/price schedule.

Q. Do we consider the cost of $24.25 cost of the background check per technician in our cost?

A. Yes, the quoted price should be an all-inclusive price. The background check cost for technicians are to be covered by the Contractor.

Q. The RFP requires Orange Coded Fiber which is 62.5-micron Fiber. VA is currently using the 50-micron OM3 fiber for interconnecting their closets. Do we quote the 62.5?

A. Quote for the requested 62.5-micron fiber as per PWS.

Q. Can we offer different prices of drops as in asbestos area, non-asbestos area, off the island?

A. To some extent yes, the cost/price has been amended to separate the Puerto Rico Locations from the USVI. Regarding asbestos, your all-inclusive price should account for that possibility, areas presumed or containing asbestos are mainly in the San Juan facility and are very few. However, the experience and capability are needed for those cases that may arise within those few areas.

A.1 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
UNIT
UNIT PRICE
0001
Cable Drops Installation Services- Installation of CAT6a Plenum to include all materials (i.e. connector, faceplate, modular box) and labor as per PWS.

Puerto Rico Locations.

Estimated quantities of 20 to 100 drops per period of performance.

Contract Period: Base POP Begin: 02-01-2020 POP End: 01-31-2021

EA
__________
0002
Cable Drops Installation Services- Installation of CAT6a Plenum to include all materials (i.e. connector, faceplate, modular box) and labor as per PWS.

St. Thomas and St. Croix, USVI Facilities

Estimated quantities of 2 to 5 per period of performance.

Contract Period: Base POP Begin: 02-01-2020 POP End: 01-31-2021

EA
____________
1001
Cable Drops Installation Services- Installation of CAT6a Plenum to include all materials (i.e. connector, faceplate, modular box) and labor as per PWS.

Puerto Rico Locations

Estimated quantities of 20 to 100 drops per period of performance.

Contract Period: Option 1 POP Begin: 02-01-2021 POP End: 01-31-2022

EA
____________
1002
Cable Drops Installation Services- Installation of CAT6a Plenum to include all materials (i.e. connector, faceplate, modular box) and labor as per PWS.

St. Thomas and St. Croix, USVI Facilities

Estimated quantities of 2 to 5 per period of performance.

Contract Period: Option 1 POP Begin: 02-01-2021 POP End: 01-31-2022

EA
____________
2001
Cable Drops Installation Services- Installation of CAT6a Plenum to include all materials (i.e. connector, faceplate, modular box) and labor as per PWS.

Puerto Rico Locations

Estimated quantities of 20 to 100 drops per period of performance.

Contract Period: Option 2 POP Begin: 02-01-2022 POP End: 01-31-2023

EA
_________
2002
Cable Drops Installation Services- Installation of CAT6a Plenum to include all materials (i.e. connector, faceplate, modular box) and labor as per PWS.

St. Thomas and St. Croix, USVI Facilities

Estimated quantities of 2 to 5 per period of performance.

Contract Period: Option 2 POP Begin: 02-01-2022 POP End: 01-31-2023

EA
___________
3001
Cable Drops Installation Services- Installation of CAT6a Plenum to include all materials (i.e. connector, faceplate, modular box) and labor as per PWS.

Puerto Rico Locations

Estimated quantities of 20 to 100 drops per period of performance.

Contract Period: Option 3 POP Begin: 02-01-2023 POP End: 01-31-2024

EA
__________
3002
Cable Drops Installation Services- Installation of CAT6a Plenum to include all materials (i.e. connector, faceplate, modular box) and labor as per PWS.

St. Thomas and St. Croix, USVI Facilities

Estimated quantities of 2 to 5 per period of performance.

Contract Period: Option 3 POP Begin: 02-01-2023 POP End: 01-31-2024

EA
__________
4001
Cable Drops Installation Services- Installation of CAT6a Plenum to include all materials (i.e. connector, faceplate, modular box) and labor as per PWS.

Puerto Rico Locations

Estimated quantities of 20 to 100 drops per period of performance.

Contract Period: Option 4 POP Begin: 02-01-2024 POP End: 01-31-2025

EA
__________
4002
Cable Drops Installation Services- Installation of CAT6a Plenum to include all materials (i.e. connector, faceplate, modular box) and labor as per PWS.

St. Thomas and St. Croix, USVI Facilities

Estimated quantities of 2 to 5 per period of performance.

Contract Period: Option 4 POP Begin: 02-01-2024 POP End: 01-31-2025

EA
__________

See attached document: PWS-Final-Amended.