36C24820Q0266-0001007.docx
DOCX document Posted
- Solicitation number
- 36C24820Q0266
About this file
36C24820Q0266 0001 Vedor Questions and Answers.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24820Q0266-0002006.docx | DOCX document | |
| 36C24820Q0266-0002007.docx | DOCX document | |
| 36C24820Q0266-0001006.docx | DOCX document | |
| 36C24820Q0266-0001008.docx | DOCX document | |
| 36C24820Q0266-001.docx | DOCX document | |
| 36C24820Q0266-000.docx | DOCX document | |
| 36C24820Q0266-002.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VENDOR QUESTIONS & ANSWERS (Q&As) Seclusion Room Safety Padding (As of 1/7/2020)
The following questions were asked of the Government relating to the subject requirement which are hereby posted and responded to.
Q&As:
(1) Question: Due to the manufacturers production schedule being 90-120 days out on deliverables from date of contractual obligation between awardee and Marathon, will there be any potential extension(s) granted to the performance period?
Answer: The delivery date has been extended from 45 calendar days from date of award to no later than 3/15/2020. This will also allow time for the purchase and installation of beds under a separate contract prior to installation of safety padding covered by this one.