This is an Amendment to a federal solicitation (SF 30) for the Carl Vinson VA Medical Center Building 3 Dental Vacuum Pump Replacement project. The Department of Veterans Affairs, Veterans Health Administration Network Contracting Office 7 issued Amendment 0001 effective November 23, 2026, to Solicitation 36C24727Q0067. The amendment extends the quotation submission deadline to November 30, 2026, at 12:00 PM EST, with submissions directed to Contracting Officer Jessica Cummings at Jessica.Cummings3@va.gov. The amendment incorporates vendor questions and government responses, replaces the previous Statement of Work in its entirety with a revised SOW that removes the requirement to replace all low-voltage communication wiring between the hub, display, and each system component, and closes the question submission period. All other terms and conditions remain unchanged.

The revised Statement of Work outlines a one-time, firm-fixed-price service contract with a 90-calendar-day period of performance from contract award. The scope requires complete replacement of two failing RAMVAC Bison 9 vacuum pumps and the OWL (On-Wall Logic) control system at the Carl Vinson VAMC dental facility in Dublin, Georgia. Replacement pumps must meet or exceed minimum specifications including 80 CFM @ 7" Hg per pump, support for 10 simultaneous users per pump, 208/230V three-phase electrical compatibility, oil-lubricated rotary vane design, and compliance with UL, NFPA 99, and FDA medical device requirements. The contractor must supply and install a new control system with equivalent or improved functionality, retain monitoring and control capabilities for two RAMVAC Osprey Air Compressors, and perform all removal, installation, electrical and plumbing integration, testing, verification, and site cleanup. All installation personnel must hold current ASSE 6010 Medical Gas Systems Installer certification, with manufacturer-trained technicians permitted to perform equipment setup and programming. Work is located in Building 3 Attic at 1826 Veterans Boulevard, Dublin, Georgia, with tentative hours of 7:00 AM to 3:30 PM EST Monday through Friday, though after-hours or weekend work may be required.

View the file

Other files

File Type Posted
36C24727Q0067_3.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 9

0001 11-23-2026 557-27-1-5151-0015

508A

DEPARTMENT OF VETERANS AFFAIRS

VETERANS HEALTH ADMINISTRATION

Network Contracting Office (NCO) 7 2957 CLAIRMONT ROAD NE, Suite 1200 Atlanta GA 30329

508A

DEPARTMENT OF VETERANS AFFAIRS

VETERANS HEALTH ADMINISTRATION

Network Contracting Office (NCO) 7 2957 CLAIRMONT ROAD NE, Suite 1200 Atlanta GA 30329

To all Offerors/Bidders 36C24727Q0067

X

X X

** HOUR & DATE for Receipt of Offers is EXTENDED to: 11-30-2026 12PM EST 557-3670162-5151-855100-2543 0100J0092

1 1

Solicitation 36C24727Q0067 is amended as follows:

1. The attached Vendor Questions and Government Responses document is incorporated. (See attachment)

2. Replace the previous SOW in its entirety with the attached revised SOW. Section 2(c) removes the requirement to replace all low-voltage communication wiring between the hub, display, and each system component.

3. The question submission period is closed.

4. Extend the quotation submission deadline to November 30, 2026, at 12PM EST. Please submit to Contracting Officer:

Email: Jessica.Cummings3@va.gov

5. All other terms and conditions remain unchanged.

Jessica Cummings Contracting Officer

11/23/2026

Questions

Solicitation: 36C24727Q0067

Building 3 Dental Vacuum Pump Replacement

1. How many dental chairs are connected to the vacuum pumps slated for replacement?

a. There are 7 dental chairs connected to the vacuum system.

2. Do the dental vacuum pumps need to be configured on a control system that alternates them daily or on another specific schedule?

a. New dental vacuum pumps need to be configured to match the operation schedule the current pumps are set on. Schedule is believed to be a lead/lag configuration that alternates lead/lag pumps periodically to provide for even mechanical wear.

3. Pump capacity. SOW Section 2 requires a minimum rated capacity of 80 CFM at 7 in.

Hg and support for 10 simultaneous users per pump. Is the 80 CFM minimum a per-pump rating, or the combined rating of the two-pump system?

a. The 80 CFM rating is a per-pump rating, meaning each individual pump must be rated at a minimum of 80 CFM.

4. Pump capacity at a higher vacuum level. Dry rotary vane dental vacuum systems are commonly rated at a deeper vacuum than 7 in. Hg. Will the Government accept manufacturer documentation showing that each proposed pump supports at least 10 simultaneous users, with rated flow stated at the manufacturer's standard vacuum level, as meeting or exceeding the Bison 9 performance?

a. Yes, pumps exceeding the performance level of the existing Bison 9 vacuum pumps will be accepted, but documentation confirming the performance ratings/capabilities of the replacement pumps must be provided.

5. Installer certification. The SOW requires all personnel performing installation to hold current ASSE 6010 certification. Will the Government accept ASSE 6010 certified installers performing all vacuum piping work, with manufacturer-trained dental equipment technicians performing equipment setting, startup, and control system programming?

a. Yes. Pump and piping installers must possess ASSE 6010 certification, while manufacturer trained dental equipment techs will be permitted to perform equipment setup and programming.

6. Existing remote switches. How many remote switch panels or illuminated switches are tied to the existing OWL system, and are they to be reused or replaced?

a. There are no remote switch panels or illuminated switches tied to the existing OWL system. Start/stop of the vacuum pumps is performed from the OWL Touch panel (manual mode and schedule), which functions in place of a standard remote switch.

7. Site visit. If an offeror's representative cannot attend on November 18, will an alternate site visit date be available?

a. No.

8. Can you provide the current vacuum pump manufacturer?

a. Current pumps are RAMVAC BISON 9 models.

STATEMENT OF WORK

Carl Vinson VA Medical Center Building 3 Dental

Vacuum Pump Replacement

GENERAL INFORMATION

a) Purpose

The purpose of this acquisition requirement is to replace two failing vacuum pumps in the attic of Building 3 (Dental Services) at the Carl Vinson VA Medical Center in Dublin, GA.

b) Background

Carl Vinson VAMC Dental Services currently relies on a dual-pump vacuum system to support all clinical suction requirements, including high-volume evacuation and infection control (saliva suction) during various types of dental operations. One of the two vacuum pumps has failed and is no longer operational; the other is in poor condition and is expected to fail in the near future.

Because suction provided by these pumps is essential for maintaining a safe and efficient operating environment during dental procedures, the continued use of the existing equipment poses an operational risk that could lead to unscheduled downtime and disruption of patient care capabilities. To ensure continuity of operations and restore full system reliability, removal of the existing vacuum pumps and the installation of new pumps for Dental Services is required.

In addition to the replacement of the two dental vacuum pumps, the On-Wall Logic (OWL) control system for the dental vacuum system will be replaced as a part of this service contract. The OWL controller system and interface is significantly outdated and an updated replacement control system will be included as a part of this Scope of Work.

c) Scope of Work

The Contractor shall provide ALL labor, materials, tools, equipment, transportation, and technical expertise required to replace the two vacuum pumps and controller system for Dental Services. This scope shall include all aspects of current vacuum pump removal, removal of obsolete vacuum pump components/piping/equipment (as necessary), new vacuum pump installation, installation of new pump piping and related components, and testing & verification that new vacuum pumps are functioning properly and without issues before contract closeout. The Contractor’s responsibilities shall include, but are not limited to, the following:

1. Site assessment and preparation

2. Removal and disposal of existing equipment and associated components

3. Installation of new vacuum pumps and control system, and all associated components

4. All electrical & plumbing integration

5. System testing and commissioning, verification of proper function of new pumps prior to contract closeout

6. Site cleanup (removal of all waste, debris, tools, and unused equipment from work area)

Additional service and equipment requirements of this contract are given in Section 2, “General Requirements”, below.

d) Period of Performance (POP)

This is a One-Time Service Contract; Period of Performance (POP) will be ninety (90) calendar days from the contract award date.

In the event that lead time for new pumps or any associated equipment exceeds the 90-day POP window, an appropriate time extension will be granted as necessary. The time extension will be agreed upon by the Government Contracting Officer’s Representative (COR), Contracting Officer (CO), and the Contractor.

e) Location of Performance

Carl Vinson VA Medical Center | Building 3 Attic

Address: 1826 Veterans Blvd Dublin, GA 31021

f) Type of Contract

Firm-Fixed-Price (FFP), One-Time Service Contract.

g) Hours of Operation

Acceptable working hours will be determined with the COR. Tentative work hours are to be 7:00am to 3:30pm EST, Monday through Friday, excluding holidays.

*Note: some work may need to be completed after-hours or on the weekend*

Normal hours of operation for the hospital are 8:00am to 4:30pm EST, Monday through Friday, excluding holidays. Holidays falling on a Sunday will be observed the following Monday.

Federal Holidays

New Year’s Day January 1st Martin Luther King Day 3rd Monday in January

President’s Day 3rd Monday in February Memorial Day Last Monday in May

Juneteenth June 19th Independence Day July 4th

Labor Day 1st Monday in September Columbus Day 2nd Monday in October Veteran’s Day November 11th

Thanksgiving Day 4th Thursday in November Christmas Day December 25th

2. GENERAL REQUIREMENTS

a) Current Vacuum Pump Removal

The Contractor shall be responsible for providing ALL labor, materials, tools, equipment, and supervision necessary for the removal of the two vacuum pumps currently in use by Dental Services. The Contractor shall be responsible for the safe disconnection of all electrical, plumbing, drain, and ventilation system connections as applicable for both pumps. All disconnection tasks must follow proper lockout/tagout procedures and ensure that all systems are de-energized and depressurized as necessary. The Contractor shall be responsible for safely detaching and removing the existing pumps from their mounting bases and any other physical supports.

The Contractor shall be responsible for removal of any and all associated accessories, such as separators, filters, external piping segments replaced as part of the new installation, and any outdated/obsolete components no longer needed for the new pumping system. The Contractor shall be responsible for the transportation of the removed pumps and equipment off-site and disposing of the removed equipment in accordance with any applicable regulatory requirements. Throughout the entire process, the Contractor shall make every effort to avoid damage to existing building systems, walls, floors, electrical conduit, and other components that will remain in service. Any incidental damage that occurs must be repaired at no additional cost to the Government.

b) Installation of New Vacuum Pumps & Pump Requirements

The Contractor shall supply and install two new vacuum pumps as replacements for the two units currently in place. The Contractor shall be responsible for the supply and installation of new vacuum pumps, including ALL labor, materials, tools, equipment, and supervision necessary for the installation and integration of new pumps. The Contractor shall install the new vacuum pump system in accordance with manufacturer specifications and VA Directives (VHA Directive 7515(1) – Medical Gas and Vacuum Systems), ensuring compliance with any applicable codes, specifically NFPA 99. This includes positioning and securing the new pumps on a secure and level mounting base, ensuring any necessary vibration/noise control, and ensuring adequate clearance for airflow, heat dissipation, and service access.

The Contractor shall connect the new pumps to existing suction lines, waste discharge lines, and any required drainage or condensate outlets, making any necessary adjustments to piping, fittings, and brackets to ensure proper alignment and airtight seals. Electrical connections shall be made in accordance with local electrical codes and matched to the voltage, phase, and load requirements of the new pumps. If the new pumps require external components such as control panels, separators, mufflers, or filters, the Contractor shall install and integrate these as a part of the system.

The Contractor is free to supply and install dental vacuum pumps of its choosing; there is no brand-name preference or restriction associated with this requirement. However, any proposed replacement pumps shall meet or exceed the performance specifications of the existing RAMVAC Bison 9 units, including but not limited to:

• Minimum rated capacity of 80 CFM @ 7" Hg

• Support for a minimum of 10 simultaneous users (10 users per pump, for a total of 20 user rating for the two-pump system)

• Electrical specifications compatible with the existing 208/230V three-phase service

• Oil-lubricated or equivalent-duty rotary vane (or comparable) pump design suitable for continuous multi-operatory dental clinical use

• Compliance with applicable UL, NFPA 99, and FDA medical device requirements for dental vacuum systems

The Contractor shall provide complete technical specification sheets and/or cut sheets for the proposed replacement equipment as part of its submission, demonstrating that the proposed pumps meet or exceed these minimum requirements. Pumps that do not meet the above spec requirements will not be accepted, and failure to supply and install vacuum pumps that do not meet the requirements may result in contract termination.

c) Controller Interface Replacement

The Contractor shall supply and install a new control and monitoring interface system to replace the existing OWL (On-Wall Logic) Touch controller system, which is being replaced as part of this contract. The existing OWL Touch system shall be replaced with a control system that provides equivalent or improved monitoring, control, and alarm functionality for all vacuum units and associated equipment, including pump start/stop control, vacuum pressure monitoring and digital display, fault/alarm detection and notification, and compatibility with the newly installed vacuum pumps and any other system components it is intended to control or monitor. The new control system supplied and installed by the Contractor must retain monitoring and control capabilities for the two RAMVAC Osprey Air Compressors controlled and monitored by the current OWL system. Replacement of the control system shall include all associated system components, including but not limited to:

• OWL Touch Display Panel

• OWL Hub Unit

• Associated power supply / transformer

• Any other components needed for full system functionality, including additional wiring (if necessary) The new control system shall be fully compatible with, and capable of interfacing with, the newly installed vacuum pumps and all associated system components under its control, including but not limited to pump motor start/stop and run status, vacuum pressure monitoring and digital display, moisture/fault detection and alarm indication, oil level or lubrication system monitoring (if applicable to the proposed pump design), and any remote switch stations or low-voltage control wiring serving the dental operatories.

The proposed controller does not have to be a brand-name match to the replacement pumps but shall be fully integrated and configured by the Contractor to provide seamless, reliable operation of the complete vacuum system as a unified unit, with no loss of functionality, monitoring capability, or alarm/notification features compared to the system being replaced.

In the event the proposed controller and replacement pumps are of different manufacturers, the Contractor shall provide written documentation such as a manufacturer compatibility statement, integration certification, or equivalent technical confirmation, demonstrating that the proposed controller is rated and supported by its manufacturer for use with the specific proposed pump model, prior to installation and as part of its technical submission.

d) Testing & Verification

After installation of new vacuum pumps, control system, and all associated components, the Contractor shall perform testing and verification for proper operation of the new vacuum pump system, including verification of suction performance, conducting leak testing, ensuring proper ventilation and noise control, and confirming that the new pumps and control system meet all operational requirements and manufacturer specifications.

This testing must be done with VA Facility Maintenance personnel present to verify proper system operation prior to acceptance. The Contractor shall demonstrate full system functionality in the presence of VA Facility Maintenance personnel, including startup and shutdown sequences, alarm and fault indication response, pressure/vacuum readings at representative operatories, and overall system performance under simulated clinical load conditions. Any functional or operational defects identified during testing and verification shall be corrected at the sole expense of the Contractor, and the new vacuum pumps and control system must be verified to be functioning correctly before contract closeout.

If requested by CVVAMC Facility Maintenance staff, the Contractor shall also provide hands-on orientation to VA Facility Maintenance personnel on routine operation, monitoring, and basic troubleshooting of the new pumps and control system.

Upon successful completion of testing, the Contractor shall provide all operation and maintenance manuals, warranty documentation, any as-built documentation, and shall obtain written acknowledgment/sign-off from VA Facility Maintenance personnel confirming that the system has been tested, demonstrated, and accepted as fully operational prior to final contract closeout.

e) Contractor Installer Certifications

The Contractor shall ensure that all personnel performing installation of the new dental vacuum pump system hold a current ASSE 6010 Medical Gas Systems Installer certification, in accordance with NFPA 99 (Health Care Facilities Code) requirements for medical-surgical vacuum systems.

f) Site Access, Coordination, and CVVAMC Assistance

The COR will serve as the primary Point of Contact (POC) and acceptance authority.

The VA will not be responsible for storage of equipment, materials, or tools.

The Contractor must check in with the COR or other designated VA personnel daily upon arrival at the facility. The check-in method will be up to the COR’s discretion. Failure to comply may result in issues with VA Police or other facility personnel.

It is the vendor’s responsibility to properly assess the working conditions and include in the bid any specialty equipment, training, additional time, personnel, or safety equipment to perform the work safely and in compliance with all applicable local, State, and Federal regulations.

All work shall be coordinated in advance with the COR or other designated VA facility personnel. This is to avoid disruption of Dental Services and patient care during normal hours of operation. No work will be performed without prior coordination and schedule approval with the COR. To avoid disruptions to Dental Services, pump removal and installation may need to be performed over the weekend or after normal hospital hours of operation. This determination will be made at the discretion of the COR.

g) Other Requirements

The Contractor shall follow all safety measures to ensure a safe working environment for all involved. The Contractor is expected to always keep the work environment clean and safe.

Employees of the Contractor and subcontractors shall always conduct themselves in a professional manner while on medical center property. The vendor shall ensure all personnel working on this contract are aware of Medical Center rules pertaining to employee behavior and conduct. Physical or verbal misconduct may be grounds for removing employees from Medical Center property, or grounds for arrest by the VA Police. Employees may be banned from Medical Center property as a result of inappropriate or illegal behavior. The vendor shall not be entitled to any compensation from the Government for any costs resulting from employee misconduct (including, but not limited to, delays in contract completion) and may be held liable for costs incurred by the Government as a result of employee misconduct.

Hospital operations and patient care shall take priority. Any anticipated disruptions to normal operations must be communicated and approved by the COR and other VA personnel as necessary. The Contractor shall take any measures necessary to ensure that patient care services are uninterrupted and unaffected by the work being performed.

3. CHANGES TO STATEMENT OF WORK (SOW)

Any changes to this SOW shall be authorized and approved only through written correspondence from the Government Contracting Officer (CO). A copy of each change will be kept in a project folder along with all other products of the project. Costs incurred by the Contractor through the actions of parties other than the CO shall be borne solely by the Contractor.

4. SECURITY

a) General Security Requirements

Contractors, Contractor personnel, subcontractors, and subcontractor personnel shall be subject to the same Federal laws, regulations, standards, and VA Directives and Handbooks as VA and VA personnel regarding information and information system security.

5. PARKING / LAYDOWN AREA

The Contractor shall make necessary arrangements for parking. There shall be no Contractor or subcontractor vehicles parked on roadways, in patient parking areas, obstructing the loading dock, etc.

The Contractor shall coordinate loading/unloading of materials/equipment in advance with the COR, including any use of the loading dock. Materials shall not be deposited on the loading dock for any length of time.

There is no guarantee for laydown of equipment. The CVVAMC shall not provide an extensive area for storage of any equipment. It is the responsibility of the Contractor to ensure their equipment remains secure.

GENERAL INFORMATION
a) Purpose
b) Background
c) Scope of Work
d) Period of Performance (POP)
e) Location of Performance
f) Type of Contract
g) Hours of Operation
2. GENERAL REQUIREMENTS
a) Current Vacuum Pump Removal
b) Installation of New Vacuum Pumps & Pump Requirements
c) Controller Interface Replacement
d) Testing & Verification
e) Contractor Installer Certifications
f) Site Access, Coordination, and CVVAMC Assistance
g) Other Requirements
3. CHANGES TO STATEMENT OF WORK (SOW)
4. SECURITY
a) General Security Requirements

5. PARKING / LAYDOWN AREA