Attachment III 557-23-104 - Bid Documents - Specifications REV28Oct2026_.pdf
PDF 7 MB Posted
- Attached to
- Z2DA--FY27 NRM | 557-23-104 | Replace Boiler Plant Steam Boilers | Construction (VA-27-00003633)
- Solicitation number
- 36C24726R0137_1
About this file
This document is a comprehensive specification and bid document for a federal construction project to replace boiler plant steam boilers at Carl Vinson VA Medical Center in Dublin, Georgia (Project 557-23-104). The contract requires the contractor to perform complete demolition of existing boiler plant structures and equipment, installation of new steam boilers and ancillary equipment, and all associated general construction, alterations, selective demolition, asbestos abatement, and connections to existing utilities. The base bid (Item I) has a period of performance of 730 days, with an optional deduct (Item II) to remove third-party commissioning agent requirements. The document establishes detailed requirements for contractor operations including security procedures, site access restrictions, utility management, phasing coordination to maintain 24/7 medical center operations, and comprehensive documentation requirements such as photographic progress tracking with digital indexing, as-built drawings, and warranty management. Key contractor responsibilities include developing a Critical Path Method (CPM) schedule with approximately 250 work activities, monthly cost-loaded updates, monthly payment applications coordinated with schedule approvals, maintenance and operating manuals with factory-trained instruction for all equipment, and comprehensive testing and commissioning of all mechanical and electrical systems. The specification mandates compliance with VA Master Specifications across multiple divisions including structural, mechanical, HVAC, plumbing, electrical, fire suppression, and communications systems, with specific technical sections referenced throughout for detailed performance standards and inspection requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment II 557-23-104 - Bid Drawings.pdf | ||
| 36C24726R0137_1 RFP.docx | DOCX document | |
| 36C24726R0137_1.docx | DOCX document | |
| Attachment IV 557-23-104 Construction SOW.docx | DOCX document | |
| Attachment V - SF24-23a Bid Bond.pdf | ||
| Attachment I - DBA Wage Deteremination GA20260095.pdf | ||
| Attachment VII VAAR 852.219-75 VA NOTICE OF LIMITATION ON SUBCONTRACTING CERTIFICATE OF COMPLIANCE.docx | DOCX document | |
| Attachment VI Past Performance Forms.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT # 557-23-104
Replace Boiler Plant Steam Boilers
Carl Vinson VA Medical Center 1826 Veterans Boulevard Dublin, GA 31021-3620
SPECIFICATIONS
BID DOCUMENTS 100% REV
07/10/2026
PREPARED BY
Carl Vinson VA Medical Center, Project 557-23-104
08-01-2025
TABLE OF CONTENTS
00 01 10 - 1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-21 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 01-24 01 33 23 Shop Drawings, Product Data, and Samples 06-25 01 35 26 Safety Requirements 05-24 01 42 19 Reference Standards 11-20 01 45 00 Quality Control 02-21 01 45 29 Testing Laboratory Services 11-18 01 45 35 Special Inspections 06-21 01 57 19 Temporary Environmental Controls 01-21 01 74 19 Construction Waste Management 04-22 01 81 13 Sustainable Construction Requirements 10-17 01 91 00 General Commissioning Requirements 04-22
DIVISION 02 – EXISTING CONDITIONS
02 21 13 Site Surveys 12-23 02 41 20 Selective Building Demolition 02 82 11 Traditional Asbestos Abatement 01-21 02 82 13.13 Glovebag Asbestos Abatement 01-21 02 82 13.21 Asbestos Roofing Abatement 01-21 02 83 33.13 Lead-Based Paint Removal and Disposal 01-21
DIVISION 03 – CONCRETE
03 30 53 (Short-Form) Cast-in-Place Concrete 01-21
DIVISION 04 – MASONRY
04 05 13 Masonry Mortaring 10-17 04 05 16 Masonry Grouting 01-21 04 20 00 Unit Masonry 08-17
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 11-18 05 36 00 Composite Metal Decking 01-21 05 50 00 Metal Fabrications 08-18 05 51 00 Metal Stairs 01-21
08-01-2025
TABLE OF CONTENTS
00 01 10 - 2
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-17
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 84 00 Firestopping 01-21 07 92 00 Joint Sealants 04-22
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-21 08 71 00 Door Hardware 03-24 08 90 00 Louvers and Vents 01-21
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 01-21 09 67 23.60 Resinous Urethane and Epoxy Mortar Flooring (RES-6A and
RES 6B)
01-21
09 91 00 Painting 01-21
DIVISION 10 – SPECIALTIES
10 14 00 Signage 01-21 10 44 16 Fire Extinguisher
DIVISION 11 – EQUIPMENT
DIVISION 12 – FURNISHINGS
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural Components
01-21
DIVISION 14– CONVEYING EQUIPEMENT
DIVISION 21- FIRE SUPPRESSION
21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 01-23 22 05 19 Meters and Gages for Plumbing Piping 09-20 22 05 23 General-Duty Valves for Plumbing Piping 09-20 22 07 11 Plumbing Insulation 09-19
08-01-2025
TABLE OF CONTENTS
00 01 10 - 3
SECTION NO DIVISION AND SECTION TITLES DATE
22 08 00 Commissioning of Plumbing Systems 11-16 22 11 00 Facility Water Distribution 05-21 22 13 00 Facility Sanitary and Vent Piping 09-20 22 13 23 Sanitary Waste Interceptors 09-20 22 15 00 General Service Compressed-Air Systems 09-20 22 31 11 Water Softeners 09-15 22 40 00 Plumbing Fixtures 05-24
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 10 Common Work Results for Boiler Plant and Steam Generation
06-24
23 05 11 Common Work Results for HVAC 03-23 23 05 12 General Motor Requirements for HVAC and Steam
Generation Equipment 03-23
23 05 41 Noise and Vibration Control for HVAC Piping and Equipment
03-23
23 05 51 Noise and Vibration Control for Boiler Plant 03-22 23 05 93 Testing, Adjusting, and Balancing for HVAC 03-23 23 07 11 HVAC and Boiler Plant Insulation 02-20 23 08 00 Commissioning of HVAC Systems 03-23 23 08 11 Demonstrations and Tests for Boiler Plant 04-20 23 09 11 Instrumentation and Control for Boiler Plant 04-24 23 09 23 Direct-Digital Control System for HVAC 03-23 23 10 00 Facility Fuel Systems 04-20 23 21 11 Boiler Plant Piping Systems 03-24
03-24 23 23 00 Refrigerant Piping 03-24 23 31 00 HVAC Ducts and Casings 03-23 23 34 00 HVAC Fans 03-23 23 37 00 Air Outlets and Inlets 03-23 23 50 11 Boiler Plant Mechanical Equipment 03-22 23 51 00 Breechings, Chimneys, and Stacks 04-20 23 52 39 Fire Tube Boilers 06-25 23 81 00 Decentralized Unitary HVAC Equipment 03-24 23 82 16 Air Coils 03-24
DIVISION 25 – INTEGRATED AUTOMATION
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 11-22 26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22 26 05 26 Grounding and Bonding for Electrical Systems 11-22 26 05 33 Raceway and Boxes for Electrical Systems 11-22 26 05 73 Overcurrent Protective Device Coordination Study 11-22 26 08 00 Commissioning of Electrical Systems 11-22 26 09 23 Lighting Controls 11-22 26 22 00 Low-Voltage Transformers 11-22
08-01-2025
TABLE OF CONTENTS
00 01 10 - 4
SECTION NO DIVISION AND SECTION TITLES DATE
26 24 13 Distribution Switchboards 11-22 26 24 16 Panelboards 11-22 26 27 26 Wiring Devices 11-22 26 29 11 Motor Controllers 11-22 26 29 21 Enclosed Switches and Circuit Breakers 11-22 26 32 13 Engine Generators 11-22 26 36 23 Automatic Transfer Switches 11-22 26 43 13 Surge Protective Devices 11-22
26 51 00 Interior Lighting 03-24
26 56 00 Exterior Lighting 11-22
DIVISION 27 – COMMUNICATIONS
27 05 26i Grounding and Bonding for Communications Systems 06-15
27 05 33i Conduits and Back Boxes for Communications Systems 12-22
27 05 53i Identification for Communications Systems 12-22
27 10 00i Structured Cabling 12-22
27 11 16i Communications Cabinets, Racks, Frames and Enclosures 12-22
27 11 19i Communications Termination Blocks and Patch Panels 12-22
27 13 23.13i
Communications Optical Fiber Splicing and Terminations 12-22
27 13 23i Communications Optical Fiber Backbone Cabling 12-22
27 15 13i Communications Copper Horizontal Cabling 12-22
27 16 19i Communications Patch Cords, Station Cords and Cross Connect Wire
12-22
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 04-18 28 05 13 Conductors and Cables for Electronic Safety and
Security 10-18
28 05 26 Grounding and Bonding for Electronic Safety and Security
09-11
28 05 28.33 Conduits and Backboxes for Electronic Safety and Security
09-11
28 13 00 Physical Access Control System 10-11 28 23 00 Video Surveillance 09-11 28 31 00 Fire Detection and Alarm 10-11
DIVISION 31 – EARTHWORK
31 20 00 Earthwork 08-23 31 23 19 Dewatering 10-12
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 12 16 Asphalt Paving 09-15
08-01-2025
TABLE OF CONTENTS
00 01 10 - 5
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 33 – UTILITIES
33 30 00 Sanitary Sewer Utilities 06-13
DIVISION 34 – TRANSPORTATION
DIVISION 48 – Electrical Power Generation
APPENDIX A – Pre-Renovation Asbestos Inspection and Lead Paint Sampling
05-01-20
LIST OF DRAWING SHEETS
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
GENERAL
GI000 COVER SHEET
GI001 SYMBOLS, ABBREVIATIONS AND ACCESSIBILITY
GI002 WALL TYPES, ACCESSIBILITY REQUIREMENTS
GI003 LIFE SAFETY PLANS
GI004 PHASING PLAN
CIVIL
C100 CIVIL DETAILS
C101 CIVIL DETAILS
C102 CIVIL DETAILS
C200 EXISTING SITE PLAN - NORTH
C201 EXISTING SITE PLAN - SOUTH
C210 SITE DEMOLITION PLAN - NORTH
C211 SITE DEMOLITION PLAN - SOUTH
C300 CONSTRUCTION PHASE SITE PLAN - NORTH
C301 CONSTRUCTION PHASE SITE PLAN - SOUTH
C400 SITE LAYOUT PLAN - NORTH
C401 SITE LAYOUT PLAN - SOUTH
C500 SITE UTILITY PLAN - NORTH
C501 SITE UTILITY PLAN - SOUTH
C600 SITE GRADING PLAN - NORTH
C601 SITE GRADING PLAN - SOUTH
STRUCTURAL
S001 STRUCTURAL GENERAL NOTES
SD101 FOUNDATION AND SLAB DEMOLITION PLANS
SD102 FRAMING DEMOLITION PLANS
SB101 FOUNDATION AND SLAB PLANS
SB501 FOUNDATION SECTIONS AND DETAILS
SF101 MEZZANINE, CATWALK, AND ROOF FRAMING PLANS
SF201 EXTERIOR ELEVATIONS
05-01-20
LIST OF DRAWING SHEETS
00 01 15 - 2
Drawing No. Title
SF401 ENLARGED FRAMING PLANS
SF402 ENLARGED FRAMING PLANS
SF501 FRAMING SECTIONS AND DETAILS
ARCHITECTURE
AD101 DEMOLITION PLANS
AE101 FIRST FLOOR
AE102 MEZZANINE PLANS
AE131 MEZZANINE AND ROOF PLAN
AE141 REFLECTED CEILING PLANS
AE201 EXTERIOR ELEVATIONS
AE202 EXTERIOR ELEVATIONS
AE301 BUILDING SECTIONS
AE311 WALL SECTIONS
AE312 WALL SECTIONS
AE401 ENLARGED DETAILS
AE402 ENLARGED DETAILS
AE601 SCHEDULES
FIRE SUPPRESSION
F001 FIRE SUPPRESSION ABBREVIATIONS, LEGEND AND DESIGN NOTES
FX101 FIRE SUPPRESSION FIRST FLOOR PLAN
FX102 FIRE SUPPRESSION MEZZANINE PLAN
PLUMBING
P001 PLUMBING ABBREVIATIONS, LEGEND, & GENERAL NOTES
PD100 PLUMBING UNDERSLAB PLAN - DEMO
PD101 PLUMBING FIRST FLOOR PLAN - DEMO
PD102 PLUMBING MEZZANINE PLAN - DEMO
PP100 PLUMBING UNDERSLAB PLAN - DRAINAGE
PP101 PLUMBING FIRST FLOOR PLAN
PP102 PLUMBING MEZZANINE PLAN
P500 PLUMBING SCHEDULES & DETAILS
P901 ISOMETRIC - DRAINAGE
P902 ISOMETRIC - DISTRIBUTION
05-01-20
LIST OF DRAWING SHEETS
00 01 15 - 3
Drawing No. Title
MECHANICAL
M001 MECHANICAL LEGEND
MD101 MECHANICAL - DEMOLITION FIRST FLOOR PLAN
MH101 MECHANICAL - FIRST FLOOR PLAN
MH102 MECHANICAL - MEZZANINE LEVEL 1 PLAN
MH103 MECHANICAL - MEZZANINE LEVEL 2 PLAN
MH104 MECHANICAL - PENTHOUSE PLAN
MPH101 MECHANICAL - FIRST FLOOR PLAN - PIPING
MPH102 MECHANICAL - MEZZANINE LEVEL 1 PLAN - PIPING
MPH103 MECHANICAL - MEZZANINE LEVEL 2 PLAN - PIPING
MPH104 MECHANICAL - PENTHOUSE PLAN - PIPING
M401 MECHANICAL - ELEVATIONS
M402 MECHANICAL - ELEVATIONS
M403 MECHANICAL - 3D VIEWS
M501 MECHANICAL - DETAILS
M502 MECHANICAL - DETAILS
M601 MECHANICAL - SCHEDULES
M602 MECHANICAL - SCHEDULES
M701 MECHANICAL - HVAC CONTROLS
MP001 BOILER PLANT NOTES, LEGENDS, AND ABBREVIATIONS
MP101 TRENCH LEVEL DEMOLITION
MP102 OPERATING FLOOR DEMOLITION
MP103 MEZZANINE DEMOLITION
MP104 ROOF DEMOLITION
MP105 PLANT EXTERIOR DEMOLITION
MP201 TRENCH LEVEL NEW WORK
MP202 OPERATING FLOOR NEW WORK
MP203 MEZZANINE NEW WORK
MP204 ROOF NEW WORK
MP205 PLANT EXTERIOR NEW WORK
MP301 BOILER - MECHANICAL VIEWS - NEW WORK
MP302 FEEDWATER - MECHANICAL VIEWS - NEW WORK
MP303 CST - MECHANICAL VIEWS - NEW WORK
MP304 STEAM HEADER - MECHANICAL VIEWS - NEW WORK
MP305 SAMPLE COOLERS - MECHANICAL VIEWS - NEW WORK
MP306 FUEL OIL - MECHANICAL VIEWS - NEW WORK
05-01-20
LIST OF DRAWING SHEETS
00 01 15 - 4
Drawing No. Title
MP307 PRV STATIONS - MECHANICAL VIEWS - NEW WORK
MP401 BOILERS 1 & 2 FUEL P&ID SCHEMATICS - DEMOLITION
MP402 BOILERS 1 & 2 TRIM P&ID SCHEMATICS - DEMOLITION
MP403 BOILER 3 FUEL P&ID SCHEMATIC - DEMOLITION
MP404 BOILER 3 TRIM P&ID SCHEMATIC - DEMOLITION
MP405 STEAM P&ID - DEMOLITION
MP406 CONDENSATE RETURN P&ID - DEMOLITION
MP407 CTT P&ID - DEMOLITION
MP408 DEAERATOR AND FEEDWATER P&ID - DEMOLITION
MP409 FUEL OIL AND NATURAL GAS P&ID - DEMOLITION
MP410 CITY WATER AND SOFT WATER P&ID - DEMOLITION
MP411 BLOWDOWN P&ID - DEMOLITION
MP501 BOILER FUEL TRAINS AND TRIM P&ID - NEW WORK
MP502 BOILER FUEL TRAINS AND TRIM P&ID - NEW WORK
MP503 DEAERATOR AND FEEDWATER P&ID
MP504 CONDENSATE TANK P&ID
MP505 STEAM P&ID
MP506 NATURAL GAS AND PROPANE P&ID
MP507 BOILER BLOWDOWN P&ID
MP508 CHEMICAL FEED SYSTEM
MP509 FUEL OIL P&ID
MP510 TEMPORARY BOILERS
MP601 BOILER DETAILS
MP602 BOILER DETAILS
MP603 BOILER DETAILS
MP604 BOILER DETAILS
MP605 BOILER DETAILS
MP701 BOILER PLANT SCHEDULES
MP702 BOILER PLANT SCHEDULES
MP703 BOILER PLANT PIPING INDEX
MP704 VALVE SCHEDULE
MP705 VALVE SCHEDULE
MP706 HAZARDOUS GAS DETECTION SYSTEM DETAILS
MP707 EMERGENCY STOP DETAILS
MP708 CONTROLS SYSTEM ARCHITECTURE
MP709 TEMPORARY BOILER CONTROLS SYSTEM ARCHITECTURE
05-01-20
LIST OF DRAWING SHEETS
00 01 15 - 5
Drawing No. Title
MP801 BOILER CONTROL POINTS LIST
MP802 BOILER CONTROL POINTS LIST
MP803 BOILER CONTROL POINTS LIST
MP804 BOILER CONTROL POINTS LIST
ELECTRICAL
E001 ELECTRICAL NOTES, SYMBOLS AND ABBREVIATIONS
ES100 ELECTRICAL SITE PLAN
ED100 ELECTRICAL - DEMO
EL100 ELECTRICAL FIRST FLOOR PLAN - LIGHTING
EP100 ELECTRICAL FIRST FLOOR PLAN- POWER
EF100 ELECTRICAL FIRST FLOOR - SPECIAL SYSTEMS
E400 ELECTRICAL ENLARGED PLANS
E600 PANEL SCHEDULES
E700 ELECTRICAL SINGLE-LINE
TECHNOLOGY
T001 TECHNOLOGY LEGEND SHEET
TS100 TECHNOLOGY SITE PLAN
T101 FIRST FLOOR - TECHNOLOGY NEW WORK PLAN
T401 ENLARGED SIGNALS ROOM PLAN
T601 TECHNOLOGY DETAILS
T602 TECHNOLOGY DETAILS
T603 TECHNOLOGY DETAILS
---END---
11-01-21
GENERAL REQUIREMENTS
01 00 00 - 1
SECTION 01 00 00
GENERAL REQUIREMENTS
GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work to replace the existing steam boilers and ancillary equipment within the boiler plant as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the
Medical Center Engineering Officer.
C. Offices of FFE-Heapy JV, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
STATEMENT OF BID ITEM(S)
E. ITEM I, BASE BID: Work includes replacement of steam boilers in existing boiler plant, along with general construction, alterations, selective demolition, abatement, installation of equipment, and connections to existing utilities. Period of performance is 730 days.
F. ITEM II, Bid Deduct: Work includes base bid, with deduct to remove requirement for 3rd party commissioning agent hired by Contractor.
1.3 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.4 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
11-01-21
GENERAL REQUIREMENTS
01 00 00 - 2
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71
00, DOOR HARDWARE and coordinate.
D. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This
11-01-21
GENERAL REQUIREMENTS
01 00 00 - 3 information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
a) Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
b) “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
E. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of permits shall be issued for General Contractor and its employees for parking in designated areas only. Contractor to coordinate with VA Medical Center Facility Manager.
1.5 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
11-01-21
GENERAL REQUIREMENTS
01 00 00 - 4
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as determined by the COR.
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
11-01-21
GENERAL REQUIREMENTS
01 00 00 - 5
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
I. Phasing:
1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. See Drawing sheet GI004 for Phasing
Plan and Notes.
2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to ensure accomplishment of this work in successive phases mutually agreeable to Medical Center Director, COR, and Contractor.
J. Building No. 27 will be partially vacated by Government in accordance with above phasing beginning immediately after date of receipt of
Notice to Proceed and only the boiler plant area turned over to
Contractor.
K. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet)
11-01-21
GENERAL REQUIREMENTS
01 00 00 - 6 minimum height, around the construction area indicated on the drawings.
Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm
(one inch) above grade. Remove the fence when directed by COR.
L. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from
Contractor's employee or watchman.
M. Utilities Services: Maintain existing utility services for Medical
Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR
COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR
ELECTRONIC SAFETY AND SECURITY for additional requirements.
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 14 days in advance of proposed interruption.
11-01-21
GENERAL REQUIREMENTS
01 00 00 - 7
Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 21 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
N. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
O. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
P. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
11-01-21
GENERAL REQUIREMENTS
01 00 00 - 8
1.6 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of flooring, doors, windows, walls and other surfaces not required to be altered throughout the building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government.
Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly.
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
11-01-21
GENERAL REQUIREMENTS
01 00 00 - 9
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.7 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
PROTECTION OF EXISTING VEGETATION,
STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
B. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs
GENERAL REQUIREMENTS
01 00 00 - 10
11-01-21 or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
C. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The
Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
D. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to
Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements. RESTORATION
E. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the
COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
F. Upon completion of contract, deliver work complete and undamaged. Existing work
(walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
G. All lawn and grassed areas disturbed by construction activities, utility installation, equipment access, stockpiling, or restoration work shall be restored upon completion of the Work. Restore disturbed areas by placing topsoil as required, fine grading, fertilizing, seeding, mulching, and watering to establish a healthy, uniform stand of turf matching adjacent existing grass.
Maintain restored areas until a satisfactory stand of grass has been established. Areas exhibiting erosion, bare spots, or unsuccessful germination shall be regraded and reseeded at no additional cost to the Government until accepted by the COR.
GENERAL REQUIREMENTS
01 00 00 - 11
H. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
I. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price.
PROFESSIONAL SURVEYING SERVICES
J. A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections.
The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.
AS-BUILT DRAWINGS
J. K. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
L. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
M. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
N. Paragraphs A, B, & C shall also apply to all shop drawings.
1.8 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan in at least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the
Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn
11-01-21
GENERAL REQUIREMENTS
01 00 00 - 12 over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.
2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.
3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
4. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers and suppliers.
e. Name and phone numbers of manufacturers or suppliers.
f. Names, addresses and phone numbers of sources of spare parts.
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.
h. Starting point and duration of warranty period.
i. Summary of maintenance procedures required to continue the warranty in force.
j. Cross-reference to specific pertinent Operation and Maintenance manuals.
k. Organizations, names and phone numbers of persons to call for warranty service.
l. Typical response time and repair time expected for various warranted equipment.
11-01-21
GENERAL REQUIREMENTS
01 00 00 - 13
5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
6. Procedure and status of tagging of all equipment covered by extended warranties.
7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
B. Performance & Payment Bonds: The Performance & Payment Bonds must remain effective throughout the construction period.
1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.
3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.
C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for
Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for
Contractor response, and other details deemed necessary by the
Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor.
This point of contract will be located within the local service area of
11-01-21
GENERAL REQUIREMENTS
01 00 00 - 14 the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.
D. Contractor’s Response to Construction Warranty Service Requirements:
E. Following oral or written notification by the Contracting Officer, the
Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period.
Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the
Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.
1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.
2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.
3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.
4. The “Construction Warranty Service Priority List” is as follows:
a)Code 1-Life Safety Systems
1) Fire suppression systems.
2) Fire alarm system(s).
b)Code 1-Air Conditioning Systems
1) Air conditioning leak in part of the building, if causing damage.
2) Air conditioning system not cooling properly.
c)Code 1 Doors
1) Overhead doors not operational, causing a security, fire or safety problem.
1) Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.
d)Code 3-Doors
11-01-21
GENERAL REQUIREMENTS
01 00 00 - 15
1) Overhead doors not operational.
2) Interior/exterior personnel doors or hardware not functioning properly.
e)Code 1-Electrical
1) Power failure (entire area or any building operational after
1600 hours).
2) Security lights.
3) Smoke detectors.
f)Code 2-Electrical
1) Power failure (no power to a room or part of building).
Receptacle and lights not operational (in a room or part of building).
g)Code 3-Electrical
1) Exterior lights not operational.
h)Code 1-Gas
1) Leaks and pipeline breaks.
i)Code 1-Heat
1) Power failure affecting heat.
j)Code 1-Plumbing
1) Hot water heater failure.
2) Leaking water supply pipes k)Code 2-Plumbing
1) Flush valves not operating properly
2) Fixture drain, supply line or any water pipe leaking.
3) Toilet leaking at base.
l)Code 3- Plumbing
1) Leaky faucets.
m)Code 3-Interior
1) Floors damaged.
2) Paint chipping or peeling.
3) Casework damaged.
n)Code 1-Roof Leaks
1) Damage to property is occurring.
o)Code 2-Water (Exterior)
1) No water to facility.
p)Code 2-Water (Hot)
1) No hot water in portion of building listed.
q)Code 3
11-01-21
GENERAL REQUIREMENTS
01 00 00 - 16
1) All work not listed above.
F. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting
Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.
Warranty Tags
Type of product/material
Model number
Serial number
Contract number
Warranty period from/to
Inspector’s signature
Construction Contractor
Address
Telephone number
Warranty Contact
Address
Telephone number
Warranty response time priority code
1.9 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical
Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
1.10 TEMPORARY TOILETS
A. Provide where directed, (for use of all Contractor's workers) ample temporary sanitary toilet accommodations with suitable sewer and water connections; or, when approved by COR, provide suitable dry closets where directed. Keep such places clean and free from flies and all
11-01-21
GENERAL REQUIREMENTS
01 00 00 - 17 connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
1.11 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.
C. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:
1. Obtain heat by connecting to Medical Center heating distribution system, if available. Provide supplemental heat if necessary.
D. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Medical Center electrical distribution system. Electricity for all uses is available at no cost to the Contractor.
E. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the
Contractor.
2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes
11-01-21
GENERAL REQUIREMENTS
01 00 00 - 18 will be cause for revocation (at COR discretion) of use of water from Medical Center's system.
F. Fuel: Natural and LP gas and burner fuel oil required for boiler cleaning, normal initial boiler-burner setup and adjusting, and for performing the specified boiler tests will be furnished by the
Government. Fuel required for prolonged boiler-burner setup, adjustments, or modifications due to improper design or operation of boiler, burner, or control devices shall be furnished and paid by the
Contractor at Contractor's expense.
1.12 TESTS
A. As per specification section 23 05 93 the contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The contractor shall document the results of the approved plan and submit for approval with the as built documentation.
B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems…