Durham_VAMC_Combined_RFI_Log_11202206 posted.xlsx
XLSX spreadsheet 53 KB Posted
- Attached to
- Z2DA--FY27 NRM 558-24-160, Domestic Water, Chilled Water and Steam Piping (VA-26-00066009)
- Solicitation number
- 36C24626B0041_1
About this file
This is a combined Pre-Bid Request for Information (RFI) Log for the Durham VA Medical Center piping replacement project (Solicitation 36C24626B0041, Project 558-24-160). The log documents 139 total RFIs submitted by bidders and design team responses addressing clarifications needed for the domestic water, chilled water, and steam piping replacement work at the Durham VA Health Care System, 508 Fulton Street, Durham, North Carolina. The project scope includes replacing aging piping in Buildings 1 and 23 with a 603-calendar-day completion period from Notice to Proceed and encompasses asbestos abatement, infection control measures, temporary construction barriers, phasing coordination, and utility interruption management to minimize disruption to the 24-hour operating healthcare facility.
Key RFI topics include asbestos abatement procedures (glove bag method applicability, testing requirements for disturbed elements, decontamination facility locations and configuration), Infection Control Risk Assessment (ICRA) level requirements, missing or incomplete drawing sheets (P-505, GC201), scope clarification regarding Alternate No. 1 (operating room addition deletion that was subsequently removed from specifications per design team response), utility shutdown notice periods (revised to 25 business days), work-hour restrictions (after 9:00 PM for night/weekend work in common areas), and seasonal temperature constraints for chilled water and steam systems. The design team responses, dated November 12, 2026, with specification revisions dated November 20, 2026, address contractor concerns regarding feasibility, space constraints, and regulatory compliance, with most RFIs marked as issued and closed. The VA is the federal agency contracting entity through the Veterans Health Administration, Veterans Integrated Service Network 6.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI Log
| Durham VA Medical Center - Project 558-24-160 (Domestic Water, Chilled Water and Steam Piping) - Solicitation 36C24626B0041 | ||||||||||||
| Combined Pre-Bid RFI Log: | ||||||||||||
| Total RFIs: | 139 | |||||||||||
| RFI No. | Category | Spec Section / Drawing | Sub-Section / Reference | Subject (summary) | RFI Question (as submitted) | Design Team Response | Responded By | Date Responded | Status | Reviewer Comments / QC | Addendum / Spec Revision Required? | Notes / Coordination (other disciplines, VA input) |
| ACM-01 | Asbestos Abatement | 02 82 13.13 | Part 1 - General, 1.1 Summary of Work (B.1) | Glove bag method / 'asbestos contaminated elements' | Extent of Work. Document call for the use of the "Glove bag Method" for asbestos contaminated elements. Glove bags cannot be used for contaminated elements, only on pipe insulation/fittings. Please provide clarification on "asbestos contaminated elements'. | A Traditional Abatement Specifications can be provided for the contaminated elements. Refer to revised specifications dated 11/20/2026. | HS | 11/12/26 | Issued / Closed | |||
| ACM-02 | Asbestos Abatement | 02 82 13.13 | Part 1 - General, 1.1 Summary of Work (B.1) | Asbestos test results for all items to be disturbed | Most of the identified work areas will require removing structural elements (drywall/ceiling tiles/plaster, etc.) to gain access to the pipe/fitting insulation to be removed. Please provide the asbestos testing results for ALL items to be disturbed for asbestos abatement or construction activities. | The survey was only assigned to identify and quantify piping system. A previous survey report of 2017 was provided VA identifying the ACM and that report did not identify any plaster or drywall as ACM. The 2017 asbestos survey report can be provided. | HS | 11/12/26 | Issued / Closed | |||
| ACM-03 | Asbestos Abatement | 02 82 13.13 | Part 1 - General, 1.1 Summary of Work (B.1) | Vertical pipe chases, basement to 10th floor (bullet #3) | Bullet #3 indicates unknown quantity of pipe and fitting insulation on fiberglass lines in vertical pipe chases from the basement to the 10th floor. Are these vertical pipe chases different than where the pipe insulation and fitting insulation listed in bullets 1 & 2 are located? If so, please identify these additional areas. | The pipe insulation behind the walls in the vertical pipe chases needs to be disturbed only if those pipe chases are demolished to access it. The pipe chases were marked on the Plumbing drawings. If the pipes are not scheduled to be disturbed, those are not required to be abated. | HS | 11/12/26 | Issued / Closed | |||
| ACM-04 | Asbestos Abatement | 02 82 13.13 | Part 1 - General, 1.9 Decontamination Facilities | Decon facility space above basement floors | Spec section calls for both a separate personnel decontamination facility and a waste/equipment decontamination facility. Location of the insulation to be removed at most areas above the basement floors do not allow enough space with out blocking other entrances and path of travels. Please provide clarification or direction. | The same decontamination facility can be utilized if there are space constraints. | HS | 11/12/26 | Issued / Closed | |||
| ACM-05 | Asbestos Abatement | 02 82 13.13 | Part 1 - General, 1.9 Decontamination Facilities | Decon clean room access from building exterior | Spec section calls for personnel decontamination facility that "the clean room shall be located so as to provide access to the holding room from the building exterior." In addition, Spec section calls for waste/equipment decontamination facility that "the clean room shall be located so as to provide access to the holding room from the building exterior." Both these two requirements are not achievable on this project. Please provide clarification or direction. | The access for holding room is for the location where the waste maybe stored prior to disposal in the floor with direct access to building exterior. The rest of the floor locations this requirement is not feasible to implement. | HS | 11/12/26 | Issued / Closed | |||
| ACM-06 | Asbestos Abatement | 02 82 13.13 | Part 1 - General, 3.7 D. Final Air Clearance Procedures | Conflict between 3.7 C and 3.7 D (PCM vs. TEM clearance) | This section contradicts the previous section 3.7 C requiring PCM or TEM finals based on quantities to be removed. As written - "Contractor's Release Criteria: Work in a regulated area is complete when the regulated area is visually clean and airborne fiber levels have been reduced to or below 0.01 f/cc as measured by the AHERA PCM protocol, and < 70 AHERA asbestos structures per square millimeter (s/mm2) by AHERA TEM." Please provide clarification or direction. | The PCM clearances will be implemented for the clearances. The section provides clearance criteria in case of PCM and TEM clearances. | HS | 11/12/26 | Issued / Closed | |||
| ACM-07 | Asbestos Abatement | 02 82 13.13 | Part 1 - General, 1.5 Applicable Codes and Regulations | Pre-construction meeting: decon set-up above basement | Pre-Construction Meeting: M.g.3). States "If required, decontamination area set-up/layout and decontamination procedures for employees." Please confirm whether or not decontamination set-up areas as identify in Part 1 - General 1.9 Decontamination Facilities will be required for work above the basement floors. | Yes, Decontamination areas will be required on the floors above basement if the quantity of removal exceeds the OSHA reuirement for remaoval quantities for decontamination facilities. | HS | 11/12/26 | Issued / Closed | |||
| ACM-08 | ICRA / Infection Control | Appendix: VHA ICRA-1.2 Instructions | Page 8 - Infection Prevention and Control Construction/Renovation/Maintenance Permit | ICRA Level IV vs. Level III (Table 5) | Form is already marked Level IV. Are we to assume ALL work on this project will be at level IV? We believe it should level III from Table 5. Please provide clarification or direction. | Refer to sheets 1-AE101 through 23-AE104 for Risk Groups and Class of Precautions. | Issued / Closed | |||||
| ACM-09 | ICRA / Infection Control | Appendix: VHA ICRA-1.2 Instructions | Appendix A: Alternative To Outdoor Exhaust Requirements | Porta-count monitoring responsibility (VPIH/CIH) | Requirements call for porta count monitoring (particulate measurements) after initial monitoring to be 3 times (every 8 hours) in a 24 hr. shift. Will the VPIH/CIH be responsible for this initial and regular testing? | PArticulate mesaurements are not performed during asbestos abatement activities.Particulate monitoring is not required. | Issued / Closed | |||||
| ACM-10 | ICRA / Infection Control | Appendix: VHA ICRA-1.2 Instructions | Appendix A: Alternative To Outdoor Exhaust Requirements | Allow 'Double Scrubbing' where no exterior access | We are currently using a "Double Scrubbing" techniques at other hospital and medical facilities where access to the outside is not available. Would this be allowed on this project? | This is acceptable for areas where access to outside is not available. | Issued / Closed | |||||
| AAC-01 | Drawings | Dwg GI001 / Sheet P-505 | Plumbing Riser Replacement Matrices, Floors 9-10 | Missing sheet P-505; confirm complete drawing set | Drawing GI001 lists Sheet P-505, 'Plumbing Riser Replacement Matrices - Floors 9-10,' but this sheet does not appear in the revised drawing PDF. Please provide Sheet P-505 and confirm the complete drawing set for bidding. | P-505 is included in set. A full complete set will be re-issued. | Issued / Closed | |||||
| AAC-02 | Drawings | Sheet GI100 / GC201 | Temporary construction barriers | Missing sheet GC201 (temporary barriers) | Sheet GI100 references Sheet GC201 for temporary construction barriers, but GC201 is not included in the drawing package. Please provide the referenced sheet or confirm whether GI002/GI003 supersede that reference. | Construction barriers have been added to GI100. Refer to revisions dated 11/20/2026. | Issued / Closed | |||||
| AAC-03 | Scope / Alternates | Spec 01 00 00, 1.3.B | Alternate No. 1 (OR addition, Project 558-323) | Alternate No. 1 scope limits (rooms, risers, tie-ins) | Specification Section 01 00 00, Paragraph 1.3.B, identifies Alternate No. 1 as deleting piping replacement in the recently constructed operating-room addition (Project 558-323). Please identify the exact rooms, risers, branch piping, and tie-in limits included in this alternate on the drawings. | Alternate No.1 will be removed from specification. Refer to revised specifcations dated 11/20/2026. | Issued / Closed | |||||
| AAC-04 | Scope / Alternates | Solicitation / SF 1442 | Bid instructions - Alternate No. 1 | Alternate No. 1 pricing and bid schedule | Please clarify how Alternate No. 1 is to be priced and submitted. The solicitation's bid instructions do not clearly identify separate base-bid and alternate pricing lines. Is Alternate No. 1 a deductive alternate, and will a revised bid schedule or SF 1442 continuation sheet be issued? | Alternate No.1 will be removed from specification. Refer to revised specifcations dated 11/20/2026. | Issued / Closed | |||||
| AAC-05 | Scope / Alternates | Statement of Work | 'Priority 1' piping replacement | Confirm all piping is base bid except Alt. 1 | The Statement of Work calls the piping replacement 'Priority 1.' Please confirm whether all piping replacement depicted on the drawings is included in the base bid, except as specifically identified in Alternate No. 1, or identify any deferred or excluded 'Priority' scope. | Alternate No.1 will be removed from specification. Refer to revised specifcations dated 11/20/2026. | Issued / Closed | |||||
| AAC-06 | Phasing / Outages | Spec 01 00 00, 1.6.M; Dwg GI003 | Utility interruption notice | 20 vs. 25 business-day outage notice conflict | Specification Section 01 00 00, Paragraph 1.6.M, requires a written request at least 20 business days before utility interruptions, while Drawing GI003 requires 25 business days before shutdown approval. Which notice period governs, and does the same period apply to requests for temporarily vacating rooms? | 25 days. Specifications 01 00 00 will be re-issued to conform with 25 days. Refer to specifications dated 11/20/2026. | Issued / Closed | |||||
| AAC-07 | Phasing / Outages | Spec 01 00 00; Dwg GI003 | Shutdown durations by system | Max shutdown durations and outage windows | Please provide the maximum anticipated allowable shutdown duration and permitted outage windows for domestic cold water, domestic hot water/recirculation, chilled water, steam, and condensate systems. Are multiple overnight or weekend outages permitted for the same riser or service? | Shutdown duration shall be determined during phasing plans to be submitted by contractor. Shutdown duration will be dependent upon impact to hospital operations. | Issued / Closed | |||||
| AAC-08 | Phasing / Outages | Dwg GI003 | Work-hour restrictions | Night/weekend work hours; daytime work in MER and vacated rooms | Drawing GI003 prohibits work in common areas/corridors from 7:00 AM to 9:00 PM and prohibits shutdowns serving sensitive areas during those hours. Please confirm permitted night and weekend work hours and whether daytime work may occur in mechanical rooms and vacated patient-care rooms. | After hours work would be after 9:00pm in those areas. | Issued / Closed | |||||
| AAC-09 | Phasing / Outages | Dwg GI003 | Seasonal temperature restrictions (CHW >65F / steam <60F) | Temperature limits: cutovers only or all new piping? | Drawing GI003 restricts chilled-water replacement when the forecast temperature exceeds 65 degrees F and steam shutdowns when it is below 60 degrees F. Do these restrictions apply only to service interruptions/cutovers, or also to installation of isolated new piping? Please identify anticipated seasonal outage windows for schedule planning. | applies only to service interruptions/cutovers | Issued / Closed | |||||
| AAC-10 | Phasing / Outages | Spec 01 00 00 | Uninterrupted hospital services | Temporary bypass piping / pumps / heating-cooling during outages | Specification Section 01 00 00 requires uninterrupted hospital services while allowing coordinated outages. Please clarify whether temporary bypass piping, temporary pumps, temporary heating/cooling equipment, or temporary domestic-water distribution must be provided during approved outages; if required, provide minimum capacities, durations, and connection points. | Temporary bypass piping, etc. are not required during a scheduled and approved outage. | Issued / Closed | |||||
| AAC-11 | Phasing / Outages | Dwg GI002 / GI003 | Phasing Groups 1-16 | Additional patient-care access restrictions; room vacating | Please identify any areas within Phasing Groups 1-16 that will have additional operating-room, laboratory, pharmacy, isolation, or other patient-care access restrictions beyond those on GI002/GI003. Will the VA make the required rooms temporarily unoccupied in accordance with the approved phasing schedule? | Room names on plan are accurate at time of bid. VA will work with contractor on rooms affected during construction. | Issued / Closed | |||||
| AAC-12 | Site / Logistics | Dwg GI002 / GI003 | VA support | VA removal of equipment/furnishings; VA escorts after hours | Please confirm whether the VA will remove and relocate patient-care equipment, movable furnishings, and stored materials that obstruct planned piping work, and whether dedicated VA escorts or facility personnel will be available for after-hours room access and utility isolations. | VA will move VA equipment and materials, VA personnel will be escorting | Issued / Closed | |||||
| AAC-13 | Site / Logistics | General | Laydown, delivery, debris routes | Laydown, storage, delivery and debris routes; elevator/dock restrictions | Please identify the available contractor laydown and secured material-storage areas, approved delivery and debris-removal routes, and any restrictions on use of service elevators, loading docks, or dumpsters, including during night shifts. This information is needed to price multi-floor material handling. | Lat down would be between buidling 8 and Garage B gravel area. Use of service elevators is allowed. Dumpster location would depnd on area available when project starts. | Issued / Closed | |||||
| AAC-14 | Scope of Work | Dwg GI002 | Exposed piping inspection / sound riser segments | Replace every segment shown vs. retain sound segments; VA-directed omissions | Drawing GI002 requires piping to be exposed for VA inspection before demolition and indicates that apparently sound riser segments may be retained. Should bidders price replacement of every pipe segment shown, regardless of apparent condition? How will VA-directed omissions be documented and valued after award? | Price full replacement | Issued / Closed | |||||
| AAC-15 | Scope of Work | Plumbing plans / P-5XX matrices | Horizontal domestic-water branches | Extent of horizontal branch replacement and reconnection | Please clarify the exact scope of horizontal domestic-water branch replacement and reconnection at each riser shown on the plumbing plans and P-5XX matrices. Are branches to be replaced only to the nearest identified tie-in, or farther toward fixtures where existing conditions require opening additional walls or ceilings? | Replace horizontal piping up to nearest tie in and as shown in the riser replacement details on P-501. | Issued / Closed | |||||
| AAC-16 | Scope of Work | General | Existing isolation valves | Failed existing isolation valves; new upstream isolation | Are all existing isolation valves needed for the planned phases known to be operational? If an existing valve not identified for replacement fails to isolate the system, should bidders include its replacement or a new upstream isolation point in the base bid? | Existing valves have not been tested by the AE. If existing valves fail, the contractor is to notify the VA COR. | Issued / Closed | |||||
| AAC-17 | Mechanical - CHW | Sheet 1-MP101 | 8-inch CHW supply/return outside Bldg 1 | Exterior CHW piping limits, tie-ins, excavation, restoration | Sheet 1-MP101 depicts new 8-inch chilled-water supply and return piping extending from approximately 5 feet outside Building 1 to the existing riser. Please provide the exterior piping limits, tie-in locations, elevations/depths, known underground conflicts, excavation requirements, and pavement/landscape restoration details for pricing. | Piping should be replaced from 5 feet outside the building to the riser as shown. Exact elevation is unknown, excavation extents is as needed to perform piping replacement. The any new landscaping and paving shall match existing. | Issued / Closed | |||||
| AAC-18 | Mechanical - CHW | Sheet 1-MP102 | 8-inch incoming CHW / 6-inch emergency CHW | Emergency CHW operation during cutovers | Sheet 1-MP102 calls for replacement of incoming 8-inch chilled-water piping, including existing 6-inch emergency chilled-water supply and return lines. Must the emergency lines remain operational throughout each cutover, and what sequence or temporary connection is required to preserve chilled-water redundancy? | The emergency lines do not need to remain operational during cutovers. A temporary bypass shall be installed to maintain chilled water to the building, coordinate exact tie in location with the VA. | Issued / Closed | |||||
| AAC-19 | Mechanical - Steam | Sheet 1-MP108 | Steam PRV station | Steam PRV design loads, pressures, sizing criteria | Sheet 1-MP108 requires field verification of existing steam pressure-reducing station capacity. Please provide design steam loads (lb/hr), inlet/outlet pressures, and applicable sizing criteria for each new or relocated PRV station so subcontractors can establish a common equipment bid basis. | AE was unable to confirm capacities of existing PRV stations, contractor shall coordinate approximate capacities with the VA. | Needs VA Input | |||||
| AAC-20 | Mechanical - Steam | Sheet M-402 | Armstrong HAFT-2448 flash tank | Flash tank design capacity and bid basis | Sheet M-402 specifies a new Armstrong HAFT-2448 flash tank but directs the contractor to confirm capacity in the field. Please provide the required design capacity, operating conditions, and a definitive bid basis if an alternate tank size is ultimately needed. | Photos of flash tank provided. Flash tank is completely insultaed and size could not be verified. Contractor shall coordinate approximate capacity with the VA. | Needs VA Input | |||||
| AAC-21 | Electrical | Sheet M-801 / Electrical plans | Duplex condensate-return units | Existing feeders/disconnects/capacity for new units | Sheet M-801 schedules replacement duplex condensate-return units, while the electrical plans show reuse of existing feeders and circuits. Please confirm that the existing feeders, disconnects, available capacity, and control power are suitable for the scheduled units; identify any new feeders or panel modifications that must be included in the base bid. | Existing feeders shall be reused and extended/modified as required. New disconnects shall be provided for each new condensate return unit with specifications listed on sheet E-001. Existing feeder and control power circuits shall be re-used for new condensate-return units. | Issued / Closed | |||||
| AAC-22 | Controls | Spec 23 09 23 (not furnished) | BAS / controls integration | Controls scope, BAS platform, point list, vendor | Please define the full controls scope for new pumps, valves, steam equipment, sensors, and associated alarms. Is integration with the existing VA building-automation system required, and if so, what is the existing controls platform, required point list, and approved vendor/interface? Specification Section 23 09 23 is referenced but was not furnished. | Controls scope consists of maintaining all existing BAS control points including alarms and monitors. – “The direct-digital control system(s) shall be Siemens PXCM family of controllers operating on a P2 network with option to revise via a software upgrade to BACnet” Refer to 23 09 23 | Needs VA Input | |||||
| AAC-23 | Specifications | Spec 23 05 93; Spec 07 84 00 | TAB and Firestopping | Missing spec sections (TAB, Firestopping) | The specifications reference Sections 23 05 93 (Testing, Adjusting, and Balancing) and 07 84 00 (Firestopping), neither of which appears in the supplied project specifications. Please provide the applicable sections or confirm the intended testing/balancing and firestopping requirements. | Refer to revised specifications dated 11/20/2026. | Issued / Closed | |||||
| AAC-24 | Testing / Commissioning | Dwg GI002; Spec 01 00 00 | Third-party testing | Third-party vs. VA testing-lab responsibility and cost | Drawing GI002 states that all required tests and studies will be performed by a third-party engineering firm at contractor expense, while Section 01 00 00 refers to testing-laboratory services retained by the VA. Please clarify which pressure tests, material tests, inspections, and independent certifications must be subcontracted and paid for by the contractor. | Specification 01 00 00 will be amended. All tests and studies shall be at contractors expense. Refer to revised specifications dated 11/20/2026. | Issued / Closed | |||||
| AAC-25 | Testing / Commissioning | General | Acceptance testing per phase | Required tests, disinfection, commissioning, witnessing | Please confirm the required chilled-water flow testing/balancing, steam/condensate functional testing, domestic-water disinfection and sampling, and commissioning activities for each completed phase. Which acceptance tests require VA or commissioning-agent witnessing before each system may be returned to service? | Refer to specifications for requirements. Any new valve, sensor or device added as part of the project shall be commissioned and tested prior to return of service. VA to be notified of all test prior to performance of tests, including balancing valves. | Issued / Closed | |||||
| AAC-26 | Hazmat | Appendix A - Asbestos Report (pp. 2 & 5) | Basement ACM pipe fittings | 45 vs. 455 ACM fittings discrepancy; base-bid quantities | Appendix A's asbestos report lists 45 basement asbestos-containing pipe fittings in the survey results (report page 2) but 455 basement fittings in its conclusions (report page 5). Which quantity is correct, and what quantities of asbestos-containing pipe insulation and fittings should be carried in the base bid? | Page 2, 45 fittings are the correct quantity for the basement fittings | HS | 11/13/26 | Issued / Closed | |||
| AAC-27 | Hazmat | Appendix A - Asbestos Report | Inaccessible chases / 9th-floor plaster ceiling | Unsurveyed areas; supplemental survey; unforeseen ACM | The asbestos report identifies inaccessible vertical pipe chases, stairwell chases, and areas above the ninth-floor plaster ceiling that were not surveyed or quantified. Will the VA provide supplemental surveys and quantities before bidding? If additional ACM is found during selective demolition, how will testing, abatement, and resulting delay be addressed? | Refer to 52.236-9 for information on existing conditions. | HS | 11/13/26 | Issued / Closed | |||
| AAC-28 | Hazmat | Appendix A | Lead-containing painted surfaces, Bldg 1 | Lead paint quantities/locations and abatement scope | Appendix A identifies lead-containing painted wall surfaces in Building 1. Please identify the expected quantities and locations of lead-painted material requiring disturbance, and clarify whether a separate lead-abatement scope, third-party clearance testing, and hazardous-waste characterization/disposal are required in the base bid. | The lead containing painted wall surfaces was conducted to provide a picture of presence of lead paint in the Building. If there is no lead -paint abatement is being conducted, then separate lead-abatement scope, third-party clearance testing, and hazardous-waste characterization/disposal are not required. | HS | 11/13/26 | Issued / Closed | |||
| AAC-29 | ICRA / Infection Control | Dwg GI100 | ICRA/PCRA control levels | ICRA level by phase/room; barriers, negative air, 24-hr | Drawing GI100 establishes ICRA/PCRA control levels, but the level required for each individual work area is not defined. Please identify the anticipated ICRA level by phase/room, including where hard barriers, anterooms, continuous negative-air monitoring, and 24-hour containment are required. | Refer to sheets 1-AE101 through 23-AE104 for Risk Groups and Class of Precautions. | Issued / Closed | |||||
| AAC-30 | ICRA / Infection Control | General | Negative-air exhaust | Exhaust routes/discharge; temporary penetrations | For areas requiring negative-air containment, please identify approved routes and discharge locations for exhausting construction air to the exterior, and clarify whether temporary window, wall, or roof penetrations are permitted and must be restored by the contractor. | Where ventilation to the exterior is not possible, the air must be filtered and discharged to space outside of work with the discharge also filtered. | Issued / Closed | |||||
| AAC-31 | Fire / Life Safety | General | Rated walls, floors, shafts | Life-safety / fire-resistance plan; firestop inspection scope | Please provide a life-safety/fire-resistance plan identifying the ratings of walls, floors, and shafts affected by new pipe penetrations. Clarify the required firestop inspection or certification scope where existing penetrations are enlarged or newly opened. | Wall ratings are called out on sheets 1-AE101 through 23-AE104. | Issued / Closed | |||||
| AAC-32 | Architectural | General | Restoration after riser access | Architectural restoration limits; access panels | Please clarify the architectural restoration limits following riser access, including whether only directly disturbed ceiling/wall/floor areas must be patched or entire continuous finish surfaces must be replaced to achieve an acceptable match. Are permanent access panels required where new valves or devices are concealed? | Directly disturbed areas to be patched and repaired to like new condition. Repaint entire wall area, from corner to corner. Access panels are required at concealed valves or devices. | Issued / Closed | |||||
| RS-001 | Scope / Alternates | Spec 01 00 00 / Project 558-323 | Alternate No. 1 - OR addition | Alt. 1 pricing method (deduct vs. total) and limits of work | The specifications establish a Base Bid and an alternate deleting piping replacement in the recently constructed Operating Room addition, but the solicitation does not provide a separate alternate pricing schedule. |
| Please confirm whether Alternate No. 1 is to be submitted as a deductive amount from the Base Bid or as a separate total bid price. Additionally, please identify the specific piping systems, drawing locations, and limits of work associated with the OR addition under Project 558-323 that are to be excluded under Alternate No. 1. | Refer to previous RFI Responses | Issued / Closed | ||||||||
| RS-002 | Drawings | Dwg GI001, GI100; Sheets P-502 to P-507, GC201 | Sheets not in drawing package | Missing sheets P-502 - P-507 and GC201 | Drawing GI001 identifies sheet P-505, and plumbing demolition notes reference sheets P-502 through P-507. Additionally, drawing GI100 references sheet GC201 for temporary construction barriers. These drawings do not appear to be included in the provided drawing package. Please provide the missing drawings or identify the applicable replacement sheets and confirm the associated scope of work. | Refer to revised drawings issued 11/20/2026. | Issued / Closed | |||
| RS-003 | Asbestos Abatement | Spec 02 82 13.13; Asbestos survey | ACM fitting quantities (602 / 455 / 45) | ACM fitting quantity discrepancy; chase quantities; overrun compensation | Section 02 82 13.13 and the asbestos survey identify approximately 602 asbestos-containing pipe fittings; however, the survey conclusion identifies 455 basement fittings compared with 45 basement fittings in the survey table. Please confirm the correct quantity of asbestos-containing fittings to be included in the Base Bid. Additionally, please establish the bidding quantity for asbestos-containing materials within concealed vertical chases and confirm how quantities exceeding the established bid quantities will be measured and compensated. | Page 2, 45 fittings are the correct quantity for the basement fittings. Refer to additional RFI answers. | HS | 11/13/26 | Issued / Closed | |
| RS-004 | Hazmat | Spec 09 91 00; Spec 02 83 33.13 (not provided); Appendix A | Lead-based paint | Missing LBP spec; LBP locations, quantities and requirements | Section 09 91 00 references Section 02 83 33.13, Lead-Based Paint Removal and Disposal, which is not included in the provided specifications. Appendix A identifies lead-positive painted surfaces within Building 1; however, the limits of lead disturbance associated with the proposed piping replacement are not clearly quantified. Please provide the referenced specification and identify the locations and quantities of lead-based paint removal required under the Base Bid. Additionally, please confirm the required containment, clearance testing, waste characterization, and disposal requirements. | The lead containing painted wall surfaces was conducted to provide a picture of presence of lead paint in the Building. If there is no lead -paint abatement is being conducted, then separate lead-abatement scope, third-party clearance testing, and hazardous-waste characterization/disposal are not required. | HS | 11/13/26 | Issued / Closed | |
| RS-005 | Phasing / Outages | General | Temporary services | Temporary DW/CHW/steam/condensate during 24-hr operation | Given that the facility must remain operational 24 hours per day, please confirm whether temporary domestic water, chilled water, steam, or condensate services are required during piping replacement activities. If temporary services are required, please identify the affected systems, required capacities, maximum permitted interruption durations, and responsibility for providing temporary connections. | Refer to previous RFI Responses | Issued / Closed | |||
| RS-006 | Phasing / Outages | General | Existing isolation valves | Condition of isolation valves; added valves/shutdowns by modification | Please confirm whether existing isolation valves serving the piping replacement areas have been tested and verified to operate properly. If existing valves fail to isolate the intended work areas, please confirm whether additional valve replacements, extended shutdowns, or temporary isolation measures will be addressed through a contract modification. | Existing valves have not been tested by the AE. If existing valves fail, the contractor is to notify the VA COR. | Issued / Closed | |||
| RS-007 | ICRA / Infection Control | Spec 01 35 26 | ICRA classifications | ICRA classes set before bid; post-award containment increases | Section 01 35 26 requires Infection Control Risk Assessments to be coordinated with the VA Safety Manager/Officer and identifies requirements that may change based on construction phasing, location, and facility operations. Please confirm whether the Government will establish the required infection-control classifications for each work area before bidding, or whether bidders are to assume a uniform containment classification throughout the project. Additionally, please confirm how Government-directed increases in containment requirements after award will be addressed. | VA will not provide ICRA requirements for each area. Refer to sheets 1-AE101 through 23-AE104 for Risk Groups and Class of Precautions. | Issued / Closed | |||
| RS-008 | Specifications | Solicitation; Spec 01 45 00 / 01 35 26 | Superintendent / QCM / SSHO | One person as Superintendent, QCM and SSHO | The solicitation permits the Superintendent to also serve as the Quality Control Manager but requires a separate Site Safety and Health Officer (SSHO). |
| Would the Government consider allowing one qualified individual to perform the duties of Superintendent, Quality Control Manager, and SSHO, provided that the individual meets all applicable qualification requirements and can effectively fulfill the responsibilities of all three positions without compromising project safety, quality, or supervision? | SSHo must be seperate form the Superintendant | Issued / Closed | ||||||||
| RS-009 | Site / Logistics | General | PIV badging | Badging requirements, documents, background checks, timeframes | Will the Government provide detailed written requirements for contractor badging? Please clarify the process for obtaining PIV badges, including required documentation, background checks, and estimated processing timeframes. | No PIV will be required for project. | Issued / Closed | |||
| RS-010 | Bid / Contract | Solicitation | Notice to Proceed | NTP timing after award | How soon after award is NTP expected to be issued? | FY 27 | Issued / Closed | |||
| RS-011 | Bid / Contract | Solicitation | Sales tax | Tax-exempt status and exemption certificate | Is this project tax exempt? If the project is sales tax exempt will the government/VA provide a sales tax exemption certificate? | Refer to 52.229-2 and 52.229-3 | Issued / Closed | |||
| RS-012 | Site / Logistics | General | Site security | Responsibility for temporary site security | Please confirm whether the successful contractor is responsible for providing temporary construction site security, including protection of materials, equipment, and contractor laydown areas throughout the project. | Refer to 52.236-9 for information on existing conditions. Contractor is not asked to provide temporary security but is responsible for scope included in contract provisions/clauses. | Issued / Closed | |||
| RS-013 | ICRA / Infection Control | General | ICRA classification | Required ICRA class for each space | What is the required ICRA classification for each space? | Refer to sheets 1-AE101 through 23-AE104 for Risk Groups and Class of Precautions. | Issued / Closed | |||
| RS-014 | ICRA / Infection Control | General | ICRA barriers | Standard ICRA panels/doors vs. anteroom cabinet | Is there a preference for using standard ICRA panels and doors, or should an anteroom cabinet be used instead? | Required measures are determined by Risk Groups and Class of Precautions shown on sheets 1-AE101 through 23-AE104. | Issued / Closed | |||
| RS-015 | Testing / Commissioning | General | Special inspections matrix | Who contracts/pays/witnesses special inspections, testing, Cx | Special Inspections, Testing, and Survey Responsibility Matrix: Please clarify which party(s) are responsible for all required special inspections, testing, and commissioning activities, and the party responsible for contracting and paying, the witness or acceptance authority. | Refer to previous RFI Responses | Issued / Closed | |||
| RS-016 | Specifications | General | Dual-role assignments | Superintendent / QCM / SSHO as same person | Can superintendent & QCM & SSHO be same person? Or any dual-role assignments are permitted under this project ? | Answered in bid documents | Issued / Closed | |||
| RS-017 | Site / Logistics | General | Contractor use areas | Trailer, storage, staging, dumpster, parking, laydown areas | Can the VA please identify the areas that will be made available for the Contractor's use during construction, including locations for: Job trailer(s), Material storage, Equipment staging, Construction dumpsters, Employee parking, Laydown and loading/unloading areas. If these areas have not yet been designated, can the VA please provide the anticipated locations and any restrictions on their use so that we can accurately assess site logistics, material handling requirements, security considerations, and associated project costs? | Lay down and parking would be between building 8 and Garage B gravel area. THis area is also used by other contractors. There is limited areas for job trailiers. | Issued / Closed | |||
| RS-018 | Seismic | Spec 13 05 41 | 1.4 Submittals | Sealed seismic bracing/anchorage drawings by delegated PE | Reference 13 05 41: SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL COMPONENTS 1.4 SUBMITTALS: Submit a complete and coordinated set of bracing and signed and sealed anchorage drawings and calculations for all non-structural elements requiring seismic restraint by the delegated professional structural engineer. Is this necessary ? | Yes, building categorized as Seismic Design Category C. | Issued / Closed | |||
| RS-019 | Seismic | Spec 13 05 41 | 1.3 Quality Control (A) | Delegated PE qualifications (5 yrs, state registration) | Reference 13 05 41: SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL COMPONENTS 1.3 QUALITY CONTROL: A. Shop-Drawing Preparation: Delegated design calculations shall be prepared by a professional structural engineer with a minimum of 5 years’ experience in the design and detailing of seismic force restraints. The professional structural engineer shall be registered in the state where the project is located and submit qualifications with list of projects illustrating compliance with the experience requirement. Is this necessary ? | Yes, building categorized as Seismic Design Category C. | Issued / Closed | |||
| RS-020 | Site / Logistics | General | Elevator use | Elevator(s) available to contractor and restrictions | Can the VA please clarify which elevator(s) within the project building(s) will be made available for Contractor use during construction. Additionally, please identify any restrictions regarding elevator size, weight capacity, hours of availability, material handling limitations, or periods when elevator use may be restricted due to facility operations. This information is necessary to properly evaluate material handling logistics, labor requirements, and associated project costs. | S4 and S5 are the service elevators. No restriction on use. | Issued / Closed | |||
| RS-021 | Specifications | Spec 01 00 00 | 1.17 Photographic Documentation | Third-party service vs. GC photo documentation program | Reference 01 00 00: 1.17 PHOTOGRAPHIC DOCUMENTATION: Can the VA please clarify whether full compliance with all requirements of Section 1.17 is mandatory through the use of a specialized third-party photographic documentation service, or whether the General Contractor may satisfy the specification requirements through its own photographic documentation program, provided all required photographs, reports, cataloging, storage, and submission requirements are met. | That is section 1.21, contractor can take pictures. | Issued / Closed | |||
| RS-022 | Specifications | Not cited (structural steel) | AISC certification | AISC-certified fabricator/erector vs. AISC inspector | Specs require steel fabricator to be AISC Quality Certification participant designated as AISC Certified Plant, Category STD and installer to be AISC Quality Certification Program participant designated as AISC-Certified Erector, Category ACSE. Can a non-AISC fabricator and/or erector get an AISC inspector, as we are told is allowed per AISC, or will the government require the fabricator and/or erector to be themselves certified? | AISC Certification is not required for non-structural components. Welds to comply with AWS D1.1 per 01 45 29.3.4.A. | Issued / Closed | |||
| RS-023 | Architectural | General | Gypsum board ceilings | Gyp board ceiling repair | Please confirm if there are gyp board ceilings that will need repaired? | OR area on 4th floor contains gyp board ceilings | Issued / Closed | |||
| RS-024 | Bid / Contract | General | Sales tax | Tax-exempt certificate | Please confirm if a tax-exempt certificate will be provided for this project? | Refer to previous RFI Responses | Issued / Closed | |||
| RS-025 | Bid / Contract | General | Certified payroll | Is project subject to certified payroll | Is this project subject to certified payroll? | Yes | Issued / Closed | |||
| RS-026 | Phasing / Outages | General | Night work | Phases requiring night work | Does the VA anticipate any phases that will require night work specifically? | Yes | Issued / Closed | |||
| RS-027 | Asbestos Abatement | Spec 02 82 13.13 - 1 | Unknown quantity in vertical chases | Unit price for abatement in vertical chases | The specs (02 82 13.13 - 1) list an 'Unknown quantity of pipe insulation and pipe fittings on fiberglass lines in vertical pipe chase from basement to 10th floor.' Could we submit a unit price for the abatement in these areas? | No | Issued / Closed | |||
| RS-028 | Asbestos Abatement | Spec 02 82 13.13 - 1; Asbestos report | ACM fitting quantities | Glovebag pricing basis vs. report quantities | The quantities listed in 02 82 13.13 - 1 for asbestos removal on pipe fittings do not match the quantities presented in the asbestos report. Is the prime to price glovebag removal based on the amounts listed in 02 82 13.13 - 1? | Yes, the quantities listed in 02 82 13.13 - 1 | HS | 11/13/26 | Issued / Closed | |
| RS-029 | Asbestos Abatement | Spec 02 82 13.13 - 1 | 602 pipe fittings | Is 602 fittings per floor or total | The specs (02 82 13.13 - 1) state 'Approximately 602 each pipe fittings on fiberglass lines on the basement, ground floor, 1st floor, 2nd floor, 3rd floor, 4th floor, 5th floor, eight floor and 10th floor.' Does this mean that each floor has approximately 602 pipe fittings? | Total approximately quantity of pipe fittings is 602 in all floors. | HS | 11/13/26 | Issued / Closed | |
| RS-030 | Specifications | Spec 01 00 00 - 14; Spec 26 05 11 - 6 | Manufacturer training | Equipment requiring on-site factory training | The specs (01 00 00- 14) state: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. The only section that appears to mention this as well is 26 05 11- 6, which is a general section and not specific to the equipment requiring factory training. Please indicate what equipment will require on-site factory training. | Provide training as required per specifications. Review specifications for training requirements. | Issued / Closed | |||
| RS-031 | Site / Logistics | General | Elevator use - both buildings | Elevator availability for equipment and piping | Will there be an elevator available for use in both buildings for equipment and piping? | Yes | Issued / Closed | |||
| RS-032 | Seismic | VA Handbook H18-8 | Seismic design requirements | Copy of H18-8 Seismic Design Requirements | Could you provide a copy of the VA Handbook H18-8 Seismic Design Requirements? | VA Handbook H18-8 Seismic Design Requirements is available on the VA TIL: https://www.cfm.va.gov/til/ | Issued / Closed | |||
| RS-033 | Phasing / Outages | General | Open chases | Number of chases open at the same time | How many chases can be open at the same time? | Number of chases allowed to be open simultaneously will be determined on the phasing plans dependent on impact on hospital operations. | Issued / Closed | |||
| RS-034 | Site / Logistics | General | Hospital facilities | Contractor use of hospital facilities | Will contractors be able to use the hospital facilities? | Yes, public bathrooms | Issued / Closed | |||
| RS-035 | Site / Logistics | General | Temporary power | Power for welding machines | Will the hospital provide power for the contractors to plug in welding machines? | No | Issued / Closed | |||
| RS-036 | Seismic | General | Seismic scope | Professional Structural Engineer required | Is a Professional Structural Engineer required for the seismic scope? | Refer to previous RFI Responses | Issued / Closed | |||
| RS-037 | Mechanical - Steam | General | PRV | PRV basis of design (brand/model) | What is the basis of design for the PRV; brand, model, etc.? | BOD is Armstrong GP-2000, refer to specifications for additional informaiton | Issued / Closed | |||
| RS-038 | Mechanical - Steam | Dwg MD-102 (note 1) | Hazardous mixing tank | Combustible venting near tank; hot work safety | Is there anything combustible venting from or around the Hazardous Mixing tailer that would make welding dangerous to the contractor. Reference note 1 on MD-102. | No known combustible materials are known at this time. | Issued / Closed | |||
| RS-039 | Bid / Contract | Solicitation | Bid date | Extension of bid date | Would the VA consider extending the bid date to allow for more time to thoroughly review all plan and specs? | Not at this time | Issued / Closed | |||
| RS-040 | Scope / Alternates | Project 558-323 | OR addition piping | Detail of piping scope in recently constructed OR addition | Could you be more specific about what the 'scope for piping replacement in recently constructed OR addition building, part of project 558-323' consists of? | This is listed in the 01 00 00 General requirements paragraph 1.3 statement of bid items | Issued / Closed | |||
| RS-041 | Site / Logistics | General | Mechanical rooms | Additional site visit to verify pipe locations and sizes | Can we please make another site visit to verify pipe locations and sizes in the mechanical rooms? | Not at this time | Issued / Closed | |||
| RS-042 | Site / Logistics | Spec 01 74 19 | Waste/material movement | Dedicated elevator for waste, material, equipment | Reference: Spec 01 74 19. Will the VA will assign one elevator to take waste, material, and equipment up and down to the upper floor? | Service elevatros S4 and S5, waste material must be transported correctly by ICRA standards. | Issued / Closed | |||
| RS-043 | Site / Logistics | General | Dumpster/trailer parking | Parking for dumpster and trailer near loading dock | Are we going to have parking spots available for dumpster and trailer close to the loading dock for abatement and trash? | No | Issued / Closed | |||
| RS-044 | Site / Logistics | Spec 22 05 11 | Crawlspace | Photos of crawlspace work area and clearances | Reference: Spec 22 05 11. Can pictures be provided of the crawlspace to show area of work, clearances, etc.? Access to these areas was not allowed during the site visit. | Basement photos provided. Crawlspace is a confined space and photos were not able to be obtained. | Needs VA Input | |||
| RS-045 | Phasing / Outages | Spec 01 00 00 | Work hours / staging | Work hours; staging by floor | Reference: Spec 01 00 00. Is work to be performed during normal business hours, afterhours, weekends only? Is there project staging for different floors? | Depends on the location, G1003 notes refer to what areas work can occur and time. | Issued / Closed | |||
| RS-046 | Specifications | Spec 22 05 11 | BAA | BAA (Buy American) requirement for all piping | Reference: Spec 22 05 11. Is all piping required to meet the BAA requirements? | Yes, piping shall comply with BAA | Issued / Closed | |||
| RS-047 | Architectural | Site visit notes | Existing wall finishes | Wall finishes in patient rooms, labs, exam rooms, offices | Reference: Site visit notes. During the site visit, access to patient rooms, Labs, Exam rooms and offices was not allowed. Can you specify the existing wall finishes in these rooms? |
tc={9CDE8B45-F09B-43C9-985D-407AD67AE49D}: [Threaded comment]
Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924
Comment:
RS-047--shouldn't the existing wall finishes been catalogued during investigation? have they changed since?
| Wall finish in these areas is paint. Refer to drawings for requirements of finishes | Issued / Closed | |||||||||
| RS-048 | Mechanical - Steam | Dwg 1-MD101 (note 2) | Steam PRV station demolition | Confined space status; photos | Reference: Drawing 1-MD101 note 2. Drawing 1-MD101 note 2 requires removal of steam pressure reducing station located in a confined space. Is the confined space permitted or not permitted? Can photos be provided for these areas? | Assumed permitted, AE was unable to access these areas during field investigations. Confirm access requirements and any existing documentation with the VA. | Issued / Closed | |||
| RS-049 | Phasing / Outages | Dwg GI003 / GI103 | Phasing groups | Consecutive work on more than 1 phase group | Reference: Drawing GI003 Phasing Groups. Drawing GI103 Phasing Groups / There are 16 phases on multiple floors can more than 1 group be worked on consecutively at a time? This would reduce the number of shutdowns required. | Yes | Issued / Closed | |||
| RS-050 | Site / Logistics | Solicitation | Site visit | Date for site-visit sign-in sheet | Reference: Solicitation. Is there a time and date when the site-visit sign-in sheet will be sent to GC's? | Will be posted with RFIs | Issued / Closed | |||
| RS-051 | Asbestos Abatement | Asbestos Survey Analytical Results 2.1, 4.1 | Building 1 pipe insulation / elbows | Does survey 2.1 quantify all abatement locations | Reference: Specifications Asbestos Survey Analytical Results 2.1, 4.1. Does the asbestos survey 2.1 quantify all abatement locations for Building 1 pipe insulation and elbows to be included in the bid? | The asbestos survey 2.1 quantify visible and accessible pipe insulation and elbows identifeid in the survey. The quantities mentioned in 2.1 and section 02 82 13.13 - 1 of the glovebag specifications are to be bid. | HS | 11/13/26 | Issued / Closed | |
| RS-052 | Asbestos Abatement | Asbestos Survey 2.1 (pp. 424-425); 4.1 (pp. 427-428) | Survey quantity conflict | Which survey governs pricing quantities | Reference: Pages 424 & 425- 2.1 Asbestos Survey Analytical Results. Pages 427 & 428-4.1 of the specs doc.. The quantities on the 2017 asbestos survey 2.1 vary from those on survey 4.1. Which survey are we to use for quantities in pricing? | The asbestos survey 2.1 quantify visible and accessible pipe insulation and elbows identifeid in the survey. The quantities mentioned in 2.1 and section 02 82 13.13 - 1 of the glovebag specifications are to be bid. | HS | 11/13/26 | Issued / Closed | |
| RS-053 | Architectural | Dwg 1-PD102, 1-PD103 | Risers in exterior walls | Exterior wall section and penetration details | Reference: Drawing 1-PD102, 1-PD103. Drawing 1-PD102 Shows risers located in exterior walls. Can the VA provide the applicable exterior wall section details, including wall construction and required penetration details, for these riser locations? | Piping is going through furred wall sections at exterior wall locations. | Issued / Closed | |||
| RS-054 | Asbestos Abatement | Spec 02 82 13.13 | Work hours | Hours allowed for wall demo to access ACM risers | Reference: Spec 02 82 13.13. What are the work hrs. allowed for the Demolition of walls to access riser piping with asbestos? | Minimize noise using every action possible. Perform noise-producing work in less sensitive hours of the day or week as directed by the COR. Maintain noise-produced work at or below the decibel levels and within the time periods specified. | HS | 11/13/26 | Issued / Closed | |
| RS-055 | Asbestos Abatement | Spec 02 82 13.13 | Work hours | Hours allowed for glovebagging ACM TSI | Reference: Spec 02 82 13.13. What are the work hrs. allowed for the glovebagging of Asbestos TSI on pipe in walls and other areas? Above hallway ceilings? | Minimize noise using every action possible. Perform noise-producing work in less sensitive hours of the day or week as directed by the COR. Maintain noise-produced work at or below the decibel levels and within the time periods specified. | HS | 11/13/26 | Issued / Closed |
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .