Durham_VAMC_Combined_RFI_Log_11202206 posted.xlsx

XLSX spreadsheet 53 KB Posted

Attached to
Z2DA--FY27 NRM 558-24-160, Domestic Water, Chilled Water and Steam Piping (VA-26-00066009)
Solicitation number
36C24626B0041_1
Issued by

About this file

This is a combined Pre-Bid Request for Information (RFI) Log for the Durham VA Medical Center piping replacement project (Solicitation 36C24626B0041, Project 558-24-160). The log documents 139 total RFIs submitted by bidders and design team responses addressing clarifications needed for the domestic water, chilled water, and steam piping replacement work at the Durham VA Health Care System, 508 Fulton Street, Durham, North Carolina. The project scope includes replacing aging piping in Buildings 1 and 23 with a 603-calendar-day completion period from Notice to Proceed and encompasses asbestos abatement, infection control measures, temporary construction barriers, phasing coordination, and utility interruption management to minimize disruption to the 24-hour operating healthcare facility.

Key RFI topics include asbestos abatement procedures (glove bag method applicability, testing requirements for disturbed elements, decontamination facility locations and configuration), Infection Control Risk Assessment (ICRA) level requirements, missing or incomplete drawing sheets (P-505, GC201), scope clarification regarding Alternate No. 1 (operating room addition deletion that was subsequently removed from specifications per design team response), utility shutdown notice periods (revised to 25 business days), work-hour restrictions (after 9:00 PM for night/weekend work in common areas), and seasonal temperature constraints for chilled water and steam systems. The design team responses, dated November 12, 2026, with specification revisions dated November 20, 2026, address contractor concerns regarding feasibility, space constraints, and regulatory compliance, with most RFIs marked as issued and closed. The VA is the federal agency contracting entity through the Veterans Health Administration, Veterans Integrated Service Network 6.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI Log

Durham VA Medical Center - Project 558-24-160 (Domestic Water, Chilled Water and Steam Piping) - Solicitation 36C24626B0041
Combined Pre-Bid RFI Log:
Total RFIs:139
RFI No.CategorySpec Section / DrawingSub-Section / ReferenceSubject (summary)RFI Question (as submitted)Design Team ResponseResponded ByDate RespondedStatusReviewer Comments / QCAddendum / Spec Revision Required?Notes / Coordination (other disciplines, VA input)
ACM-01Asbestos Abatement02 82 13.13Part 1 - General, 1.1 Summary of Work (B.1)Glove bag method / 'asbestos contaminated elements'Extent of Work. Document call for the use of the "Glove bag Method" for asbestos contaminated elements. Glove bags cannot be used for contaminated elements, only on pipe insulation/fittings. Please provide clarification on "asbestos contaminated elements'.A Traditional Abatement Specifications can be provided for the contaminated elements. Refer to revised specifications dated 11/20/2026.HS11/12/26Issued / Closed
ACM-02Asbestos Abatement02 82 13.13Part 1 - General, 1.1 Summary of Work (B.1)Asbestos test results for all items to be disturbedMost of the identified work areas will require removing structural elements (drywall/ceiling tiles/plaster, etc.) to gain access to the pipe/fitting insulation to be removed. Please provide the asbestos testing results for ALL items to be disturbed for asbestos abatement or construction activities.The survey was only assigned to identify and quantify piping system. A previous survey report of 2017 was provided VA identifying the ACM and that report did not identify any plaster or drywall as ACM. The 2017 asbestos survey report can be provided.HS11/12/26Issued / Closed
ACM-03Asbestos Abatement02 82 13.13Part 1 - General, 1.1 Summary of Work (B.1)Vertical pipe chases, basement to 10th floor (bullet #3)Bullet #3 indicates unknown quantity of pipe and fitting insulation on fiberglass lines in vertical pipe chases from the basement to the 10th floor. Are these vertical pipe chases different than where the pipe insulation and fitting insulation listed in bullets 1 & 2 are located? If so, please identify these additional areas.The pipe insulation behind the walls in the vertical pipe chases needs to be disturbed only if those pipe chases are demolished to access it. The pipe chases were marked on the Plumbing drawings. If the pipes are not scheduled to be disturbed, those are not required to be abated.HS11/12/26Issued / Closed
ACM-04Asbestos Abatement02 82 13.13Part 1 - General, 1.9 Decontamination FacilitiesDecon facility space above basement floorsSpec section calls for both a separate personnel decontamination facility and a waste/equipment decontamination facility. Location of the insulation to be removed at most areas above the basement floors do not allow enough space with out blocking other entrances and path of travels. Please provide clarification or direction.The same decontamination facility can be utilized if there are space constraints.HS11/12/26Issued / Closed
ACM-05Asbestos Abatement02 82 13.13Part 1 - General, 1.9 Decontamination FacilitiesDecon clean room access from building exteriorSpec section calls for personnel decontamination facility that "the clean room shall be located so as to provide access to the holding room from the building exterior." In addition, Spec section calls for waste/equipment decontamination facility that "the clean room shall be located so as to provide access to the holding room from the building exterior." Both these two requirements are not achievable on this project. Please provide clarification or direction.The access for holding room is for the location where the waste maybe stored prior to disposal in the floor with direct access to building exterior. The rest of the floor locations this requirement is not feasible to implement.HS11/12/26Issued / Closed
ACM-06Asbestos Abatement02 82 13.13Part 1 - General, 3.7 D. Final Air Clearance ProceduresConflict between 3.7 C and 3.7 D (PCM vs. TEM clearance)This section contradicts the previous section 3.7 C requiring PCM or TEM finals based on quantities to be removed. As written - "Contractor's Release Criteria: Work in a regulated area is complete when the regulated area is visually clean and airborne fiber levels have been reduced to or below 0.01 f/cc as measured by the AHERA PCM protocol, and < 70 AHERA asbestos structures per square millimeter (s/mm2) by AHERA TEM." Please provide clarification or direction.The PCM clearances will be implemented for the clearances. The section provides clearance criteria in case of PCM and TEM clearances.HS11/12/26Issued / Closed
ACM-07Asbestos Abatement02 82 13.13Part 1 - General, 1.5 Applicable Codes and RegulationsPre-construction meeting: decon set-up above basementPre-Construction Meeting: M.g.3). States "If required, decontamination area set-up/layout and decontamination procedures for employees." Please confirm whether or not decontamination set-up areas as identify in Part 1 - General 1.9 Decontamination Facilities will be required for work above the basement floors.Yes, Decontamination areas will be required on the floors above basement if the quantity of removal exceeds the OSHA reuirement for remaoval quantities for decontamination facilities.HS11/12/26Issued / Closed
ACM-08ICRA / Infection ControlAppendix: VHA ICRA-1.2 InstructionsPage 8 - Infection Prevention and Control Construction/Renovation/Maintenance PermitICRA Level IV vs. Level III (Table 5)Form is already marked Level IV. Are we to assume ALL work on this project will be at level IV? We believe it should level III from Table 5. Please provide clarification or direction.Refer to sheets 1-AE101 through 23-AE104 for Risk Groups and Class of Precautions.Issued / Closed
ACM-09ICRA / Infection ControlAppendix: VHA ICRA-1.2 InstructionsAppendix A: Alternative To Outdoor Exhaust RequirementsPorta-count monitoring responsibility (VPIH/CIH)Requirements call for porta count monitoring (particulate measurements) after initial monitoring to be 3 times (every 8 hours) in a 24 hr. shift. Will the VPIH/CIH be responsible for this initial and regular testing?PArticulate mesaurements are not performed during asbestos abatement activities.Particulate monitoring is not required.Issued / Closed
ACM-10ICRA / Infection ControlAppendix: VHA ICRA-1.2 InstructionsAppendix A: Alternative To Outdoor Exhaust RequirementsAllow 'Double Scrubbing' where no exterior accessWe are currently using a "Double Scrubbing" techniques at other hospital and medical facilities where access to the outside is not available. Would this be allowed on this project?This is acceptable for areas where access to outside is not available.Issued / Closed
AAC-01DrawingsDwg GI001 / Sheet P-505Plumbing Riser Replacement Matrices, Floors 9-10Missing sheet P-505; confirm complete drawing setDrawing GI001 lists Sheet P-505, 'Plumbing Riser Replacement Matrices - Floors 9-10,' but this sheet does not appear in the revised drawing PDF. Please provide Sheet P-505 and confirm the complete drawing set for bidding.P-505 is included in set. A full complete set will be re-issued.Issued / Closed
AAC-02DrawingsSheet GI100 / GC201Temporary construction barriersMissing sheet GC201 (temporary barriers)Sheet GI100 references Sheet GC201 for temporary construction barriers, but GC201 is not included in the drawing package. Please provide the referenced sheet or confirm whether GI002/GI003 supersede that reference.Construction barriers have been added to GI100. Refer to revisions dated 11/20/2026.Issued / Closed
AAC-03Scope / AlternatesSpec 01 00 00, 1.3.BAlternate No. 1 (OR addition, Project 558-323)Alternate No. 1 scope limits (rooms, risers, tie-ins)Specification Section 01 00 00, Paragraph 1.3.B, identifies Alternate No. 1 as deleting piping replacement in the recently constructed operating-room addition (Project 558-323). Please identify the exact rooms, risers, branch piping, and tie-in limits included in this alternate on the drawings.Alternate No.1 will be removed from specification. Refer to revised specifcations dated 11/20/2026.Issued / Closed
AAC-04Scope / AlternatesSolicitation / SF 1442Bid instructions - Alternate No. 1Alternate No. 1 pricing and bid schedulePlease clarify how Alternate No. 1 is to be priced and submitted. The solicitation's bid instructions do not clearly identify separate base-bid and alternate pricing lines. Is Alternate No. 1 a deductive alternate, and will a revised bid schedule or SF 1442 continuation sheet be issued?Alternate No.1 will be removed from specification. Refer to revised specifcations dated 11/20/2026.Issued / Closed
AAC-05Scope / AlternatesStatement of Work'Priority 1' piping replacementConfirm all piping is base bid except Alt. 1The Statement of Work calls the piping replacement 'Priority 1.' Please confirm whether all piping replacement depicted on the drawings is included in the base bid, except as specifically identified in Alternate No. 1, or identify any deferred or excluded 'Priority' scope.Alternate No.1 will be removed from specification. Refer to revised specifcations dated 11/20/2026.Issued / Closed
AAC-06Phasing / OutagesSpec 01 00 00, 1.6.M; Dwg GI003Utility interruption notice20 vs. 25 business-day outage notice conflictSpecification Section 01 00 00, Paragraph 1.6.M, requires a written request at least 20 business days before utility interruptions, while Drawing GI003 requires 25 business days before shutdown approval. Which notice period governs, and does the same period apply to requests for temporarily vacating rooms?25 days. Specifications 01 00 00 will be re-issued to conform with 25 days. Refer to specifications dated 11/20/2026.Issued / Closed
AAC-07Phasing / OutagesSpec 01 00 00; Dwg GI003Shutdown durations by systemMax shutdown durations and outage windowsPlease provide the maximum anticipated allowable shutdown duration and permitted outage windows for domestic cold water, domestic hot water/recirculation, chilled water, steam, and condensate systems. Are multiple overnight or weekend outages permitted for the same riser or service?Shutdown duration shall be determined during phasing plans to be submitted by contractor. Shutdown duration will be dependent upon impact to hospital operations.Issued / Closed
AAC-08Phasing / OutagesDwg GI003Work-hour restrictionsNight/weekend work hours; daytime work in MER and vacated roomsDrawing GI003 prohibits work in common areas/corridors from 7:00 AM to 9:00 PM and prohibits shutdowns serving sensitive areas during those hours. Please confirm permitted night and weekend work hours and whether daytime work may occur in mechanical rooms and vacated patient-care rooms.After hours work would be after 9:00pm in those areas.Issued / Closed
AAC-09Phasing / OutagesDwg GI003Seasonal temperature restrictions (CHW >65F / steam <60F)Temperature limits: cutovers only or all new piping?Drawing GI003 restricts chilled-water replacement when the forecast temperature exceeds 65 degrees F and steam shutdowns when it is below 60 degrees F. Do these restrictions apply only to service interruptions/cutovers, or also to installation of isolated new piping? Please identify anticipated seasonal outage windows for schedule planning.applies only to service interruptions/cutoversIssued / Closed
AAC-10Phasing / OutagesSpec 01 00 00Uninterrupted hospital servicesTemporary bypass piping / pumps / heating-cooling during outagesSpecification Section 01 00 00 requires uninterrupted hospital services while allowing coordinated outages. Please clarify whether temporary bypass piping, temporary pumps, temporary heating/cooling equipment, or temporary domestic-water distribution must be provided during approved outages; if required, provide minimum capacities, durations, and connection points.Temporary bypass piping, etc. are not required during a scheduled and approved outage.Issued / Closed
AAC-11Phasing / OutagesDwg GI002 / GI003Phasing Groups 1-16Additional patient-care access restrictions; room vacatingPlease identify any areas within Phasing Groups 1-16 that will have additional operating-room, laboratory, pharmacy, isolation, or other patient-care access restrictions beyond those on GI002/GI003. Will the VA make the required rooms temporarily unoccupied in accordance with the approved phasing schedule?Room names on plan are accurate at time of bid. VA will work with contractor on rooms affected during construction.Issued / Closed
AAC-12Site / LogisticsDwg GI002 / GI003VA supportVA removal of equipment/furnishings; VA escorts after hoursPlease confirm whether the VA will remove and relocate patient-care equipment, movable furnishings, and stored materials that obstruct planned piping work, and whether dedicated VA escorts or facility personnel will be available for after-hours room access and utility isolations.VA will move VA equipment and materials, VA personnel will be escortingIssued / Closed
AAC-13Site / LogisticsGeneralLaydown, delivery, debris routesLaydown, storage, delivery and debris routes; elevator/dock restrictionsPlease identify the available contractor laydown and secured material-storage areas, approved delivery and debris-removal routes, and any restrictions on use of service elevators, loading docks, or dumpsters, including during night shifts. This information is needed to price multi-floor material handling.Lat down would be between buidling 8 and Garage B gravel area. Use of service elevators is allowed. Dumpster location would depnd on area available when project starts.Issued / Closed
AAC-14Scope of WorkDwg GI002Exposed piping inspection / sound riser segmentsReplace every segment shown vs. retain sound segments; VA-directed omissionsDrawing GI002 requires piping to be exposed for VA inspection before demolition and indicates that apparently sound riser segments may be retained. Should bidders price replacement of every pipe segment shown, regardless of apparent condition? How will VA-directed omissions be documented and valued after award?Price full replacementIssued / Closed
AAC-15Scope of WorkPlumbing plans / P-5XX matricesHorizontal domestic-water branchesExtent of horizontal branch replacement and reconnectionPlease clarify the exact scope of horizontal domestic-water branch replacement and reconnection at each riser shown on the plumbing plans and P-5XX matrices. Are branches to be replaced only to the nearest identified tie-in, or farther toward fixtures where existing conditions require opening additional walls or ceilings?Replace horizontal piping up to nearest tie in and as shown in the riser replacement details on P-501.Issued / Closed
AAC-16Scope of WorkGeneralExisting isolation valvesFailed existing isolation valves; new upstream isolationAre all existing isolation valves needed for the planned phases known to be operational? If an existing valve not identified for replacement fails to isolate the system, should bidders include its replacement or a new upstream isolation point in the base bid?Existing valves have not been tested by the AE. If existing valves fail, the contractor is to notify the VA COR.Issued / Closed
AAC-17Mechanical - CHWSheet 1-MP1018-inch CHW supply/return outside Bldg 1Exterior CHW piping limits, tie-ins, excavation, restorationSheet 1-MP101 depicts new 8-inch chilled-water supply and return piping extending from approximately 5 feet outside Building 1 to the existing riser. Please provide the exterior piping limits, tie-in locations, elevations/depths, known underground conflicts, excavation requirements, and pavement/landscape restoration details for pricing.Piping should be replaced from 5 feet outside the building to the riser as shown. Exact elevation is unknown, excavation extents is as needed to perform piping replacement. The any new landscaping and paving shall match existing.Issued / Closed
AAC-18Mechanical - CHWSheet 1-MP1028-inch incoming CHW / 6-inch emergency CHWEmergency CHW operation during cutoversSheet 1-MP102 calls for replacement of incoming 8-inch chilled-water piping, including existing 6-inch emergency chilled-water supply and return lines. Must the emergency lines remain operational throughout each cutover, and what sequence or temporary connection is required to preserve chilled-water redundancy?The emergency lines do not need to remain operational during cutovers. A temporary bypass shall be installed to maintain chilled water to the building, coordinate exact tie in location with the VA.Issued / Closed
AAC-19Mechanical - SteamSheet 1-MP108Steam PRV stationSteam PRV design loads, pressures, sizing criteriaSheet 1-MP108 requires field verification of existing steam pressure-reducing station capacity. Please provide design steam loads (lb/hr), inlet/outlet pressures, and applicable sizing criteria for each new or relocated PRV station so subcontractors can establish a common equipment bid basis.AE was unable to confirm capacities of existing PRV stations, contractor shall coordinate approximate capacities with the VA.Needs VA Input
AAC-20Mechanical - SteamSheet M-402Armstrong HAFT-2448 flash tankFlash tank design capacity and bid basisSheet M-402 specifies a new Armstrong HAFT-2448 flash tank but directs the contractor to confirm capacity in the field. Please provide the required design capacity, operating conditions, and a definitive bid basis if an alternate tank size is ultimately needed.Photos of flash tank provided. Flash tank is completely insultaed and size could not be verified. Contractor shall coordinate approximate capacity with the VA.Needs VA Input
AAC-21ElectricalSheet M-801 / Electrical plansDuplex condensate-return unitsExisting feeders/disconnects/capacity for new unitsSheet M-801 schedules replacement duplex condensate-return units, while the electrical plans show reuse of existing feeders and circuits. Please confirm that the existing feeders, disconnects, available capacity, and control power are suitable for the scheduled units; identify any new feeders or panel modifications that must be included in the base bid.Existing feeders shall be reused and extended/modified as required. New disconnects shall be provided for each new condensate return unit with specifications listed on sheet E-001. Existing feeder and control power circuits shall be re-used for new condensate-return units.Issued / Closed
AAC-22ControlsSpec 23 09 23 (not furnished)BAS / controls integrationControls scope, BAS platform, point list, vendorPlease define the full controls scope for new pumps, valves, steam equipment, sensors, and associated alarms. Is integration with the existing VA building-automation system required, and if so, what is the existing controls platform, required point list, and approved vendor/interface? Specification Section 23 09 23 is referenced but was not furnished.Controls scope consists of maintaining all existing BAS control points including alarms and monitors. – “The direct-digital control system(s) shall be Siemens PXCM family of controllers operating on a P2 network with option to revise via a software upgrade to BACnet” Refer to 23 09 23Needs VA Input
AAC-23SpecificationsSpec 23 05 93; Spec 07 84 00TAB and FirestoppingMissing spec sections (TAB, Firestopping)The specifications reference Sections 23 05 93 (Testing, Adjusting, and Balancing) and 07 84 00 (Firestopping), neither of which appears in the supplied project specifications. Please provide the applicable sections or confirm the intended testing/balancing and firestopping requirements.Refer to revised specifications dated 11/20/2026.Issued / Closed
AAC-24Testing / CommissioningDwg GI002; Spec 01 00 00Third-party testingThird-party vs. VA testing-lab responsibility and costDrawing GI002 states that all required tests and studies will be performed by a third-party engineering firm at contractor expense, while Section 01 00 00 refers to testing-laboratory services retained by the VA. Please clarify which pressure tests, material tests, inspections, and independent certifications must be subcontracted and paid for by the contractor.Specification 01 00 00 will be amended. All tests and studies shall be at contractors expense. Refer to revised specifications dated 11/20/2026.Issued / Closed
AAC-25Testing / CommissioningGeneralAcceptance testing per phaseRequired tests, disinfection, commissioning, witnessingPlease confirm the required chilled-water flow testing/balancing, steam/condensate functional testing, domestic-water disinfection and sampling, and commissioning activities for each completed phase. Which acceptance tests require VA or commissioning-agent witnessing before each system may be returned to service?Refer to specifications for requirements. Any new valve, sensor or device added as part of the project shall be commissioned and tested prior to return of service. VA to be notified of all test prior to performance of tests, including balancing valves.Issued / Closed
AAC-26HazmatAppendix A - Asbestos Report (pp. 2 & 5)Basement ACM pipe fittings45 vs. 455 ACM fittings discrepancy; base-bid quantitiesAppendix A's asbestos report lists 45 basement asbestos-containing pipe fittings in the survey results (report page 2) but 455 basement fittings in its conclusions (report page 5). Which quantity is correct, and what quantities of asbestos-containing pipe insulation and fittings should be carried in the base bid?Page 2, 45 fittings are the correct quantity for the basement fittingsHS11/13/26Issued / Closed
AAC-27HazmatAppendix A - Asbestos ReportInaccessible chases / 9th-floor plaster ceilingUnsurveyed areas; supplemental survey; unforeseen ACMThe asbestos report identifies inaccessible vertical pipe chases, stairwell chases, and areas above the ninth-floor plaster ceiling that were not surveyed or quantified. Will the VA provide supplemental surveys and quantities before bidding? If additional ACM is found during selective demolition, how will testing, abatement, and resulting delay be addressed?Refer to 52.236-9 for information on existing conditions.HS11/13/26Issued / Closed
AAC-28HazmatAppendix ALead-containing painted surfaces, Bldg 1Lead paint quantities/locations and abatement scopeAppendix A identifies lead-containing painted wall surfaces in Building 1. Please identify the expected quantities and locations of lead-painted material requiring disturbance, and clarify whether a separate lead-abatement scope, third-party clearance testing, and hazardous-waste characterization/disposal are required in the base bid.The lead containing painted wall surfaces was conducted to provide a picture of presence of lead paint in the Building. If there is no lead -paint abatement is being conducted, then separate lead-abatement scope, third-party clearance testing, and hazardous-waste characterization/disposal are not required.HS11/13/26Issued / Closed
AAC-29ICRA / Infection ControlDwg GI100ICRA/PCRA control levelsICRA level by phase/room; barriers, negative air, 24-hrDrawing GI100 establishes ICRA/PCRA control levels, but the level required for each individual work area is not defined. Please identify the anticipated ICRA level by phase/room, including where hard barriers, anterooms, continuous negative-air monitoring, and 24-hour containment are required.Refer to sheets 1-AE101 through 23-AE104 for Risk Groups and Class of Precautions.Issued / Closed
AAC-30ICRA / Infection ControlGeneralNegative-air exhaustExhaust routes/discharge; temporary penetrationsFor areas requiring negative-air containment, please identify approved routes and discharge locations for exhausting construction air to the exterior, and clarify whether temporary window, wall, or roof penetrations are permitted and must be restored by the contractor.Where ventilation to the exterior is not possible, the air must be filtered and discharged to space outside of work with the discharge also filtered.Issued / Closed
AAC-31Fire / Life SafetyGeneralRated walls, floors, shaftsLife-safety / fire-resistance plan; firestop inspection scopePlease provide a life-safety/fire-resistance plan identifying the ratings of walls, floors, and shafts affected by new pipe penetrations. Clarify the required firestop inspection or certification scope where existing penetrations are enlarged or newly opened.Wall ratings are called out on sheets 1-AE101 through 23-AE104.Issued / Closed
AAC-32ArchitecturalGeneralRestoration after riser accessArchitectural restoration limits; access panelsPlease clarify the architectural restoration limits following riser access, including whether only directly disturbed ceiling/wall/floor areas must be patched or entire continuous finish surfaces must be replaced to achieve an acceptable match. Are permanent access panels required where new valves or devices are concealed?Directly disturbed areas to be patched and repaired to like new condition. Repaint entire wall area, from corner to corner. Access panels are required at concealed valves or devices.Issued / Closed
RS-001Scope / AlternatesSpec 01 00 00 / Project 558-323Alternate No. 1 - OR additionAlt. 1 pricing method (deduct vs. total) and limits of workThe specifications establish a Base Bid and an alternate deleting piping replacement in the recently constructed Operating Room addition, but the solicitation does not provide a separate alternate pricing schedule.
Please confirm whether Alternate No. 1 is to be submitted as a deductive amount from the Base Bid or as a separate total bid price. Additionally, please identify the specific piping systems, drawing locations, and limits of work associated with the OR addition under Project 558-323 that are to be excluded under Alternate No. 1.Refer to previous RFI ResponsesIssued / Closed
RS-002DrawingsDwg GI001, GI100; Sheets P-502 to P-507, GC201Sheets not in drawing packageMissing sheets P-502 - P-507 and GC201Drawing GI001 identifies sheet P-505, and plumbing demolition notes reference sheets P-502 through P-507. Additionally, drawing GI100 references sheet GC201 for temporary construction barriers. These drawings do not appear to be included in the provided drawing package. Please provide the missing drawings or identify the applicable replacement sheets and confirm the associated scope of work.Refer to revised drawings issued 11/20/2026.Issued / Closed
RS-003Asbestos AbatementSpec 02 82 13.13; Asbestos surveyACM fitting quantities (602 / 455 / 45)ACM fitting quantity discrepancy; chase quantities; overrun compensationSection 02 82 13.13 and the asbestos survey identify approximately 602 asbestos-containing pipe fittings; however, the survey conclusion identifies 455 basement fittings compared with 45 basement fittings in the survey table. Please confirm the correct quantity of asbestos-containing fittings to be included in the Base Bid. Additionally, please establish the bidding quantity for asbestos-containing materials within concealed vertical chases and confirm how quantities exceeding the established bid quantities will be measured and compensated.Page 2, 45 fittings are the correct quantity for the basement fittings. Refer to additional RFI answers.HS11/13/26Issued / Closed
RS-004HazmatSpec 09 91 00; Spec 02 83 33.13 (not provided); Appendix ALead-based paintMissing LBP spec; LBP locations, quantities and requirementsSection 09 91 00 references Section 02 83 33.13, Lead-Based Paint Removal and Disposal, which is not included in the provided specifications. Appendix A identifies lead-positive painted surfaces within Building 1; however, the limits of lead disturbance associated with the proposed piping replacement are not clearly quantified. Please provide the referenced specification and identify the locations and quantities of lead-based paint removal required under the Base Bid. Additionally, please confirm the required containment, clearance testing, waste characterization, and disposal requirements.The lead containing painted wall surfaces was conducted to provide a picture of presence of lead paint in the Building. If there is no lead -paint abatement is being conducted, then separate lead-abatement scope, third-party clearance testing, and hazardous-waste characterization/disposal are not required.HS11/13/26Issued / Closed
RS-005Phasing / OutagesGeneralTemporary servicesTemporary DW/CHW/steam/condensate during 24-hr operationGiven that the facility must remain operational 24 hours per day, please confirm whether temporary domestic water, chilled water, steam, or condensate services are required during piping replacement activities. If temporary services are required, please identify the affected systems, required capacities, maximum permitted interruption durations, and responsibility for providing temporary connections.Refer to previous RFI ResponsesIssued / Closed
RS-006Phasing / OutagesGeneralExisting isolation valvesCondition of isolation valves; added valves/shutdowns by modificationPlease confirm whether existing isolation valves serving the piping replacement areas have been tested and verified to operate properly. If existing valves fail to isolate the intended work areas, please confirm whether additional valve replacements, extended shutdowns, or temporary isolation measures will be addressed through a contract modification.Existing valves have not been tested by the AE. If existing valves fail, the contractor is to notify the VA COR.Issued / Closed
RS-007ICRA / Infection ControlSpec 01 35 26ICRA classificationsICRA classes set before bid; post-award containment increasesSection 01 35 26 requires Infection Control Risk Assessments to be coordinated with the VA Safety Manager/Officer and identifies requirements that may change based on construction phasing, location, and facility operations. Please confirm whether the Government will establish the required infection-control classifications for each work area before bidding, or whether bidders are to assume a uniform containment classification throughout the project. Additionally, please confirm how Government-directed increases in containment requirements after award will be addressed.VA will not provide ICRA requirements for each area. Refer to sheets 1-AE101 through 23-AE104 for Risk Groups and Class of Precautions.Issued / Closed
RS-008SpecificationsSolicitation; Spec 01 45 00 / 01 35 26Superintendent / QCM / SSHOOne person as Superintendent, QCM and SSHOThe solicitation permits the Superintendent to also serve as the Quality Control Manager but requires a separate Site Safety and Health Officer (SSHO).
Would the Government consider allowing one qualified individual to perform the duties of Superintendent, Quality Control Manager, and SSHO, provided that the individual meets all applicable qualification requirements and can effectively fulfill the responsibilities of all three positions without compromising project safety, quality, or supervision?SSHo must be seperate form the SuperintendantIssued / Closed
RS-009Site / LogisticsGeneralPIV badgingBadging requirements, documents, background checks, timeframesWill the Government provide detailed written requirements for contractor badging? Please clarify the process for obtaining PIV badges, including required documentation, background checks, and estimated processing timeframes.No PIV will be required for project.Issued / Closed
RS-010Bid / ContractSolicitationNotice to ProceedNTP timing after awardHow soon after award is NTP expected to be issued?FY 27Issued / Closed
RS-011Bid / ContractSolicitationSales taxTax-exempt status and exemption certificateIs this project tax exempt? If the project is sales tax exempt will the government/VA provide a sales tax exemption certificate?Refer to 52.229-2 and 52.229-3Issued / Closed
RS-012Site / LogisticsGeneralSite securityResponsibility for temporary site securityPlease confirm whether the successful contractor is responsible for providing temporary construction site security, including protection of materials, equipment, and contractor laydown areas throughout the project.Refer to 52.236-9 for information on existing conditions. Contractor is not asked to provide temporary security but is responsible for scope included in contract provisions/clauses.Issued / Closed
RS-013ICRA / Infection ControlGeneralICRA classificationRequired ICRA class for each spaceWhat is the required ICRA classification for each space?Refer to sheets 1-AE101 through 23-AE104 for Risk Groups and Class of Precautions.Issued / Closed
RS-014ICRA / Infection ControlGeneralICRA barriersStandard ICRA panels/doors vs. anteroom cabinetIs there a preference for using standard ICRA panels and doors, or should an anteroom cabinet be used instead?Required measures are determined by Risk Groups and Class of Precautions shown on sheets 1-AE101 through 23-AE104.Issued / Closed
RS-015Testing / CommissioningGeneralSpecial inspections matrixWho contracts/pays/witnesses special inspections, testing, CxSpecial Inspections, Testing, and Survey Responsibility Matrix: Please clarify which party(s) are responsible for all required special inspections, testing, and commissioning activities, and the party responsible for contracting and paying, the witness or acceptance authority.Refer to previous RFI ResponsesIssued / Closed
RS-016SpecificationsGeneralDual-role assignmentsSuperintendent / QCM / SSHO as same personCan superintendent & QCM & SSHO be same person? Or any dual-role assignments are permitted under this project ?Answered in bid documentsIssued / Closed
RS-017Site / LogisticsGeneralContractor use areasTrailer, storage, staging, dumpster, parking, laydown areasCan the VA please identify the areas that will be made available for the Contractor's use during construction, including locations for: Job trailer(s), Material storage, Equipment staging, Construction dumpsters, Employee parking, Laydown and loading/unloading areas. If these areas have not yet been designated, can the VA please provide the anticipated locations and any restrictions on their use so that we can accurately assess site logistics, material handling requirements, security considerations, and associated project costs?Lay down and parking would be between building 8 and Garage B gravel area. THis area is also used by other contractors. There is limited areas for job trailiers.Issued / Closed
RS-018SeismicSpec 13 05 411.4 SubmittalsSealed seismic bracing/anchorage drawings by delegated PEReference 13 05 41: SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL COMPONENTS 1.4 SUBMITTALS: Submit a complete and coordinated set of bracing and signed and sealed anchorage drawings and calculations for all non-structural elements requiring seismic restraint by the delegated professional structural engineer. Is this necessary ?Yes, building categorized as Seismic Design Category C.Issued / Closed
RS-019SeismicSpec 13 05 411.3 Quality Control (A)Delegated PE qualifications (5 yrs, state registration)Reference 13 05 41: SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL COMPONENTS 1.3 QUALITY CONTROL: A. Shop-Drawing Preparation: Delegated design calculations shall be prepared by a professional structural engineer with a minimum of 5 years’ experience in the design and detailing of seismic force restraints. The professional structural engineer shall be registered in the state where the project is located and submit qualifications with list of projects illustrating compliance with the experience requirement. Is this necessary ?Yes, building categorized as Seismic Design Category C.Issued / Closed
RS-020Site / LogisticsGeneralElevator useElevator(s) available to contractor and restrictionsCan the VA please clarify which elevator(s) within the project building(s) will be made available for Contractor use during construction. Additionally, please identify any restrictions regarding elevator size, weight capacity, hours of availability, material handling limitations, or periods when elevator use may be restricted due to facility operations. This information is necessary to properly evaluate material handling logistics, labor requirements, and associated project costs.S4 and S5 are the service elevators. No restriction on use.Issued / Closed
RS-021SpecificationsSpec 01 00 001.17 Photographic DocumentationThird-party service vs. GC photo documentation programReference 01 00 00: 1.17 PHOTOGRAPHIC DOCUMENTATION: Can the VA please clarify whether full compliance with all requirements of Section 1.17 is mandatory through the use of a specialized third-party photographic documentation service, or whether the General Contractor may satisfy the specification requirements through its own photographic documentation program, provided all required photographs, reports, cataloging, storage, and submission requirements are met.That is section 1.21, contractor can take pictures.Issued / Closed
RS-022SpecificationsNot cited (structural steel)AISC certificationAISC-certified fabricator/erector vs. AISC inspectorSpecs require steel fabricator to be AISC Quality Certification participant designated as AISC Certified Plant, Category STD and installer to be AISC Quality Certification Program participant designated as AISC-Certified Erector, Category ACSE. Can a non-AISC fabricator and/or erector get an AISC inspector, as we are told is allowed per AISC, or will the government require the fabricator and/or erector to be themselves certified?AISC Certification is not required for non-structural components. Welds to comply with AWS D1.1 per 01 45 29.3.4.A.Issued / Closed
RS-023ArchitecturalGeneralGypsum board ceilingsGyp board ceiling repairPlease confirm if there are gyp board ceilings that will need repaired?OR area on 4th floor contains gyp board ceilingsIssued / Closed
RS-024Bid / ContractGeneralSales taxTax-exempt certificatePlease confirm if a tax-exempt certificate will be provided for this project?Refer to previous RFI ResponsesIssued / Closed
RS-025Bid / ContractGeneralCertified payrollIs project subject to certified payrollIs this project subject to certified payroll?YesIssued / Closed
RS-026Phasing / OutagesGeneralNight workPhases requiring night workDoes the VA anticipate any phases that will require night work specifically?YesIssued / Closed
RS-027Asbestos AbatementSpec 02 82 13.13 - 1Unknown quantity in vertical chasesUnit price for abatement in vertical chasesThe specs (02 82 13.13 - 1) list an 'Unknown quantity of pipe insulation and pipe fittings on fiberglass lines in vertical pipe chase from basement to 10th floor.' Could we submit a unit price for the abatement in these areas?NoIssued / Closed
RS-028Asbestos AbatementSpec 02 82 13.13 - 1; Asbestos reportACM fitting quantitiesGlovebag pricing basis vs. report quantitiesThe quantities listed in 02 82 13.13 - 1 for asbestos removal on pipe fittings do not match the quantities presented in the asbestos report. Is the prime to price glovebag removal based on the amounts listed in 02 82 13.13 - 1?Yes, the quantities listed in 02 82 13.13 - 1HS11/13/26Issued / Closed
RS-029Asbestos AbatementSpec 02 82 13.13 - 1602 pipe fittingsIs 602 fittings per floor or totalThe specs (02 82 13.13 - 1) state 'Approximately 602 each pipe fittings on fiberglass lines on the basement, ground floor, 1st floor, 2nd floor, 3rd floor, 4th floor, 5th floor, eight floor and 10th floor.' Does this mean that each floor has approximately 602 pipe fittings?Total approximately quantity of pipe fittings is 602 in all floors.HS11/13/26Issued / Closed
RS-030SpecificationsSpec 01 00 00 - 14; Spec 26 05 11 - 6Manufacturer trainingEquipment requiring on-site factory trainingThe specs (01 00 00- 14) state: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. The only section that appears to mention this as well is 26 05 11- 6, which is a general section and not specific to the equipment requiring factory training. Please indicate what equipment will require on-site factory training.Provide training as required per specifications. Review specifications for training requirements.Issued / Closed
RS-031Site / LogisticsGeneralElevator use - both buildingsElevator availability for equipment and pipingWill there be an elevator available for use in both buildings for equipment and piping?YesIssued / Closed
RS-032SeismicVA Handbook H18-8Seismic design requirementsCopy of H18-8 Seismic Design RequirementsCould you provide a copy of the VA Handbook H18-8 Seismic Design Requirements?VA Handbook H18-8 Seismic Design Requirements is available on the VA TIL: https://www.cfm.va.gov/til/Issued / Closed
RS-033Phasing / OutagesGeneralOpen chasesNumber of chases open at the same timeHow many chases can be open at the same time?Number of chases allowed to be open simultaneously will be determined on the phasing plans dependent on impact on hospital operations.Issued / Closed
RS-034Site / LogisticsGeneralHospital facilitiesContractor use of hospital facilitiesWill contractors be able to use the hospital facilities?Yes, public bathroomsIssued / Closed
RS-035Site / LogisticsGeneralTemporary powerPower for welding machinesWill the hospital provide power for the contractors to plug in welding machines?NoIssued / Closed
RS-036SeismicGeneralSeismic scopeProfessional Structural Engineer requiredIs a Professional Structural Engineer required for the seismic scope?Refer to previous RFI ResponsesIssued / Closed
RS-037Mechanical - SteamGeneralPRVPRV basis of design (brand/model)What is the basis of design for the PRV; brand, model, etc.?BOD is Armstrong GP-2000, refer to specifications for additional informaitonIssued / Closed
RS-038Mechanical - SteamDwg MD-102 (note 1)Hazardous mixing tankCombustible venting near tank; hot work safetyIs there anything combustible venting from or around the Hazardous Mixing tailer that would make welding dangerous to the contractor. Reference note 1 on MD-102.No known combustible materials are known at this time.Issued / Closed
RS-039Bid / ContractSolicitationBid dateExtension of bid dateWould the VA consider extending the bid date to allow for more time to thoroughly review all plan and specs?Not at this timeIssued / Closed
RS-040Scope / AlternatesProject 558-323OR addition pipingDetail of piping scope in recently constructed OR additionCould you be more specific about what the 'scope for piping replacement in recently constructed OR addition building, part of project 558-323' consists of?This is listed in the 01 00 00 General requirements paragraph 1.3 statement of bid itemsIssued / Closed
RS-041Site / LogisticsGeneralMechanical roomsAdditional site visit to verify pipe locations and sizesCan we please make another site visit to verify pipe locations and sizes in the mechanical rooms?Not at this timeIssued / Closed
RS-042Site / LogisticsSpec 01 74 19Waste/material movementDedicated elevator for waste, material, equipmentReference: Spec 01 74 19. Will the VA will assign one elevator to take waste, material, and equipment up and down to the upper floor?Service elevatros S4 and S5, waste material must be transported correctly by ICRA standards.Issued / Closed
RS-043Site / LogisticsGeneralDumpster/trailer parkingParking for dumpster and trailer near loading dockAre we going to have parking spots available for dumpster and trailer close to the loading dock for abatement and trash?NoIssued / Closed
RS-044Site / LogisticsSpec 22 05 11CrawlspacePhotos of crawlspace work area and clearancesReference: Spec 22 05 11. Can pictures be provided of the crawlspace to show area of work, clearances, etc.? Access to these areas was not allowed during the site visit.Basement photos provided. Crawlspace is a confined space and photos were not able to be obtained.Needs VA Input
RS-045Phasing / OutagesSpec 01 00 00Work hours / stagingWork hours; staging by floorReference: Spec 01 00 00. Is work to be performed during normal business hours, afterhours, weekends only? Is there project staging for different floors?Depends on the location, G1003 notes refer to what areas work can occur and time.Issued / Closed
RS-046SpecificationsSpec 22 05 11BAABAA (Buy American) requirement for all pipingReference: Spec 22 05 11. Is all piping required to meet the BAA requirements?Yes, piping shall comply with BAAIssued / Closed
RS-047ArchitecturalSite visit notesExisting wall finishesWall finishes in patient rooms, labs, exam rooms, officesReference: Site visit notes. During the site visit, access to patient rooms, Labs, Exam rooms and offices was not allowed. Can you specify the existing wall finishes in these rooms?

tc={9CDE8B45-F09B-43C9-985D-407AD67AE49D}: [Threaded comment]

Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924

Comment:

RS-047--shouldn't the existing wall finishes been catalogued during investigation? have they changed since?

Wall finish in these areas is paint. Refer to drawings for requirements of finishesIssued / Closed
RS-048Mechanical - SteamDwg 1-MD101 (note 2)Steam PRV station demolitionConfined space status; photosReference: Drawing 1-MD101 note 2. Drawing 1-MD101 note 2 requires removal of steam pressure reducing station located in a confined space. Is the confined space permitted or not permitted? Can photos be provided for these areas?Assumed permitted, AE was unable to access these areas during field investigations. Confirm access requirements and any existing documentation with the VA.Issued / Closed
RS-049Phasing / OutagesDwg GI003 / GI103Phasing groupsConsecutive work on more than 1 phase groupReference: Drawing GI003 Phasing Groups. Drawing GI103 Phasing Groups / There are 16 phases on multiple floors can more than 1 group be worked on consecutively at a time? This would reduce the number of shutdowns required.YesIssued / Closed
RS-050Site / LogisticsSolicitationSite visitDate for site-visit sign-in sheetReference: Solicitation. Is there a time and date when the site-visit sign-in sheet will be sent to GC's?Will be posted with RFIsIssued / Closed
RS-051Asbestos AbatementAsbestos Survey Analytical Results 2.1, 4.1Building 1 pipe insulation / elbowsDoes survey 2.1 quantify all abatement locationsReference: Specifications Asbestos Survey Analytical Results 2.1, 4.1. Does the asbestos survey 2.1 quantify all abatement locations for Building 1 pipe insulation and elbows to be included in the bid?The asbestos survey 2.1 quantify visible and accessible pipe insulation and elbows identifeid in the survey. The quantities mentioned in 2.1 and section 02 82 13.13 - 1 of the glovebag specifications are to be bid.HS11/13/26Issued / Closed
RS-052Asbestos AbatementAsbestos Survey 2.1 (pp. 424-425); 4.1 (pp. 427-428)Survey quantity conflictWhich survey governs pricing quantitiesReference: Pages 424 & 425- 2.1 Asbestos Survey Analytical Results. Pages 427 & 428-4.1 of the specs doc.. The quantities on the 2017 asbestos survey 2.1 vary from those on survey 4.1. Which survey are we to use for quantities in pricing?The asbestos survey 2.1 quantify visible and accessible pipe insulation and elbows identifeid in the survey. The quantities mentioned in 2.1 and section 02 82 13.13 - 1 of the glovebag specifications are to be bid.HS11/13/26Issued / Closed
RS-053ArchitecturalDwg 1-PD102, 1-PD103Risers in exterior wallsExterior wall section and penetration detailsReference: Drawing 1-PD102, 1-PD103. Drawing 1-PD102 Shows risers located in exterior walls. Can the VA provide the applicable exterior wall section details, including wall construction and required penetration details, for these riser locations?Piping is going through furred wall sections at exterior wall locations.Issued / Closed
RS-054Asbestos AbatementSpec 02 82 13.13Work hoursHours allowed for wall demo to access ACM risersReference: Spec 02 82 13.13. What are the work hrs. allowed for the Demolition of walls to access riser piping with asbestos?Minimize noise using every action possible. Perform noise-producing work in less sensitive hours of the day or week as directed by the COR. Maintain noise-produced work at or below the decibel levels and within the time periods specified.HS11/13/26Issued / Closed
RS-055Asbestos AbatementSpec 02 82 13.13Work hoursHours allowed for glovebagging ACM TSIReference: Spec 02 82 13.13. What are the work hrs. allowed for the glovebagging of Asbestos TSI on pipe in walls and other areas? Above hallway ceilings?Minimize noise using every action possible. Perform noise-producing work in less sensitive hours of the day or week as directed by the COR. Maintain noise-produced work at or below the decibel levels and within the time periods specified.HS11/13/26Issued / Closed