36C24626B0020.docx

DOCX document 18 KB Posted

Attached to
Z1NB--Boiler Replacement Sources Sought
Solicitation number
36C24626B0020
Issued by

About this file

This is a Sources Sought Notice issued by the Department of Veterans Affairs Network Contracting Office 6 for market research purposes regarding a boiler replacement project at the Durham VA Medical Center Campus in Durham, North Carolina. The VHA is seeking qualified vendors to provide comprehensive labor, materials, tools, equipment, transportation, supervision, coordination, and services for replacing three firetube boilers. The scope includes removal and disposal of existing underground fuel-oil storage tanks and boilers, installation of two temporary boilers during replacement of the three permanent 600 HP boilers (with a requirement to provide a trailer-mounted temporary boiler within 48 hours if one fails), and installation of new sprinkler systems in Buildings 7 and 9. Construction must be performed during VA first shift (7:00 AM–3:30 PM, Monday–Friday), with utility work in parking lots conducted during second shift (3:00 PM–11:30 PM). Any construction requiring utility outages must occur during second shift or weekends with four-week advance coordination with the VA Contracting Officer's Representative.

The anticipated project magnitude ranges from $10,000,000 to $20,000,000, with a period of performance of 574 days from the Notice to Proceed. The applicable NAICS code is 236220 (Commercial and Institutional Building Construction) with a small business size standard of $45.0 million. Pursuant to 38 U.S.C. § 8127(d), the acquisition will be set-aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSBs) or Veteran-Owned Small Businesses (VOSBs) registered in the SBA VetCert database if there is a reasonable expectation of receiving two or more qualified offers and fair and reasonable pricing. Interested vendors must submit responses by 5:00 PM EDT on February 4, 2026, to alice.custis@va.gov, including company information, SAM Unique Entry ID, socioeconomic size category, capabilities statement, and responses to specific questions regarding project timeline, temporary boiler procurement, construction schedule impacts, and project feasibility. This notice does not constitute a formal solicitation, and no payment will be provided for submitted information.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sources Sought Notice Sources Sought Notice

SUBJECT*
Boiler Replacement Sources Sought

GENERAL INFORMATION

CONTRACTING OFFICE’S ZIP CODE*
23667
SOLICITATION NUMBER*
36C24626B0020
RESPONSE DATE/TIME/ZONE
02-10-2026 8 am EASTERN TIME, NEW YORK, USA
ARCHIVE
30 DAYS AFTER THE RESPONSE DATE
RECOVERY ACT FUNDS
N
SET-ASIDE
SDVOSBC
PRODUCT SERVICE CODE*
Z1NB
NAICS CODE*
236220

CONTRACTING OFFICE ADDRESS

Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667

POINT OF CONTACT*

Contracting Specialist Alice Custis alice.custis@va.gov

757.722.9961 ext 18670

PLACE OF PERFORMANCE

ADDRESS

508 Fulton St

Durham NC

POSTAL CODE
27705
COUNTRY
USA

ADDITIONAL INFORMATION

AGENCY’S URL
https://www.va.gov/
URL DESCRIPTION
Department of Veterans Affairs mainpage

AGENCY CONTACT’S EMAIL ADDRESS

EMAIL DESCRIPTION

DESCRIPTION

THIS IS A SOURCES SOUGHT NOTICE ONLY.

This notice does NOT constitute a request for proposal, request for quote, or invitation for bid. No formal solicitation document exists at this time. We are seeking information for market research purposes only. The Government will not pay for any information solicited.

The VHA Network Contracting Office 6 (NCO 6) is conducting a market survey to find qualified vendors to provide all labor, materials, tools, equipment, transportation, supervision, coordination, and services necessary for replacing three (3) firetube boilers at the Durham VA Medical Center Campus. Scope includes and is not limited to:

· Removal, disposal, and replacement of existing underground fuel-oil storage tanks and boilers

· Install two temporary boilers while the three permanent 600 HP boilers are being replaced. Should one of the Temporary Boilers fail, the Contractor should have a trailer mounted temporary boiler within 48-hours to fulfill the steam requirement until the failed boiler in building 24 is returned to service.

· Install new sprinkler system in Buildings 7 (boiler plant) and 9 (chiller plant)

a. Construction shall be performed during VA working 1st shift, 7AM-3:30PM, Monday-Friday. Utility work in the East and West parking lots shall be performed during VA working 2nd shift, 3 PM – 11:30 PM

b. Contractor shall phase construction in either the East or West Parking to return spaces to normal usage at the end of all shifts.

c. Any construction that requires utility outage shall take place during second shift or during the weekend. Coordinate shutdowns with the VA COR 4-weeks in advance.

The proposed NAICS 236220 Commercial and Institutional Building Construction is applicable to this acquisition; with a size standard of $45.0 Million.

The anticipated Magnitude of Construction is between $10,000,000.00 and $20,000,000.00.

The anticipated Period of Performance is 574 days from the Notice to Proceed.

Small Business Requirements For market research purposes, all responses to this notice will be reviewed, regardless of small business/socioeconomic category, including those firms that are identified as large businesses. Review of responses to this notice will support later determination of acquisition strategy and set-aside requirements if a solicitation becomes available.

Pursuant to 38 U.S.C. 8127(d), acquisitions will be set-aside for SDVOSBs or VOSBs, registered in the SBA VetCert database, whenever there is a reasonable expectation of receiving two or more offers/quotes from eligible, capable and verified firms, and that an award can be made at a fair and reasonable price that offers best value to the Government.

However, if responses from qualified firms prove inadequate, an alternate set-aside or full and open competition may be considered.

Instructions:

All interested parties should respond, in writing via email to alice.custis@va.gov. No telephone inquiries will be accepted. Your response is required by 5:00 PM EDT on Wednesday, February 4 , 2026.

In your response, please include the following:

· Company name

· Address

· Point of contact with email and phone number

· SAM Unique Entry ID number (see https://www.sam.gov for more information)

· Company Socio-Economic SIZE (example…large, small, SDVOSB, VOSB, WOSB etc.)

· Proposed NAICS code or PSC (if different from above)

· Capabilities statement, to include experience with contracts of similar scope and magnitude

· Brief explanation of how company will comply with the limitations on subcontracting (if applicable)

In addition to this information, please include responses to all of the following in your submission:

· What additional information would you require in order to provide a quote for this project?

· Approximately how long would it take to complete the project, including lead times for materials?

· Is the anticipated period of performance reasonable? If not, what would you recommend?

· Is 48 hours enough time to get a temporary boiler? What is a reasonable time expectation to allow for one to be procured and brought to the site? What are the cost implications between 48 hours for a temporary boiler and what you are proposing as the reasonable time expectation?

· What impact do the working hours or the requirement for a four-week shutdown have on the schedule or the pricing?

· Is our anticipated Magnitude of Construction appropriate for this project?

· Is there anything that would deter you from responding to this requirement?

*= Required Field
Sources Sought Notice

Sources Sought Notice