This is an amendment (Standard Form 30) to solicitation 36C24625B0003 that provides responses to submitted questions and includes site visit rosters and drawings for a metal egress stairs project at the Salisbury VA Medical Center Building 11. The amendment clarifies key technical aspects including: no contractor cutting required for stair access as the VA will handle window removal/door installation; materials must meet federal/state/local codes for healthcare environment metal egress stairs; color samples are to be submitted for facility selection; and the Superintendent can serve as QC and Safety Officer if credentials are approved. The facility provided intent-only drawings but requires contractor-submitted engineered shop drawings for approval.
The amendment addresses contractor questions about schedule flexibility during holidays (to be discussed during scheduling meetings), and provides options regarding stair support design - either suspended with brackets attached to brick facade or supported by posts to ground level to accommodate future windshield enclosure. The VA requests separate quotes if cost difference between designs is significant. The original solicitation remains a 120-day period of performance for designing and installing two metal egress stairs, including all labor, equipment, and materials.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24625B0003 0002.docx | DOCX document | |
| 659-24-300_Reference DWGs_20240820_.pdf | ||
| 36C24625B0003_1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 12-23-2024 659-24-300 Department of Veterans Affairs Network Contracting Office 6 1601 Brenner Ave Salisbury
NC
28144
To all Offerors/Bidders
36C24625B0003
X X X The purpose of this amendment is to update the Questions and Answers of the RFI's submitted on the project.
Posting of the site visit roster and post the drawings.
The purpose of this amendment is to post the response answers to the questions from the RFI period.
The site visit roster and drawings are also attached as well.
1. Will we be required to cut in access to the stairs?
0. No, the VA has an inhouse project to remove windows and install an access door.
1. What gauge steel is required for stairs, railings, supports and brackets?
1. Materials, fabrication, and install shall meet all federal, state, and local codes pertaining to metal egress stairs in a healthcare environment.
1. Specific color is not mentioned for stairs, only lists for railing. Are we matching the railing color?
2. See SOW (A.5. Finishes)
2. We ask for the Contractor to submit a sample color panel for the facility to choose from.
1. What are the on-site supervision requirements?
3. See SOW (B.2. Supervision by Contractor)
1. Due to size of project wanted to confirm if a Superintendent and QC Manager are needed or just a Superintendent?
4. Superintendent can also serve as QC and Safety Officer as long as their credentials are approved by the facility.
1. Are plan sheets available for this project and if so will they be posted?
5. The facility has drawings for intent only. These will be sent out with this RFI.
5. Referring to the SOW (A.3. Architectural), Contractor will submit engineered shop drawings for the facility to approve.
1. In light of the upcoming holiday period, varying business hours, vacations and other time off along with reduced time to engage vendors as well as review any plan sheets posted for this project would a delay (one [1] to two [2] weeks) be considered?
6. After the Contractor has submitted their project schedule, this can be discussed during the scheduling meeting between the Contractor, COR, and the CO.
6. The COR and CO will discuss any concerns the Contractor may have.
6. Any extension to the contract must have valid reasoning and be approved by the CO.
1. The drawings currently show the stairs being suspended and attached to the brick façade with brackets. During the site walk it was mentioned that the VA wants support post for stairs to come all the way down to the ground and connect with the existing pad in front of double doors, as a plan to enclose at some point to create a wind shield for the entry into the shop and storage areas. Do we need to proceed with bidding as shown in drawings or do we need to adjust to make wind shield an option in the future?
7. The facility’s drawings are for intent only. We would like to accommodate requests where possible but need to stay in budget.
7. If the cost between the two types are significantly different, the facility asks for the contractor provide two separate quotes so we may weigh our options.
See attached document: 659-24-300_Reference DWGs_20240820_.