This sources sought notice requests qualifications packages from architect-engineering firms for a sanitary sewer survey project at the Hampton VA Medical Center in Hampton, Virginia. Responses are due by March 1, 2023. The Department of Veterans Affairs intends to award a firm-fixed price contract for A/E services including schematics, design development, construction documents, specifications, construction period services, site visits, cost estimates, as-built documentation, and related information. The estimated construction cost is between $2,000,000 to $5,000,000. This is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses. The selected A/E firm will provide design and construction administration services with design completion expected within 405 calendar days of notice to proceed, and construction period services for 400 calendar days from the construction award date.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sources Sought Notice Sources Sought Notice

SUBJECT*
Sanitary Sewer Survey | 590-23-102

GENERAL INFORMATION

CONTRACTING OFFICE’S ZIP CODE*
23667
SOLICITATION NUMBER*
36C24623R0013
RESPONSE DATE/TIME/ZONE
03-01-2023 9:00 AM EASTERN TIME, NEW YORK, USA
ARCHIVE
99 DAYS AFTER THE RESPONSE DATE
RECOVERY ACT FUNDS
N

SET-ASIDE

PRODUCT SERVICE CODE*
C1DA
NAICS CODE*
541330

CONTRACTING OFFICE ADDRESS

Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667

POINT OF CONTACT*

Contract Specialist Toni J. Knight Toni.Knight@va.gov 757-315-3959

PLACE OF PERFORMANCE

ADDRESS
Department of Veterans Affairs

Hampton VAMC

Hampton Virginia

POSTAL CODE
23249
COUNTRY
USA

ADDITIONAL INFORMATION

AGENCY’S URL

URL DESCRIPTION

AGENCY CONTACT’S EMAIL ADDRESS
Toni.Knight@va.gov
EMAIL DESCRIPTION
NCO 6 Contracting

DESCRIPTION

This request for A-E firm qualifications packages is a 100% set-aside for Service-Disabled Veteran Owned Small Business (SDVOSB) concerns under VAAR 852.219- 10, VA Notice of Total Service-Disabled Veteran-Owned Small Business Set-Aside/ VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (NOVEMBER 2020) (DEVIATION).

THIS IS NOT A REQUEST FOR PROPOSAL. THIS IS A REQUEST FOR SF 330'S ARCHITECT/ENGINEER QUALIFICATION PACKAGES ONLY.

ALL INFORMATION NEEDED TO SUBMIT SF 330 DOCUMENTS IS CONTAINED HEREIN. NO SOLICITATION PACKAGE, TECHNICAL INFORMATION, OR BIDDER/PLAN HOLDER LIST WILL BE ISSUED.

THERE WILL BE NO SITE VISITS ARRANGED DURING THIS PHASE OF THE REQUIREMENT.

PUBLIC ANNOUNCEMENT FOR PROCUREMENT OF ARCHITECT-ENGINEERING (A/E) SERVICES: This is a request for Standard Form 330, Architect-Engineer Qualifications only. A-E Services are being procured in accordance with the Selection of Architects and Engineers Statute (Public Law 92-582), formerly known as the Brooks Act, and implemented in Federal Acquisition Regulation (FAR) subpart 36.6. All submissions will be evaluated in accordance with the below selection criteria. Please submit SF 330 packages to the point of contact(s) listed below. The Government will not pay, nor reimburse, any costs associated with responding to this request. The Government is under no obligation to award a contract as a result of this announcement. Firms will be selected based on demonstrated competence and qualifications for the required work. Any resulting award for the proposed A/E services will be procured under a negotiated Firm-Fixed Price contract in accordance with (IAW) FAR Part 15.

GENERAL INFORMATION:

The Department of Veterans Affairs, Hampton V.A Medical Center located in Hampton VA, is seeking sources and intends to award a firm fixed-price contract for Architect/Engineering (A/E) firm to provide Schematics, Design Development, Construction Documents, Technical Specifications, Construction Period Services, Site Visits, Cost Estimates, As-Built Documentation, and all other related information for Project # 590 -23 - 102, “Sanitary Sewer Survey” located at 100 Emancipation BLVD, Hampton VA, 23667.

Design shall comply with VA guidelines and specifications. Design manuals and specifications can be found at http://www.cfm.va.gov/TIL/. Proposed work is located at Hampton VA Medical Center, Hampton, Virginia, 23667.

The Estimated Construction Magnitude in accordance with VA Acquisition Regulation (VAAR) 836.204 (f) is between $2,000,000 and $5,000,000.

The A/E Services listed herein is being procured in accordance with the Federal Acquisition Regulation (FAR) 36.6 and VAAR 836.6. All offerors are advised that in accordance to VAAR 836.606-71 the total cost of the architect or engineer services to produce and deliver designs, plans, drawings, and specification must not exceed six percent (6%) of the estimated cost of the construction.

Potential contractors must provide credentials that confirm registration of Architects or Engineers registered to practice in this particular professional field involved in Virginia, must be registered in SAM (www.sam.gov) and Veteran Small Business Certification (VetCert): http://veterans.cerify.sba.gov at time of submission of their qualifications in order to be considered for an award.

As a prospective offeror for this Service-Disabled Veteran-Owned Small Business (SDVOSB) set aside, you are verifying your company meets the status requirements of a SDVOSB concern as established by VAAR 852.219-10. NOTE - Offerors are referred to 852.219-10 (d)(1) Services. In the case of a contract for services (except construction), it will not pay more than 50% of the amount paid by the government to it to firms that are not VIP-listed SDVOSBs. In order to assure compliance with this clause, all firms submitting a SF330 for this Special Notice are required to indicate what percentage of the cost of contract performance will be expended by the concerns employees and in which discipline(s) and percentage of cost of contract performance to be expended (and in what disciplines) by any other subcontracted or otherwise used small or large business entity(s). Any subcontracted or otherwise business entity(s) used must be identified by name, office location and size/type of business (i.e. SDVOSB, VOSB, 8(a), large, etc.). All submissions will be evaluated in accordance with the evaluation selection criteria as specified herein.

The Hampton VA Medical Center is a working facility and phasing plans for minimizing downtime, and provisions for continuation of service during outages is critical to this project.

Points of Contact: Toni J Knight, Contract Specialist Email: Toni.Knight@va.gov will be the primary contact. Please cc: Contracting Officer: Guy.Brooks@va.gov on all time sensitive submissions.

PROJECT INFORMATION:

Project No.: 590-23-102 Project Title: A-E Sanitary Sewer System Survey Hampton VAMC 100 Emancipation Blvd Hampton, Virginia 23667 The NAICS Code for this procurement is 541330, Engineering Services, and the applicable Small Business Size Standard is $22.5 million annual revenue. The projected award date for the anticipated A/E contract is on or before May 31, 2023.

The anticipated period of performance for completion of final report with recommendations and repair processes is 405 Calendar Days after the Notice to Proceed (NTP).

An Architect & Engineer (A/E) contract will be negotiated. The A/E shall provide a cost estimate of future repairs. Cost estimates detailing quantities of materials, labor, profit, overhead, insurance, taxes, etc. in the format found at https://www.cfm.va.gov/til/aeDesSubReq.asp for Minor and NRM Projects.

Hampton VA Medical Center Architect Engineer (A/E)

SCOPE OF WORK

Sanitary Sewer System Survey and Repairs Project # 590-23-102

-- Services --

Provide professional Architect/Engineer services to include:

1. Site investigation

2. Civil

3. Environmental survey (lead, asbestos, mold identification, etc.)

4. Construction drawings and specifications

5. Third party construction estimates

6. Construction period services

7. Construction Inspections

8. Conduct Infection Control Risk Assessment (ICRA) in conjunction with VA Safety/Infection Control staff

-- Project Scope --

SCOPE:

The A/E shall provide design services for NRM construction project 590-23-102. The intent of the project is to remedy inflow and infiltration into the existing sanitary sewer network of the Hampton VAMC facility by rehabilitating and/or replacing sections of the system in disrepair. A condition assessment was conducted by VA in conjunction with Hampton Roads Sanitation District (HRSD) in February 2022 and will be provided with project documents as a guide, as attachment 1.

Design shall comply with VA guidelines and specifications. Design manuals and specifications can be found at http://www.cfm.va.gov/TIL/. Proposed work is located at Hampton VA Medical Center, Hampton, Virginia, 23667.

Design for a construction budget of $3,147,000. Completed design shall result in a cost that is within the budget limitations. To ensure this, the A/E shall set up one (1) or more bid deduct alternatives totaling 10% of the construction cost. If the base bid cost exceeds budget, and deduct alternates do not bring the project within the construction budget, the A/E shall re-design or take necessary steps to reduce the cost so that budget limitations are not exceeded.

The Architect/Engineer shall make a thorough investigation of the existing site (including topographic surveys, test borings, test pits, soil tests, subsurface exploration and other investigations as he determines and are required for the proper design of the project). Existing conditions shall be determined by verifying information from field investigations and any documentation that may be available. A survey shall be conducted to obtain sufficient information to permit designers to develop a detailed cost estimate and schematics. The entire Veterans Affairs drawing files will be made available and accessible along with reproduction materials, but the A/E shall provide the manpower to reproduce prints. AutoCAD drawings are also available for use. This information is the best available but the Government does not guarantee its accuracy or completeness. The A/E investigation of field conditions shall be performed in a competent, professional manner in accordance with Architectural Design Manual PG 18-10. Site utility locations will be verified by the A/E (VA staff will not mark utilities, but will assist with locating if workload permits).

Incorporate in the preliminary drawings the pre-construction risk assessment/evaluation as the sample shown below.

Provide bound specifications and 100% construction drawings with all xref’s bound. Construction documents will be required to be furnished in hard copy, electronic .dwg files (AutoCAD 2022 or most current at the time of final design submission) and electronic .pdf files. All AutoCAD drawings (including subcontractors) shall be in an organized drawing file system using its “Project Browser/Navigator”.

The A/E shall include in his design any environmental permits (i.e. VPDES) and ensure proper erosion control measures are also included in the contract documents for construction.

Cost estimates detailing quantities of materials, labor, profit, overhead, insurance, taxes, etc. in the format found at https://www.cfm.va.gov/til/ae/CostEstimatingManual.pdf.

Life safety and infection control will be taken into account during all phases of design. Final construction documents will detail measures to be taken by the contractor to assure life safety and infection control. A preconstruction risk assessment will be completed and included in project submissions.

Plans for phasing construction to minimize impact on the medical center will be incorporated into the construction documents. Plan construction to include impacts on the medical center such as relocating patient and staff equipment, providing temporary barriers, providing temporary utilities, temporary means of entrance and egress (i.e., ramps, steps, automatic door operators, push plates, sensors, etc.), minimizing impact on vehicle traffic, patient flow, etc.

All design submissions will be submitted in accordance with the Program Guide PG-18-15, Volume C, for Minor and NRM projects. These submission requirements may be found at the following web site https://www.cfm.va.gov/til/aeDesSubReq.asp. Other applicable program guides can be found at https://www.cfm.va.gov/til/dGuide.asp.

Provide construction administration to include shop drawings review, site inspections, and RFI response.

-- Site Investigations --

EXPECTATION: A/E shall make site visits as necessary to survey existing conditions.

Make site visits as required to determine existing as-built conditions affecting this project. Note: Information including drawings and other documentation provided to the A/E is used as reference only. All additional references and specifications are available in VHA’s Technical Information Library at address http://www.cfm.va.gov/TIL/. A/E shall field verify every aspect that relates to the project. Coordinate visits with the Project Manager/Contracting Officer Representative (COR) as assigned after award. The A/E shall arrange for and oversee the performance of such investigations. Auto CAD architectural/civil background drawings will be provided by the VA upon request. The A/E shall field verify all dimensions, layouts, etc. A/E shall field verify every aspect that relates to the project.

-- Design Review Schedule --

EXPECTATION: Submit review package so they are received on the noted day.

Review
Due Date (Calendar Days After NTP)
Initial Project Design Meeting (PDT)
0
30% percent construction documents
90
VA Review Period (30 days)
120
50% percent construction documents
210
VA Review Period (30 days)
240
95% percent construction documents
330
VA Review Period (30 days)
360
100% Construction Documents
405

Notes: NTP will be issued at Project Design Team (PDT) meeting. A/E will be required to attend and take minutes from each PDT meeting. Minutes will be submitted electronically to the Project Manager/COR and Contracting Officer within three calendar days of each meeting.

-- Design Requirements/Submissions –

EXPECTATIONS:

Submit complete review package in accordance with the following requirements and guidelines outlined in https://www.cfm.va.gov/til/aeDesSubReq.asp. Please pay specific attention to the schematic, design, and construction submission requirements. As appropriate depending upon the complexity of the design, the A/E may elect to delete individual submissions where not required (i.e. Do not address A. Site Development, Landscaping for interior renovation projects)

DELIVER ONE (1) DISC AND TWO (2) HARD COPIES:

Design Development (DD) 25%:

· Address all comments from the Schematic Submission review.

· Identify all design calculations.

· Identify all existing utilities and utility requirements.

· Complete applicable DD Checklist requirements Design Development (DD) 50%:

· Address all comments from the previous Submission review.

· Complete remaining DD Checklist requirements Design Development (CD) 95%:

· Address all comments from the previous Submission review.

· Design all finishes

· Finalize required submittals.

· Complete applicable CD Checklist Contract Documents (Bid documents):

· Submit a complete document package of all contract requirements. The Cover Page shall be submitted for approval signatures. If necessary, update and submit until approved by the VA.

· Consolidate all necessary submittals by specification section on an Excel spreadsheet. Checklist to be utilized to track/monitor submittal process.

-- Construction Period Services –

PROVIDE:

· Assist the VA to determine whether the contractor or subcontractor meets qualification requirements, supported by written recommendations of any problems or litigation encountered in past based on firsthand knowledge.

· Review all submittals and provide recommendations to the VA within fourteen (14) calendar days upon request.

· Review and provide replies to contractor generated RFIs when required by the Project Manager/COR within seven (7) calendar days.

· Review contractor's cost estimates and provide recommendations to the VA.

· Make site visits on requests of the VA and prepare written reports to include agreed upon changes in design as determined necessary during the construction. Visits made based on errors and omissions in design will be at no cost to the VA.

· Participate in partial/final acceptance inspections as scheduled and generate punch list items for completion. The punch list shall reference the contract documents for specific deficiencies (i.e. specification section, drawing detail, etc.)

· Prepare as-built drawings on original set with A/E’s stamp, based on record drawings that the contractor kept during construction. Transpose contractor’s as-builts to AutoCAD (.dwg) and provide a set of updated as-builts on CD within 30 days to the Project Engineer. Final drawing submittal will include hard copies as described for other submissions as well as a CD clearly labeled with the project name, number and submittal date containing:

1. Folder labeled “bid documents”

a. All specifications bound in one (1) word document (make sure spec sections are separated by page breaks and that new sections start on right hand page)

b. All drawing sheets in one .pdf file.

2. Folder labeled “DWG’s” with subfolders containing engineering disciplines (Architectural, MEP, Structural, Civil, etc.) which includes the .arj file (for every discipline) to launch and organize the drawing file system and make all drawings the current project inside of AutoCAD.

3. Folder labeled “PDF sheets” containing separate .pdf documents for each discipline.

4. Folder labeled “cost estimate” containing a copy of the final construction cost estimate documents.

5. Folder labeled “calculations” containing final calculation documents.

6. Folder labeled “specifications” with a word document for each spec section.

7. Folder labeled “misc” for IH reports, materials testing, VPDES permit, soils tests, sustainability checklist, etc.

8. Upon construction completion, red line drawings will be furnished to the A/E to prepare as built drawings. Final as built drawings will be furnished as master building drawings in a project manager format prescribed by the VA.

· The A/E shall review and approve all specified equipment and installation submittals and shop drawings. The A/E shall attend the pre-construction conference to review and confirm project scope. During construction, the A/E shall allow one (1) pre-construction conference, three (3) intermediate inspections and one (1) final inspection as directed and scheduled by the COR.

-- Period of Performance –

· Design completion: 405 calendar days; VA design reviews

· Procurement timeframe: Six (6) months from the time Engineering submits package to contracting. Designer shall answer pre-bid RFIs and provide updated construction documents to capture any changes made through the procurement process

· Construction period services: 400 calendar days from construction award date

· Total contract period: 985 calendar days

See Sources Sought Notice for Additional Information