RFI Questions Expand Parking Lot T 36C24621R0042.pdf

PDF 426 KB Posted

Attached to
Y1PZ--Expand Parking Lot T
Solicitation number
36C24621R0042
Issued by

View the file

Other files

File Type Posted
S06 36C24621R0042 0003.pdf PDF
36C24621R0042 0003_1.docx DOCX document
Itemized Breakdown Expand Parking Lot T.xlsx XLSX spreadsheet
36C24621R0042 0002_1.docx DOCX document
36C24621R0042 0002.pdf PDF
S04 Site visit sign-in.pdf PDF
P07 VA20210188 Highway 1-1-2021.pdf PDF
36C24621R0042 0001.docx DOCX document
658-20-108_Specs.pdf PDF
658-20-108_Drawings.pdf PDF
36C24621R0042_2.docx DOCX document
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI questions for Expand Parking Lot T

1. During the site visit there were two trees noted as their driplines were in the area of disturbance and they may need to be removed. Please clarify. Contractor shall layout new parking lot. If additional tree removal is required it will be addressed through a Contract modification

2. Page 9 of 65 of the RFP references an itemized breakdown of costs to be provided on (attachment A). Attachment A not in the bid documents. Please provide. Itemized breakdown is Excel Worksheet please return it back in a pdf format. See Attachment – Itemized Breakdown Expand Parking Lot T

3. Will there be a staging area near the site for this project?

Yes

4. Spec section 01-00-00-1.6.G states: To ensure such executions, Contractor shall furnish the COR/Contracting Officer’s Representative with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR/Contracting Officer’s Representative two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to insure accomplishment of this work in successive phases mutually agreeable to Medical Center Director, COR, and Contractor. Question: There are no phases indicated on drawings. What are the phasing sequences expected by the government? This is a General Requirement. No Phasing is expected on this project

5. Spec Section 01-00-00-1.17D. Government does not guarantee that other materials will not be encountered, nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of Veterans Affairs, bidders will be permitted to make subsurface explorations of their own at site.

Question: Are there boring logs that can be made available as stated in the specification?

No Borings were performed

6. The drawing labeled “Erosion Control and Site Plan” shows both temporary seeding (TS) as well as permanent seeding (PS) being placed in the limits of disturbance. Detail #1 on the “Permeable Grid System / Parking Stall Installation” shows 5/8” dia/clean aggregate on top and makes no mention of any type of seeding. Question: Can you please confirm the intent of the finished product (i.e., grass or no grass)? Parking area to be finished with gravel and any disturbance outside of it will be fixed and permanently seeded

7. Is the proposal package to be presented in hard copy, or via email? The RFI states both.

Email the proposal to bryant.guerrant@va.gov, a hard copy of Bid Bond will have to be mail to: Salem VA Medical Center; Attn: Bryant Guerrant, Contract Specialist; 1970 Roanoke Blvd; Building 74 Room 211; Salem Virginia 24153

8. Is the Technical Proposal required? Yes. Contracting to confirm based on Acquisition

Strategy

9. Please provide drawings that are to Scale. The current drawings are not to scale.

Auto-Cad drawings will be provided to the successful bidder with Centerline and some dimensions. We are working on this now.

mailto:bryant.guerrant@va.gov

10. Is a bond required for this project if the bid is less than $150,000? If the contract will exceed $30,000 but will not exceed $150,000, the bidder/offeror to whom award is made will be required to furnish a Payment Bond, Standard Form 25A, or alternative payment protection. (See Information regarding Bidding Material, Bid Guarantee and Bonds page)

11. Will a SWPP plan be required for this project?

No SWPP is required

12. The drawing labeled “Civil Details and Notes” under the section called “Erosion and Control Sediment” states “The new parking lot is comprised of a two-way (30-ft wide) travel lane with parking stalls on either side. The new parking lot is constructed over a relatively flat, grassed area with low slopes (less than 5%) and follows natural contours of the land in an effort to maintain existing drainage patterns. The drawing labeled “Demolition / Grading Plan” shows existing and new contours.

• Question: At the site visit, a noticeable dip in the terrain was present, can you please confirm that there are no requirements for any additional drainage systems (i.e., culverts) other than the gravel diaphragm (detail D1) depicted on the drawings? Install per Plans and Specs.

13. The drawing labeled “Erosion Control and Site Plan” depicts the new parking lot expansion tying into the existing parking lot.

• Question: At the site visit, the tie-in area did not appear to be a parking lot, rather a graveled area. Can you please confirm that there is no work in this area other than butting up to this area with the new parking lot as required by the drawing? Bring New parking Lot up even with existing Parking Lot. Once laid out we can confirm more