36C24621B0004 0001_1.docx
DOCX document 38 KB Posted
- Attached to
- Z1DA--659-20-201: Nurse Call (VA-21-00042272)
- Solicitation number
- 36C24621B0004
About this file
This document contains questions and answers regarding a federal contract opportunity for nurse call system upgrades at a Department of Veterans Affairs medical center. Key details include that the opportunity is for replacing the nurse call systems in several buildings on site. While asbestos abatement was included in the specifications, it is not required for this project. Offerors should plan to use new conduit for all work rather than any existing conduit. The period of performance is 150 days with the potential for an administrative notice to proceed to allow for material lead times. The third floor of one building is excluded from the scope due to an ongoing renovation. Bids are due by May 3, 2021 at 3:30 PM Eastern with the bid opening to take place virtually on May 4, 2021 at 10:00 AM Eastern. Responder 5000 version 4.x and Responder Enterprise version SR3 are approved nurse call systems that meet the opportunity's technical requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 02T-130.pdf | ||
| Site Visit Attendance Sheet.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contract Opportunity Special Notice
PRODUCT SERVICE CODE
SUBJECT
CONTRACTING OFFICE'S
ZIP-CODE
SOLICITATION NUMBER
ARCHIVE
DAYS AFTER THE RESPONSE DATE
RECOVERY ACT FUNDS
NAICS CODE
CONTRACTING OFFICE
ADDRESS
POINT OF CONTACT
(POC Information Automatically Filled from User Profile Unless Entered)
DESCRIPTION
See Attachment
AGENCY'S URL
URL DESCRIPTION
AGENCY CONTACT'S EMAIL
ADDRESS
EMAIL DESCRIPTION
GENERAL INFORMATION
ADDITIONAL INFORMATION
* = Required Field Contract Opportunity Special Notice
Z1DA
659-20-201: Nurse Call (VA-21-00042272) 28144 36C24621B0004 N 541519 Department of Veterans Affairs Network Contracting Office 6 1601 Brenner Ave Salisbury NC 28144 Sean Cosby sean.cosby@va.gov sean.cosby@va.gov Amendment attached.
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND
ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID
CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR
AND DATE SPECIFIED MAY
is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:
(Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by lett er or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED
INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA -
FAR (48 CFR) 53.243
(Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE
CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 659-20-201 Department of Veterans Affairs Network Contracting Office 6 1601 Brenner Ave Salisbury NC 28144
To all Offerors/Bidders
36C24621B0004
X x x x The purpose of this amendment is to answer questions from the RFI period of this solicitation.
Questions and answers are attached on the following page.
Bid due date: May 3 rd 2021 1530 Bid Opening: May 4th, 2021 (Virtual) meeting invite will be provided to all bidders via email prior to bid opening.
1. Specs include Glovebag Asbestos Abatement but no qualities or locations are shown. Is there Asbestos Abatement on this project? We have asbestos in the specs to just to cover all of our bases. Do not see any asbestos abatement with the work they are doing.
1. Period of performance is 150 days Submittals and lead time for material as well as phasing, access and coordination with Nurse Admin will take time. Would the VA entertain an Administrative NTP after award till Material arrives then begin the 150 day Period of Performance? An admin NTP can be issued with request from contractor and planning with contracting.
1. During the walk through it was mentioned some of the work areas on the current plans were going to be deleted. Please advise. Part of the 3rd floor of building 2 is already under construction for a modernization project, so those rooms will not require upgrades in the Nurse Call system. (see attached drawing)
1. During the walk through there was some discussion of conduit that might be available for use on this project. Is the conduit identified or should we include new conduit for all work? You should include new conduit for all your work.
1. The response due date on the beta.sam.gov site, https://beta.sam.gov/opp/25ab04deb65d44f3b92148b5359b9ff9/view, states May 03, 2021 03:30 pm EDT and the Sources Sought notice states May 4, 2021, at 10:00 a.m. Can you confirm the bid response due date? Bids are due 5/3/21 at 1530 to the email address sean.cosby@va.gov. The actual bids will be opened online via TEAMS or Webex(invites will be sent to all bidders prior) 5/4/21 at 1000.
1. In reference to the requirement “E. Nurse call system must be One-VA Technical Reference Model (TRM) approved. More information can be found at: www.va.gov/trm” on page 435 of the 20-091+CD+ReplNrsCallSpecs+20210210 document in 1.9 PORJECT SCOPE OF WORK, Rauland Responder 5 (manufacturer release T17) has been listed as a DIVEST status by the VA Office of Information and technology. https://www.oit.va.gov/Services/TRM/ToolPage.aspx?tid=9735# As a result of the DIVEST status, all projects currently utilizing the technology/standard must plan to eliminate their use of the technology/standard. Responder 5 is scheduled to move to UNAPPROVED status in TRM April 1, 2022. Because the interconnectivity requirements in the solicitation potentially expose other clinical system to security issues, will the facility accept OR EQUAL bids as the Rauland Responder 5 nurse call system is currently in a divested TRM status and not allowed to be procured or operated in a VAMC? Responder 5000 version 3 is in the divest stage but version 4.x is approved. For Responder Enterprise version 5.0 is unauthorized, several versions are in the divest stage and version SR3 is approved.
Responder 5000
| <Past |
| CY2020 |
| CY2021 |
| CY2022 |
| Future> |
| Release |
| Q1 |
| Q2 |
| Q3 |
| Q4 |
| Q1 |
| Q2 |
| Q3 |
| Q4 |
| Q1 |
| Q2 |
| Q3 |
| Q4 |
| 3 |
| Approved w/Constraints |
[1, 2, 3] Approved w/Constraints [1, 2, 3] Approved w/Constraints [1, 2, 3] Approved w/Constraints [1, 2, 3] Divest [3, 4, 5] Divest [3, 4, 5] Divest [3, 4, 5] Divest [3, 4, 5] Divest [3, 4, 5] Divest [3, 4, 5] Divest [3, 4, 5] Divest [3, 4, 5]
| 4.x |
| Approved w/Constraints |
[1, 2, 3] Approved w/Constraints [1, 2, 3] Approved w/Constraints [1, 2, 3] Approved w/Constraints [1, 2, 3] Approved w/Constraints [3, 4, 5] Approved w/Constraints [3, 4, 5] Approved w/Constraints [3, 4, 5] Approved w/Constraints [3, 4, 5] Approved w/Constraints [3, 4, 5] Approved w/Constraints [3, 4, 5] Approved w/Constraints [3, 4, 5] Approved w/Constraints [3, 4, 5]
1.
1. Responder Enterprise
| <Past |
| CY2020 |
| CY2021 |
| CY2022 |
| Future> |
| Release |
| Q1 |
| Q2 |
| Q3 |
| Q4 |
| Q1 |
| Q2 |
| Q3 |
| Q4 |
| Q1 |
| Q2 |
| Q3 |
| Q4 |
| 5.0 |
| Unapproved |
| Unapproved |
| Unapproved |
| Unapproved |
| Unapproved |
| Unapproved |
| Unapproved |
| Unapproved |
| Unapproved |
| Unapproved |
| Unapproved |
| Unapproved |
| T15 |
| Divest |
[4, 5, 6] Divest [4, 5, 6] Divest [4, 5, 7] Divest [4, 5, 7, 8] Divest [7, 8, 9, 10] Divest [7, 8, 9, 10]
| Unapproved |
| Unapproved |
| Unapproved |
| Unapproved |
| Unapproved |
| Unapproved |
| T16 |
| Divest |
[4, 5, 6] Divest [4, 5, 6] Divest [4, 5, 7] Divest [4, 5, 7, 8] Divest [7, 8, 9, 10] Divest [7, 8, 9, 10]
| Unapproved |
| Unapproved |
| Unapproved |
| Unapproved |
| Unapproved |
| Unapproved |
| T17 |
| Approved w/Constraints |
[4, 5, 6] Approved w/Constraints [4, 5, 6] Approved w/Constraints [4, 5, 7] Divest [4, 5, 7, 8] Divest [7, 8, 9, 10] Divest [7, 8, 9, 10] Divest [7, 8, 9, 10] Divest [7, 8, 9, 10] Divest [7, 8, 9, 10]
| Unapproved |
| Unapproved |
| Unapproved |
| SR3 |
| Unapproved |
| Unapproved |
| Unapproved |
| Approved w/Constraints |
[4, 5, 7, 8] Approved w/Constraints [7, 8, 9, 10] Approved w/Constraints [7, 8, 9, 10] Approved w/Constraints [7, 8, 9, 10] Approved w/Constraints [7, 8, 9, 10] Approved w/Constraints [7, 8, 9, 10] Approved w/Constraints [7, 8, 9, 10] Approved w/Constraints [7, 8, 9, 10] Approved w/Constraints [7, 8, 9, 10]
See attached document: 02T-130.
See attached document: Site Visit Attendance Sheet.
File details come from the government source that posted it. Updated .