This is a Presolicitation Notice for HVAC upgrades at the VA Loch Raven location. The Department of Veterans Affairs Veterans Health Administration is seeking contractor services for upgrades at the VA Maryland Health Care System, Building 1 Community Living Center (CLC) on the Loch Raven Campus in Baltimore, Maryland (21201). The solicitation number is 36C24527Q0061, with a response deadline of December 14, 2026, at 8:00 a.m. Eastern Time. This is a small business set-aside under NAICS code 561210 with Product Service Code J065. The period of performance is 90 calendar days.

The contractor must provide all material, labor, equipment, and supervision to complete the following primary deliverables: upgrade exhaust fans and replace Air Handling Unit (AHU-B) in the Covid Ward 2nd floor B wing; replace and upgrade exhaust fans EF-1A and EF-1B for higher CFM outputs; install and assess heat tracing for the chiller system with a 20-amp GFPE circuit breaker installation; replace cooling coils in the kitchen basement AHU-E; replace the fan motor rated for 60Hz operation; and replace the Variable Frequency Drive (VFD) with ABB manufacturer equipment. The contractor must coordinate with VA's Johnson Controls International (JCI) contract for Building Automation System (BAS) integration and comply with all VA facility guidelines, including Infection Control Risk Assessment (ICRA) and Pre-Construction Risk Assessment (PCRA). Testing, Adjusting, and Balancing (TAB) must be performed by a certified TABB or ANAB-accredited vendor after HVAC modifications, with results documented in a report. The contractor must provide warranty letters, Operations and Maintenance manuals, shop drawings, and training to the VA, with all deliverables received prior to final payment. Contractor must provide itemized costs for each deliverable, track quantities on pay applications, and obtain written authorization from the Contracting Officer for any work outside the contract scope. Utility and HVAC shutdowns require at least 14 days written notice to the facility. The Point of Contact is Contract Officer Keysha Gorman at Keysha.Gorman74@va.gov or 410-637-1513.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Presolicitation Notice Presolicitation Notice

SUBJECT*
HVAC upgrades at VA Loch Raven location

GENERAL INFORMATION

CONTRACTING OFFICE’S ZIP CODE*
21201
SOLICITATION NUMBER*
36C24527Q0061
RESPONSE DATE/TIME/ZONE
12-14-2026 8am EASTERN TIME, NEW YORK, USA
ARCHIVE
30 DAYS AFTER THE RESPONSE DATE
SET-ASIDE
SBA
PRODUCT SERVICE CODE*
J065
NAICS CODE*
561210
PLACE OF PERFORMANCE
Department of Veterans Affairs

VAMC

10 N Greene St

Baltimore MD

POSTAL CODE
21201
COUNTRY
USA

CONTACT INFORMATION

CONTRACTING OFFICE ADDRESS
Department of Veterans Affairs

VAMC

10 N Greene St Baltimore MD 21201

POINT OF CONTACT*

Contract Officer Keysha Gorman Keysha.Gorman74@va.gov 410-637-1513

ADDITIONAL INFORMATION

AGENCY’S URL
https://www.maryland.va.gov/locations/Loch_Raven_VA_Medical_
URL DESCRIPTION
Loch Raven VA Medical Center
AGENCY CONTACT’S EMAIL ADDRESS
Keysha.Gorman74@va.gov
EMAIL DESCRIPTION
Keysha Gorman

DESCRIPTION

The contractor will provide all material, labor, equipment, and supervision necessary to complete the above-named project at the VA Maryland Health Care System (VAMHCS), Building 1 Community Living Center (CLC) of the Loch Raven Campus.

1. Primary Deliverables and Project Requirements

0. Covid Ward 2nd floor B wing

0. Upgrade exhaust fans

0. Air Handling Unit (AHU-B) located in attic

0. Replace and upgrade EF-1A and EF-1B for higher CFM outputs

0. Install heat tracing for chillers

1. Wiring and junction box located in room G-15. Chiller located outside CLC in the pit behind the service road.

1. Assess current heat tracing for chill water line. Complete and terminate existing heat tracing wiring to an emergency electrical panel in G-17 in coordination with the VA. Panel selection is TBD.

1. Install a 20-amp GFPE circuit breaker for the heat tracing to the panel selected by the VA.

0. Kitchen basement

1. Replace cooling coil(s)

0. AHU-E located in attic.

1. Replace fan motor

1. AHU-E located in attic. AHU has one fan.

1. New motor must be rated for and capable of sustaining a fan speed of 60Hz.

1. Replace Variable Frequency Drive (VFD)

2. VFD located in the attic and attached to the AHU

2. Replace VFD in kind with Manufacturer (ABB)

0. Controls Integration & Coordination

2. VA has an existing contract with Johnson Controls International (JCI).

0. The contractor shall coordinate with the COR and Facility Maintenance to satisfy necessities for the facility’s existing Building Automation System (BAS) controls corresponding to all new work.

0. Contractor will replace/reinstall or provide new hardware or connections for BAS monitoring when required to complete BAS programming or integration. This can include control wiring, modulators, switches, routing, existing equipment etc. These requirements are determined on a case-by-case basis.

0. Testing Adjusting & Balancing (TAB)

3. TAB shall occur after HVAC modifications are made. It must be performed by a certified vendor/contractor per TABB and/or other ANAB accredited programs for standard industry HVAC system performance compliance

3. Contractor shall provide notice to and request attendance of the COR and/or other COR-approved VA representation prior to TAB.

3. A report on the TAB results must be delivered to the COR.

2. TAB report will be reviewed and approved by the VA prior to contractual closeout and final payment

0. Warranty, Operations & Manuals (O&Ms) and Shop Drawings

4. Contractor and/or subcontractor shall provide a warranty letter including point of contact, to the VA.

0. Warranty is based on workmanship, material and equipment.

0. Duration of warranty starts after acceptance and use of new equipment & components

4. O&Ms for all new equipment and other components requiring preventative maintenance shall be provided to the VA.

1. All O&M documents must be received by the VA prior to contractual closeout and final payment

1. Contractor shall provide training to the VA.

4. Shop Drawings

2. All layout changes and new equipment shall be updated in as-builts, shop drawings, manufacturer diagrams, details, where applicable. Due to the nature of the contract, this requirement will be determined based on off application by the COR at completion of work. If no applicable documents are required, then the COR will opt for omission.

1. Assumptions

1. Contractor to provide a cost/unit for each of the deliverable items above and use the total amounts provided for their proposal. Contractor to track the quantities used on their pay applications with any amounts left over being returned to the government after final payment. All deliverables must be received by the VA prior to final payment.

0. Line items will be tracked in every pay application. Financial progress for a line item will be cross-referenced with the corresponding item’s physical progress and/or completion status. Misrepresentation of a line item’s financial progress may result in rejection from the COR and require the contractor to resubmit the pay application with revision(s).

0. Pay applications must be submitted with a total amount not to exceed the Purchase Order (PO) balance. A contract modification from the Contracting Officer (CO) is required for payment application submissions exceeding the PO balance.

1. Additional work outside of the contract and contractual supplement documents (provided drawings, as-builts, details, existing product information, etc) require authorization and written execution from the CO.

1. Any additional work (quantified via labor, material or equipment) performed/provided by the contractor without guidance from the VA or direction from the CO shall not be included in payment applications. The contractor is committed to working at their own expense and risk under this condition.

1. Supplemental contractual and scope of work include existing as-builts, details and compliance for VA guidelines, federal & state guidelines, applicable codes, etc.

2. VA can provide the contractor with additional available drawings and other documentation. These are considered items pertaining to the original contract’s scope of work

1. Standard Inclusions & General Compliance

2. Contractor is responsible for cleaning the work area of trash regardless of if it is their trash or not. This includes areas that other entities may have access to like the attic and mechanical spaces. Contractor is responsible for stewardship of work area and compliance with VA medical facility guidelines. Contractor will adhere to VA-granted permitting requirements and industry standard safety practices including but not limited to:

0. Infection Control Risk Assessment (ICRA)

0. Pre-Construction Risk Assessment (PCRA)

0. Hot or burn work

0. Confined space entry work (if applicable)

0. Lock out tag out (LOTO) procedures

0. PPE

2. Parking at the Loch Raven campus is limited and contractors are subject to facility guidelines for locations of contractor vehicles. Guidance for contractor parking is enforced by the COR, Facility Maintenance Supervisor, Campus Manager, and Deputy Medical Director.

1. Parking outside the campus boundary is not in the VA’s jurisdiction

2. The contractor shall coordinate with the facility prior to work that impacts patient care such as shutting down A/C, heating, power or other utilities.

2. Utility and HVAC shutdowns require at least a 14-day written request to the facility per the VA’s internal Standard Operating Procedure.

Period of performance is 90 calendar days.