36C24525R0050_2.docx
DOCX document 474 KB Posted
- Solicitation number
- 36C24525R0050
About this file
This document is a solicitation for a construction project to replace the boiler plant water main at the Perry Point VA Medical Center in Maryland. The project, identified as Solicitation Number 36C24525R0050 and Project 512A5-25-002, is a small-scale construction effort set aside exclusively for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) with a project magnitude between $250,000 and $500,000. The contract requires the contractor to furnish all labor, tools, materials, equipment, and supervision to replace the water main, prepare and paint a 500,000-gallon elevated domestic water storage tank, and make minor piping and system configuration improvements.
Key project details include a site visit scheduled for April 29, 2025, at 11:00 hrs EST, with all proposals due by May 16, 2025, at 11:00 AM EST. The contract period is set from May 30, 2025, to August 28, 2025, with a 90-day completion timeline. The project will take place at the Perry Point VAMC in Maryland, and contractors must be registered in SAM.gov and veterans.certify.sba.gov. The North American Industry Classification System (NAICS) code is 236220, with a size standard of $45 million, and the Product Service Code is Z2NE for repair or alteration of water supply facilities.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| VAAR 852.219-75.pdf | ||
| 36C24525R0050 0001_1.docx | DOCX document | |
| Specifications Combined.pdf | ||
| Drawing 1 - New Work Plan - Exterior_Rev 1.pdf | ||
| S02_Map to Site Visit Meeting Point_04.02.2025.docx | DOCX document | |
| Drawing 2 - New Work Plan - Interior_Rev 1.pdf | ||
| 36C24525R0050_2.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUBJECT*
Project 512A5-25-002, Replace Boiler Plant Water Main at Perry Point VAMC, MD
GENERAL INFORMATION
| CONTRACTING OFFICE’S ZIP CODE* |
| 25405 |
| SOLICITATION NUMBER* |
| 36C24525R0050 |
| RESPONSE DATE/TIME/ZONE |
| 05-23-2025 11:00 EASTERN TIME, NEW YORK, USA |
| ARCHIVE |
| 30 DAYS AFTER THE RESPONSE DATE |
| RECOVERY ACT FUNDS |
| N |
| SET-ASIDE |
| SDVOSBC |
| PRODUCT SERVICE CODE* |
| Z2NE |
| NAICS CODE* |
| 236220 |
| CONTRACTING OFFICE ADDRESS |
| Department of Veterans Affairs |
VAMC (613)
VISN 5 Contract Satellite Office 510 Butler Avenue, Building 306A Martinsburg WV 25405
POINT OF CONTACT*
Contracting Officer Liana J Holland Liana.Holland@va.gov No phone calls - emails only
PLACE OF PERFORMANCE
| ADDRESS |
| Perry Point VAMC |
Department of Veterans Affairs
361 Boiler House Road
Perry Point MD
| POSTAL CODE |
| 21902 |
| COUNTRY |
| USA |
ADDITIONAL INFORMATION
| AGENCY’S URL |
| https://www.va.gov |
| URL DESCRIPTION |
| Agency Homepage |
| AGENCY CONTACT’S EMAIL ADDRESS |
| Liana.Holland@va.gov |
| EMAIL DESCRIPTION |
| CO Email Address |
DESCRIPTION
Combined Synopsis/Solicitation Notice Combined Synopsis/Solicitation Notice Please see the solicitation and all attachments
| *= Required Field |
| Combined Synopsis/Solicitation Notice |
Combined Synopsis/Solicitation Notice
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C24525R0050
X 04-08-2025
TBD
512A5-25-002
Department of Veterans Affairs
VAMC (613)
VISN 5 Contract Satellite Office 510 Butler Avenue, Building 306A Martinsburg WV 25405 Liana J Holland (Contracting Officer) Network Contracting Office 5
510 Butler Avenue Martinsburg WV 25405 Liana J Holland 304-263-0811 x 7611 This project is a Construction Project to Replace Boiler Plant Water Main at the Perry Point VAMC, Perry Point, MD.
The contractor shall furnish all labor, tools, materials, equipment, supplies, and supervision to perform work as described in the statement of work and as required by the contract drawings and specifications. This contract will prepare and paint the existing 500,000 gallon elevated domestic water storage tank, as well as make minor piping and system configuration improvements in accordance with the Statement of Work (SOW) and specifications attached hereto.
The Contractor will be responsible to coordinate and schedule work to minimize to short duration and shall be expected to plan work typically during duty hours of 7 AM to 3:30 PM eastern time except as noted in the general conditions and as approved by the Contracting Officer.
The NAICS Code for this procurement is 236220.
Size standard: $45 million.
Magnitude of construction is between $250,000 and $500,000.
This is an SDVOSB Set-Aside. All Contractors are required to be registered with www.sam.gov; SDVOSB's and VOSB's are required to be registered with https://veterans.certify.sba.gov/. All statuses will be verified.
A site visit is scheduled for Tuesday April 29th, 2025 at 11:00hrs EST. The meeting place will be in the parking lot of building 321 (Chiller Plant), Perry Point VAMC, Perry Point, MD 21902-1103.
This will be the only site visit date for the project. Absolutely no other visits will be scheduled.
All Requests for Information (RFI's) must be emailed to Liana J Holland at liana.holland@va.gov no later than 11:00hrs on Friday May 2nd, 2025. No proposal extensions will be granted due to late RFI submissions.
All proposals MUST be received by 11:00hrs (11am) EST on Friday May 16th, 2025.
***********************************IMPORTANT SUBMISSION INFORMATION - PLEASE READ:************************************** VAAR 852.219-75 MUST be completed and signed with your proposal. Failure to complete and submit this clause will render your proposal incomplete and therefore ineligible for award.
X X
52.211-10 X
15 days after award
11:00
EDT
05-23-2025 X
Page 1 of
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
Department of Veterans Affairs
VAMC (613)
VISN 5 Contract Satellite Office 510 Butler Avenue, Building 308B Martinsburg WV 25405
PAYMENT WILL BE MADE BY
FSC e-Invoice Payment Invoice must be submitted electronically http://www.fsc.va.gov/einvoice.asp http://www.fsc.va.gov/einvoice.asp
Liana J Holland
VA-VHA-RPOE-2025-0010
Page 1 of Table of Contents
| PART I - THE SCHEDULE | 4 |
| SECTION A - SOLICITATION/CONTRACT FORM | 4 |
| A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 4 |
| A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK | 5 |
| A.3 SOW | 8 |
| A.4 PRICE/COST SCHEDULE | 21 |
| ITEM INFORMATION | 21 |
| A.5 DELIVERY SCHEDULE | 22 |
| A.6 52.201-1 ACQUISITION 360: VOLUNTARY SURVEY (SEP 2023) | 22 |
| A.7 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (NOV 2021) | 23 |
| A.8 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021) | 24 |
| A.9 52.204-26 COVERED TELECOMMUNICATIONS EQUIPMENT OR SERVICES—REPRESENTATION (OCT 2020) | 27 |
| A.10 52.204-29 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—REPRESENTATION AND DISCLOSURES (DEC 2023) | 27 |
| A.11 52.204-30 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—PROHIBITION (DEC 2023) | 29 |
| A.12 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021) | 33 |
| A.13 52.216-1 TYPE OF CONTRACT (APR 1984) | 35 |
| A.14 52.219-28 POSTAWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JAN 2025) | 35 |
| A.15 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 38 |
| A.16 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020) | 39 |
| A.17 52.223-20 AEROSOLS (MAY 2024) | 39 |
| A.18 52.223-21 FOAMS (MAY 2024) | 40 |
| A.19 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022) | 41 |
| A.20 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) | 45 |
| A.21 52.233-2 SERVICE OF PROTEST (SEP 2006) | 46 |
| A.22 52.236-4 PHYSICAL DATA (APR 1984) | 47 |
| A.23 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 48 |
| A.24 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 48 |
| A.25 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 48 |
| A.26 52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020) | 49 |
| A.27 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2025) | 49 |
| A.28 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984) | 54 |
| A.29 SUPPLEMENTAL INSURANCE REQUIREMENTS | 56 |
| A.30 IT CONTRACT SECURITY | 57 |
| A.31 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022) | 67 |
| A.32 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018) | 67 |
| A.33 VAAR 852.204-70 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (MAY 2020) | 67 |
| A.34 VAAR 852.204-71 INFORMATION AND INFORMATION SYSTEMS SECURITY (FEB 2023) | 67 |
| A.35 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018) | 76 |
| A.36 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION) | 77 |
| A.37 VAAR 852.223-71 SAFETY AND HEALTH (SEP 2019) | 80 |
| A.38 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 81 |
| A.39 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018) | 82 |
| A.40 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018) | 83 |
| A.41 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019) | 83 |
| A.42 VAAR 852.236-72 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 2019) | 84 |
| A.43 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019) | 85 |
| A.44 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019) ALTERNATE I (APR 2019) | 85 |
| A.45 VAAR 852.239-75 INFORMATION AND COMMUNICATION TECHNOLOGY ACCESSIBILITY NOTICE (FEB 2023) | 86 |
| A.46 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020) | 87 |
| A.47 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) | 88 |
| A.48 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019) | 88 |
| A.49 VAAR 852.246-75 WARRANTY OF CONSTRUCTION—GUARANTEE PERIOD SERVICES (OCT 2018) | 89 |
| A.50 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018) | 90 |
| A.51 VAAR 852.252-70 SOLICITATION PROVISIONS OR CLAUSES INCORPORATED BY REFERENCE (JAN 2008) | 93 |
A.3 SOW
Scope of Work Station Level Project No. 512A5-24-002 Replace Boiler Plant Water Main
1. OVERVIEW —
1.1 Government Agency Department and Address:
VA Maryland HealthCare System – VISN5 – Perry Point VAMC – Perry Point, MD
| 1.2 | Project Title, Number and Location: |
| Project Title: | Replace Boiler Plant Water Main |
Project Number: 512A5-25-002
1.3 Scope of Work
In the event that the primary source of domestic water to the Boiler Plant and Chiller Plant is required to be shut-off, a secondary water main is required to maintain a domestic water source. Provide all labor, supervision, travel, equipment, tools, materials, inspection/testing services, and legal disposal of waste materials to install a new water main to the Boiler Plant and Chiller Plant at the Perry Point VA Medical Center. Additionally, cap and abandon in-place the existing water main and backflow preventer within the Chiller Plant.
Project Intent
· Provide locked chain-link fencing as required to prevent unauthorized access to work site hazards. Coordinate material laydown area, equipment storage, and work site layout with COR.
· Survey and mark all existing subsurface utility locations prior to digging.
· Coordinate temporary utility plan and campus utility shutdowns (at least 2 weeks in advance) with the COR and VA Maintenance and Operations staff.
· Tap into adjacent combined system water main running parallel to Avenue D. Water supply to the Perry Point VAMC is provided via an onsite water treatment and pumping facility.
· Excavate access pits as required to expose existing 8-inch water pipe main along Avenue D to install new piping lateral to the Boiler/Chiller Plant.
· Cut-in and install a new 8” x 6” reducing tee into existing water main. Provide bedding and concrete thrust block.
· Install new piping stub, fused MJ Fittings, MJ Adapters w/ DI Back-Up rings & nuts & bolts, and new 6-inch Resilient Seat Gate Valve with 2” operating nut. Valve shall be manufactured in accordance with AWWA Standard C515. Provide bedding for new valve assembly. Connect to new water lateral piping. Install new valve box and cap as required to match finish grade.
· Provide and install approximately 400 linear feet of new AWWA C906 6-inch DIPS, fused, DR 11 (200 psi), HDPE water supply piping and associated fittings, color Black with Blue Stripe, between the existing 8-inch water main and pipe bend location required to transition to the Boiler/Chiller Plant. New HDPE shall be affixed with locating tracer tape. Minimum bury depth shall be no less than 4-feet below finish grade. See drawings for layout plan. Contractor shall verify actual length and exact configuration in field.
· Provide and install approximately 40 linear feet of new 6-inch, ductile iron water supply piping and associated connection fittings (flanged or grooved), between the pipe bend required to transition to the Boiler/Chiller Plant. Connect to new HPDE lateral pipe. Contractor shall verify actual length and exact configuration in field. See drawings for layout plan.
· Core-drill existing concrete foundation for new piping penetration. Install new ductile iron water pipe with rubber link-seals on each side of foundation penetration. Coordinate size of penetration to fit applicable link seal.
· Install ductile iron water supply piping to a point no less than 1 feet within the building interior to which new service is to continue and make connections thereto. Provide 150# ANSI B16.5 flange connection with EPDM gasket and bolt set at end of supply pipe once it enters building for connection to new water supply piping.
· Where new 6-inch water main enters building, install approximately 400 linear feet of new 6-inch, stainless steel, ASTM A312, schedule 10, insulated water supply piping and associated appurtenances (double backflow preventors, valves, and fittings, gauges) as depicted on the design drawings. New water supply piping shall be installed along ceiling of building, utilizing any existing pipe hangers where possible. Contractor shall verify actual length and exact configuration in field.
· At the 4-inch portion of the 6” x 4” tee, install approximately 160 linear feet of new 4-inch, copper, Type K, water supply piping and associated appurtenances (double backflow preventors, valves, fittings, and gauges) as indicated on the design drawings. Contractor shall verify actual length and exact configuration in field.
· Provide and install two laterals off of the new 4-inch water supply piping as indicated on the design drawing:
· Install approximately 50 linear feet of new 4-inch, copper, Type K, insulated water supply piping and terminate with a flanged gate valve for the VA to connect to the existing chilled water make-up. Contractor shall verify actual length and exact configuration in field.
· Install approximately 50 linear feet of new 4-inch, copper, Type K, water supply piping and terminate with a flanged gate valve for the VA to connect to the existing cooling towers. Contractor shall verify actual length and exact configuration in field.
· Install new gate valve after laterals. Reduce new 4-inch supply line to 1-inch and tie-in new 1-inch, copper, Type K, insulated water supply line (approximately 40 feet) into existing 1-inch water supply line above Chiller Plant’s break room.
· Cut-in and install a new 6-inch tee into existing water main entering the Boiler Plant and finish connecting the new 6-inch water main and associated appurtenances (double backflow preventors, valves, fittings, and gauges) as depicted on the design drawings.
· Following installation of new water main, remove and properly dispose of existing 4-inch backflow preventer located in the Chiller Plant’s Break Room.
· Cap and abandon in-place existing water main located in the Chiller Plant’s Break Room.
· Coordinate final connection tie-in location with COR and facility M&O.
· Interior piping shall be insulated with 1” wall fiberglass, All Service Jacket.
· Install formed concrete thrust blocks at all piping tees and bends.
· All HPDE pipe butt connections and fittings shall be fused.
· All new piping and valve components shall be certified for use with potable drinking water service.
· All new piping shall be flushed, pressure tested and disinfected prior to putting new supply into service.
· Backfill and compact soil subgrade, place topsoil, and seed disturbed vegetated areas.
1.4 Work Items Under this Task Order
Offers are to submit proposals based on the project specifications and drawings provided under the project solicitation. The resulting total bid amount shall then be broken down item by item for review of quantities, unit costs and labor costs.
Contractor shall make arrangements to visit the site to survey existing conditions and to determine the methods of the work to be performed prior to submitting proposal.
Work items under this task order include the following but is not limited to:
· Complete all demolition, repair, and replacement work as detailed in the attached construction drawings. All work and materials shall be in accordance with the attached construction specifications. Contractor shall be responsible for adherence to all VA and OSHA construction safety requirements pertaining to the project scope as described in the project drawings and specifications.
· Unless noted otherwise, all new surface repair work shall match the existing adjacent work as much as practical.
· Work Site Protection and Administration shall be included.
· Warranty on new work shall be good for a period of 1 year from date of completion per FAR unless otherwise stated.
· Removal and Disposal and/or recycling of all demolished building materials and construction waste per applicable regulations shall be included. Manifests/disposal/recycle tonnage must be summarized and reported to the COR.
· Hazmat materials shall be removed as shown in work area. Contractor to adhere to OSHA “Lead in Construction” standard (29 CFR 1926.62) for residual lead paint that may remain. All hazardous material manifests and Land Disposal Restrictions MUST be signed by an authorized VA representative before regulated material may be transported off-site. Contractor is responsible for all supplemental testing required (ie. TCLP) to profile and segregate waste streams.
· Contractor shall be responsible for all material deliveries, storage, and the coordination of deliveries. Over-height and over-weight restrictions are in place in one or all of the site access points.
· Contractor responsible for all temporary site operations facilities, including temporary utility connections, temporary worker restrooms/port-o-johns, field office, storage areas/CONEX boxes, etc. Contractor shall provide total site security measures including locking 8ft-high chain-link fence around entire site complete with privacy screening slats.
· Contractor shall be responsible for providing and maintaining all aspects of construction site safety including but not limited to:
· Fire Extinguishers
· Construction site fencing and access control
· Refer to Specification 01 00 00 General Requirements for all requirements pertaining to the project including the availability and usage of government provided utilities.
· Refer to specification 01 33 23 Shop Drawings, Product Data, and Samples for project submittal requirements.
1.5 Additional Terms and Conditions
1.5.1 Schedule
Please review specification section 01 32 16.15 for requirements for schedule. Please note that the contractor’s bid proposal provided at the time of bid due date shall require a draft CPM schedule. The intent is to proceed with submittals immediately after contract award, submittals for the long lead items shall be developed, provided, and reviewed.
A project Notice to Proceed (NTP) is planned to be issued roughly 30 days post award. Contractor shall mobilize onsite beginning construction within 15 days of NTP issue. The contractor shall have (90) Ninety calendar days to complete all work including closeout.
See below chart for NTP:
| ID |
| Milestone Task Description |
| Duration |
| Schedule |
Date Actual Date
| 1 |
| Project NTP |
| 1 Day |
| Award + 30 |
| 2 |
| Site Mobilization |
| 15 Days |
| NTP + 15 |
| 3 |
| Complete all work |
| 65 Days |
| NTP + 80 |
| 4 |
| Commissioning and Project Close-out |
| 10 Days |
| NTP + 90 |
1.5.2 Pricing and Payment
1.5.2.1 This project will be deemed complete when all of the required tasks outlined in this SOW are complete and function as intended by design; the work shall be completed within the areas defined in this document. The VA will complete a final walk through and inspection of all work before processing final payment.
1.5.2.2 The contractor may submit progress payment invoices according to the Contracting Officer’s specifications at intervals acceptable to the VA. These progress payments will be substantiated by the COR inspections and the daily logs submitted by the contractor. A schedule of values will need to be submitted and approved.
1.5.2.3 Progress payment invoices shall be sent via email to the COR for approval and payment.
1.5.2.4 Final payment will not be processed until final walk through, and approval is complete which includes all punch list items.
1.6 Construction Requirements
| 1.6.1 | The Contractor shall have the skills, availability, capacity and all other required resources required to complete the job on time without delay. |
| 1.6.2 | All site contractors shall have completed the Occupational Safety & Health Administration (OSHA) approved 10-hour construction safety training. |
| 1.6.3 | Mechanical and Plumbing contractors shall have technical training and demonstrable track records of working experience in construction, inspection, and testing of plumbing systems and related components in healthcare, industrial, educational, and commercial facilities. Contractor must hold a current license by the State of Maryland as a licensed Master Plumber/Gas Fitter or approved by COR. |
| 1.6.4 | All work is to shall be in compliance with local, state and federal rules and regulations, and VA technical standards. Compliance is to whichever rule or regulation is the most stringent. VA Master Specifications shall be used as the default when no specifications are issued and when a referenced specification is not found in the projects RFP package, they are at https://www.cfm.va.gov/til/. The intent of the default specifications is to furnish concise industrial and/or commercial standards for construction of Government facilities. If the Statement of Work does not address a specification for an element of the work, the default specification shall apply for the element of work as approved by COR. The omittance of a VA specification, does not relieve the contractor to perform required work under the base task order cost proposal. |
| 1.6.5 | Provide daily on-site project management to coordinate all building trades and provide liaison for construction and VA Project Engineering. General Foreman will be designated and be on-site at all times. |
| 1.6.6 | All employees of contractor shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and be restricted from unauthorized access. VA issued ID Badges shall be worn by all workers while within the campus boundaries. Contractor shall make all necessary arrangements to obtain the required badging prior to commencement of work. VA issued ID Badges shall be worn by all workers at all times. |
| 1.6.7 | Follow all Infection Control Risk Assessment (ICRA) guidelines for dust control during all construction and demolition work. A construction dust “Risk Assessment” will be conducted by the Medical Center’s Infection Control Nurse. Temporary “dust” barriers will be installed based on this assessment. Bi-weekly inspections of barriers and work areas will be conducted by Infection Control Nurse, Safety Manager, and COR to enforce implementation of risk assessment. |
| 1.6.8 | Follow Interim Life Safety Measures (ILSM). Any series of Operational Actions taken to temporarily reduce hazards posed by Life Safety deficiencies which have been created by demolition, renovation, or construction works, and which are to remain in place and in effect for duration of Contract work. Provide ILSM where fire protection, fire suppression or smoke/fire partitions will be shut down or rendered ineffective during construction. Coordinate with VA safety office through COR. ILSM must be posted outside work area at all times. |
| 1.6.9 | All equipment and materials shall be approved prior to being brought on job site. |
| 1.6.10 | Normal work hours are 7:00am to 3:30pm, Monday to Friday. Contractor shall make prior arrangements to work earlier or later with COR. Also, contractor shall make arrangements for subcontractors to work in secured areas. VA will not grant access to subcontractors, it is the responsibility of the contractor. |
| 1.6.11 | Daily logs shall be submitted to the COR the Monday following each week worked. |
| 1.6.12 | When using special keys for access to roof, mechanical and electrical areas, doors must be kept closed and locked while in such spaces. |
| 1.6.13 | Contractor must obtain a burn permit from VA Safety Office / Fire Dept prior to any welding, flame cutting, soldering work, and burning. |
| 1.6.14 | The work performed shall be in a professional environment, employees must conduct themselves accordingly. Employees shall not use abusive language, carry firearms, or bring alcoholic beverages on site. Employee's dress code shall consist of normal work uniform. Shirts must be worn at all times. |
| 1.6.15 | Contractor shall provide general clean up to construction area daily to the satisfaction of the COR. |
| 1.6.16 | Remove demolished equipment and restore site. |
| 1.6.17 | Hospital smoking policy (NO SMOKING ON CAMPUS). |
| 1.6.18 | OSHA and VA CONSTRUCTION SAFETY STANDARDS will be enforced. Contractor Supervisor must have 30-hour OSHA Construction Safety course. All contractor employees must have 10-hour OSHA Construction Safety course. |
| 1.6.19 | All fire stop material must be red. |
| 1.6.20 | Any expansion bolts/anchors must be tightened with a torque wrench per OEM. |
| 1.6.21 | For quality control, the individual may not carry dual roles in the construction project. The VA shall require a person with QC/QA background that there only role is to validate that the construction meets or exceeds requirements of the contract. This person will generate a final punch list and provide to the COR. Then the COR will schedule review the completed job with contractor or/and code officials to generate a punch list. The QC inspector shall provide summary to the COR on a weekly basis with inspection sheets and corrections or commented. |
2.0 Safety and Environmental Precautions
| 2.1. | The Contractor shall comply with all applicable Federal, State and local legal requirements regarding workers health and safety. The requirements include but are not limited to, those found in Federal and State Occupational Safety and Health Act (OSHA) statutes and regulations, such as applicable provisions of Title 29, Code of Federal Regulations (CFR) Parts 1910 and 1926. Contractor is solely responsible for determining the legal requirements that apply to activities and shall ensure safe and healthful working conditions for its employees. |
| 2.2. | Contractor shall assume the responsibility to guard against causing of fires and/or explosions and to protect Government Property. |
| 2.3. | The Contractor shall perform the work in a manner consistent with the area security and fire safety regulations especially with regard to exits and exit way access. Utility shutdowns shall not compromise security, communication or fire safety for occupants. Egress must be maintained for contract workers per OSHA. |
| 2.4. | No flammable liquids shall be stored or used in the medical center. |
| 2.5. | The necessary number and appropriate types of portable fire extinguishers are required per National Fire Protection Agency (NFPA) 10 and NFPA 241. |
| 2.6. | The Contractor shall receive from the station fire department a permit for all cutting, welding, and soldering. All permits shall be prominently displayed during all construction. Permits must be opened at the start of each activity and closed at the end of each workday. |
| 2.7. | All necessary precautions shall be taken by the contractor to prevent accidental operation of any existing smoke detectors or sprinkler heads. |
| 2.8. | Contractor shall be responsible for operational actions taken to temporarily reduce the hazard posed by life safety deficiencies created during and until completion of construction, as well as temporary construction partitions of non-combustible or limited combustible material that will not contribute to the development of spread of fire smoke tight and have smooth clean surface. |
| 2.9. | In order to provide for control of all environmentally hazardous materials arising from demolition and/or construction activities, the Contractor shall comply with all applicable environmentally hazardous material control and all applicable provisions of the Corps of Engineers’ Manual EM 385-1-1, “General Safety Requirements” as well as the specific requirements stated elsewhere in the Contract Documents. |
| 2.10. | All overhead lifts shall comply to VA requirements which may include off shift/day’s lifts (IE weekends) as scheduled and approved by COR. |
| 2.11. | Site mobilization area: The site mobilization area will be designated prior to the start of work. Area shall be fixed fence and be secured to allow access only to authorized personnel. Fence signs shall be installed to make general public aware. A job board with required permits, bulletins or site documentation shall be installed in area that can be visibly observed by the general public. Temporary walk path (stone or other means) shall be provided if contractor places office trailer in the area. No material tracking onto the sidewalk or roadways is allowed. Area shall be repaired with topsoil and hydroseed when weather conditions allow. No material shall be allowed to be wind blown off the site. Housekeeping of the area shall be performed daily or as required. Contractor is required for any snow removal and protection of assets. All material/equipment shall be covered and protected from weather elements. Sidewalk must always be accessible. Keys must be provided to the VA for any locked fences or other areas as deemed by the COR. |
3.0 Waste Disposal and Management
All waste will be properly handled and disposed of in an environmentally sound manner and will comply with local and federal guidelines. Keeping the premises free from debris is a key component to maintaining a safe work environment. Below are the types of waste and the process for each.
| 3.1 | General Non-Hazardous Waste |
| 3.1.1 | A construction project generates waste either from the parts that are removed or from the packaging of the new products being installed. The contractor shall ensure that all installation debris and product packaging is removed from the work area and placed in trash receptacles that the contractor provides. |
| 3.1.2 | This waste will be transported and disposed of by the contractor’s waste management company. |
| 3.1.3 | Comply with VA Master Specification 017419 Construction Waste Management. This specification identifies materials that MUST be recycled or reused during construction and demolition projects. Additionally, VHA requires that 50% of demolition debris be diverted from the solid waste stream. Contractor shall document all disposal records or recycling records, with quantity and destination of all waste streams. |
| 3.2 | Hazardous Waste (Includes but not limited to Lead and Lead-Based Paint Wastes) |
| 3.2.1 | The contractor must dispose of all universal wastes that does not remain intact as hazardous waste per EPA hazardous waste guidelines (40 CFR 260-299) and COMAR 26 Subtitles 13-18. The contractor must also dispose of all hazardous wastes per EPA hazardous waste guidelines (40 CFR 260-299) and COMAR 26 Subtitles 13-18. |
| 3.2.2 | All required paperwork such as hazardous waste profiles, hazardous waste manifests and land disposal restriction (LDR) forms that go with the hazardous waste manifests will be filled out by a MD licensed, hazardous waste subcontractor. The contractor will schedule and coordinate hazardous waste removal with VAMHCS Safety personnel. Hazardous waste manifests will be signed by ONLY a VAMHCS employee with DOT RCRA training certification (please contact VAMHCS GEMS Manager) and a copy provided to the VAMHCS GEMS Manager for the specific VAMHCS facility. Final signed manifests must be received by the VAMHCS from the hazardous waste Treatment, Storage, and Disposal Facility within 45 days of waste shipment per EPA 40 CFR 263.20-.25 as well as Code of Maryland Regulations (COMAR) 26.13.03.06. |
| 3.4.3 | Comply with EPA and MDE requirements for proper handling (such as bagging, sealing and recycling) Mercury-Containing Devices (may include but are not limited to thermometers, manometers, pressure stats, gauges, float or level controls, load meters, supply relays, phase splitters, and sink traps) per 40 CFR 273 and COMAR 26.13.02.08, 26.13.10.06, 26.13.10.09 and 26.13.10.20, 26.13.10.21 and 26.13.10.26 or latest requirements. |
| 3.4.4 | All hazardous waste expected as a result of renovation, demolition or construction activities (including but not limited to mercury-containing dental amalgam wastes, fluorescent bulbs, electrical devices that contain PCBs) must be properly managed and disposed in accordance with EPA and MDE requirements per EPA 40 CFR 260-299 as well as COMAR 26.13.02.01, 26.13.02.08, 26.13.10.20, 26.13.10.21 and 26.13.10.26 or latest requirements. |
| 3.4.5 | Records of hazardous waste disposal (such as manifests, hazardous waste profiles, LDRs) must be provided by approved waste transporter and signed by an approved VAMHCS Manifest signer from the VAMHCS Safety Department. All records provided to COR and VAMHCS GEMS Coordinator at VAMHCSGEMSProgram@va.gov |
| 3.4.6 | All hazardous chemicals that need to remain at the job site must be stored and handled in accordance with EPA; MDE; OSHA and NFPA requirements |
| 3.4.7 | Contractor must adhere to the lead in construction standard (29 CFR 1926.62(a) where lead is encountered in the course of work. If any lead is present, these regulations apply. The employer (contractor) must determine if employees will be exposed above the Permissible Exposure Limit for lead. |
E N D S C O P E O F W O R K
General Decision Number: MD20250112 03/14/2025
State: Maryland
Construction Type: Building
County: Cecil County in Maryland.
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).
|If the contract is entered |� Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |� The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $17.75 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2025. | |If the contract was awarded on|� Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |� The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $13.30 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours performing on that | | | contract in 2025. |
The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.
Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 03/14/2025
SAMD2024-032 12/01/2024
Rates Fringes
BALANCING TECHNICIAN.............$ 32.00 8.29
BRICKLAYER.......................$ 37.50 14.78
CARPENTER........................$ 37.08 25.48
CARPET LAYER.....................$ 34.12 14.86
ELECTRICIAN......................$ 52.64 20.46
ELEVATOR MECHANIC................$ 56.36 45.50
LABORER
AIR TOOL OPERATOR...........$ 25.28 7.87
ASPHALT PAVER...............$ 25.28 7.87
ASPHALT RAKER...............$ 22.23 2.46
BLASTER - DYNAMITE..........$ 25.28 7.87
BURNER......................$ 25.28 7.87
COMMON......................$ 22.23 2.46
CONCRETE PUDDLER............$ 22.23 2.46
CONCRETE SURFACER...........$ 25.28 7.87
CONCRETE TENDER.............$ 22.23 2.46
CONCRETE VIBRATOR...........$ 22.23 2.46
DENSITY GAUGE...............$ 22.23 2.46
FIREPROOFER - MIXER.........$ 22.23 2.46
FLAGGER.....................$ 22.23 2.46
GRADE CHECKER...............$ 22.23 2.46
HAND ROLLER.................$ 22.23 2.46
HAZARDOUS MATERIAL HANDLER..$ 25.28 7.87
JACKHAMMER..................$ 22.23 2.46
LANDSCAPING.................$ 22.23 2.46
LAYOUT......................$ 22.23 2.46
LUTEMAN.....................$ 22.23 2.46
MASON TENDER................$ 25.28 7.87
MORTAR MIXER................$ 22.23 2.46
PIPELAYER...................$ 25.28 7.87
PLASTERER - HANDLER.........$ 22.23 2.46
SCAFFOLD BUILDER............$ 25.28 7.87
TAMPER......................$ 22.23 2.46
MECHANICAL SYSTEMS SERVICE
TECH
HVAC Systems................$ 52.27 24.58
PAINTER
INDUSTRIAL..................$ 35.55 15.28
PLUMBER..........................$ 46.21 24.90
POWER EQUIPMENT OPERATOR
ASPHALT DISTRIBUTOR.........$ 31.75 8.19
BROOM / SWEEPER.............$ 24.00 6.87
BULLDOZER...................$ 30.08 7.08
CONCRETE PUMP...............$ 34.18 14.62
CRANE.......................$ 41.00 18.10
DRILL - RIG.................$ 34.18 14.62
EXCAVATOR...................$ 34.18 14.62
FORKLIFT....................$ 34.18 14.62
GRADALL.....................$ 30.95 2.47
LOADER......................$ 34.18 14.62
PAVER.......................$ 23.50 5.44
ROLLER - ASPHALT............$ 27.25 5.48
ROLLER - EARTH..............$ 21.75 4.26
SCREED......................$ 29.33 7.61
SKID STEER (Bobcat).........$ 19.38 2.32
VACUUM TRUCK................$ 37.50 14.85
RESILIENT FLOOR..................$ 34.12 14.86
SHEETMETAL WORKER (including metal roofing)...................$ 47.92 24.44
STEAMFITTER/PIPEFITTER...........$ 49.24 24.74
TRUCK DRIVER
DUMP - ARTICULATING.........$ 23.00 5.01
DUMP........................$ 23.92 4.74
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)).
The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.
Union Rate Identifiers
A four-letter identifier beginning with characters other than ""SU"", ""UAVG"", ?SA?, or ?SC? denotes that a union rate was prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.
0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.
Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification.
Union Average Rate Identifiers
The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE:
UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio.
The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.
A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.
Survey Rate Identifiers
The ""SU"" identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007 6/27/2024. SU indicates the rate is a single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier.
?SU? wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1).
State Adopted Rate Identifiers
The ""SA"" identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007 01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.
The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the ?SA? identifier took effect under state law in the state from which the rates were adopted.
WAGE DETERMINATION APPEALS PROCESS
1) Has there been an initial decision in the matter? This can be:
a) a survey underlying a wage determination
b) an existing published wage determination
c) an initial WHD letter setting forth a position on a wage determination matter
d) an initial conformance (additional classification and rate) determination
On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of Wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mail to:
Branch of Wage Surveys Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations.
Requests can be submitted via email to BCWD-Office@dol.gov or by mail to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).
Requests for review and reconsideration can be submitted via email to dba.reconsideration@dol.gov or by mail to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210.
END OF GENERAL DECISION
A.4 PRICE/COST SCHEDULE
ITEM INFORMATION
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1.00 |
| JB |
| __________________ |
| __________________ |
Contractor to provide all labor, supervision, travel, equipment, tools, materials, inspection/testing services, and legal disposal of waste materials to install a new water main to the Boiler Plant and Chiller Plant at the Perry Point VA Medical Center. Additionally, cap and abandon in-place the existing water main and backflow preventer within the Chiller Plant.
Contract Period: Base POP Begin: 05-30-2025 POP End: 08-28-2025 PRINCIPAL NAICS CODE: 236220 - Commercial and Institutional Building Construction PRODUCT/SERVICE CODE: Z2NE - Repair or Alteration of Water Supply Facilities
| GRAND TOTAL |
| __________________ |
A.5 DELIVERY SCHEDULE
| ITEM NUMBER |
| SHIPPING INFORMATION |
| QUANTITY |
| DELIVERY DATE |
| 0001 |
| SHIP TO: |
| Department of Veterans Affairs |
Avenue D Perry Point, MD 21902
USA
| 1.00 |
| 08/28/2025 |
| MARK FOR: |
| Liana J Holland |
304-263-0811 ext 7611 Liana.Holland@va.gov
| FOB: |
| DESTINATION |
A.6 52.201-1 ACQUISITION 360: VOLUNTARY SURVEY (SEP 2023)
(a) All actual and potential offerors are encouraged to provide feedback on the preaward and debriefing processes, as applicable. Feedback may be provided to agencies up to 45 days after award. The feedback is anonymous, unless the participant self-identifies in the survey. Actual and potential offerors can participate in the survey by selecting the following link: https:// www.acquisition.gov/360.
(b) The Contracting Officer will not review the information provided until after contract award and will not consider it in the award decision. The survey is voluntary and does not convey any protections, rights, or grounds for protest.