This is a sealed bid solicitation (IFB) for construction services issued by the Department of Veterans Affairs, Network Contracting Office 4, for an Emergency Room Doorway project at Wilmington VAMC in Delaware. The solicitation number is 36C24426B0016, with an issue date of May 26, 2026, and a bid opening deadline of July 1, 2026, at 12:00 PM EST via virtual Microsoft Teams meeting. The contract will be a firm-fixed-price award to a single contractor based on lowest price, with a performance period of 120 days after Notice to Proceed. The procurement is a 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside with a magnitude of construction between $25,000 and $100,000. The NAICS code is 236220 (Commercial and Institutional Building Construction) with a $45 million size standard. Bidders must be registered and certified in VETCERT, registered in SAM, and registered in the VETS-4212 Database to be eligible for award. A pre-bid conference and site visit will be held on June 3, 2026, at 9:00 AM EST. Written questions are due by June 10, 2026, at 12:00 PM EST.
The scope of work includes providing all labor, materials, and equipment to remove the existing door and doorway material, supply and install a new hollow metal door frame and door, supply and install stucco and wire mesh, connect a PIV reader to the door, and address the stone walkway directly in front of the doorway. All work must comply with federal, state, and local regulations, including VA Infection Control Risk Assessment (ICRA) requirements. Work hours are Monday through Friday, 8:00 AM to 4:30 PM, with contractor responsibility for correct worker classification and wage compliance. Prior to commencing work, the general contractor must provide proof that an OSHA-certified "competent person" will maintain presence at the worksite whenever the general or subcontractors are present. The solicitation includes Davis-Bacon prevailing wage requirements for Delaware counties and incorporates standard FAR and VAAR clauses addressing security, small business compliance, environmental standards, labor standards, and protest procedures. A signed copy of VAAR 852.219-75 (VA Notice of Limitations on Subcontracting—Certificate of Compliance) must be returned with the bid or the proposal will not be considered for award.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Site visit sign in sheet.pdf | ||
| 36C24426B0016 0001_1.docx | DOCX document | |
| 36C24426B0016 0001.pdf | ||
| 36C24426B0016_2.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES
4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER
7. ISSUED BY CODE 8. ADDRESS OFFER TO
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014) STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within ____________ calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES NO
a. Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________
(hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b. An offer guarantee is, is not required.
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C24426B0016 X
05-26-2026
460-23-007
00244
Department of Veterans Affairs Network Contracting Office 4 Wilmington VAMC 1601 Kirkwood Highway Wilmington DE 19805
Hanna.Karmazyn@va.gov
Hanna Karmazyn 302-332-5107
The scope of work consists of providing all labor, materials, and equipment to perform the tasks outlined in the Statement of Work for the Emergency Room Doorway at the Wilmington, DE VAMC.
The contractor shall abide by all federal state, and local code/regulations/standards.
Magnitude of Construction: Between $25,000.00-$100,000.00 Project: Emergency Room Doorway NAICS: 236220- Commercial and Institutional Building Construction Size Standards: $45 Million This procurement is a 100% Service Disabled Veteran Owned Small Business (SDVOSB) set-aside acquisition.
Award will be made to the responsive, responsible bidder, whose bid, in conformance with the solicitation, results in the Lowest Price.
This solicitation will result in a firm-fixed price contract. Only one award will be made.
All documents for this solicitation will be available on the SAM website https://sam.gov/ Bidders must be registered and certified in VETCERT to be eligible for award, SEE https://veterans.certify.sba.gov/ Bidders must be registered in SAM to be eligible for award, SEE https://www.sam.gov/.
Bidders must be registered in the VETS-4212 Database, SEE https://www.dol.gov/vets/vets4212.htm
Interested parties are encouraged to attend the pre-bid Conference/Site Visit. The site visit will be held on June 3, 2026 at 9:00AM EST. Participants are to meet the project COR, Michael Stone, at Building 10 Conference Room 003.
Questions are due in writing via e-mail to the CS at Hanna.Karmazyn@va.gov by 12:00PM EST on June 10, 2026. Late questions will NOT be accepted. Answers will be provided via am amendment posted publicly to htts://sam.gov/
The Contractor shall be responsible for the correct title classification of workers and compliance with all applicable wage and hour laws.
Solicitation may be canceled and all offers rejected before award but after solicitation closing date when it is clearly in the best interest of the Government.
Prior to commencement of work, general contractor shall provide proof that an OSHA certified "competent person' (CP) will maintain a presence at the work site whenever the general or subcontractors are present.
Bid opening will be conducted virtually as listed on page 18 under “Public Bid Opening”.
NOTE: Failure to return a signed copy of 852.219-75 will result in proposal not being considered for award.
10 120
X X 52.211-10
X 10
1 12:00 PM EST
07-01-2026
X
14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO 10 U.S.C. 2304(c)( ) 41 U.S.C. 3304(a) ( )
26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY
PHONE: FAX:
28. NEGOTIATED AGREEMENT 29. AWARD Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code)
(Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
(Type or print)
(4 copies unless otherwise specified)
(Type or print) (Type or print)
(Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror)
(To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
00244
Department of Veterans Affairs Network Contracting Office 4
Austin Payment Center Department of Veterans Affairs
PO Box 149971 Austin TX 78714-9971
(877) 353-9791 (512) 460-5429
Table of Contents
PART I - THE SCHEDULE
SECTION A - SOLICITATION/CONTRACT FORM
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION,
ALTERATION, OR REPAIR)– BACK
-- Services --
-- Environmental/Occupational Safety and Health (EOSH) --
A.3 PRICE/COST SCHEDULE
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
2.3 52.216-1 TYPE OF CONTRACT (APR 1984) (DEVIATION) (NOV 2025)
2.4 52.219-1 SMALL BUSINESS PROGRAM REPRESENTATIONS (NOV 2025)
(DEVIATION) ALTERNATE II (NOV 2025)
2.5 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION
(FEB 2024)(DEVIATION NOV 2025)
2.6 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE
OF THE WORK (MAY 2014) (DEVIATION NOV 2025)
2.7 52.222-32 CONSTRUCTION WAGE RATE REQUIREMENTS—PRICE
ADJUSTMENT (ACTUAL METHOD) (AUG 2018) (DEVIATION NOV 2025)
2.8 52.222-90 ADDRESSING DEI DISCRIMINATION BY FEDERAL CONTRACTORS
(DEVIATION APR 2026)
2.9 52.223-20 AEROSOLS (MAY 2024)
2.10 52.223-21 FOAMS (MAY 2024)
2.11 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)
(DEVIATION NOV 2025)
2.12 52.240-90 SECURITY PROHIBITIONS AND EXCLUSIONS
REPRESENTATIONS AND CERTIFICATIONS (NOV 2025) (DEVIATION)
2.13 52.240-91 SECURITY PROHIBITIONS AND EXCLUSIONS (NOV 2025)
(DEVIATION) ALTERNATE I (NOV 2025) (DEVIATION NOV 2025)
2.14 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE
(FEB 1998)
2.15 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
2.16 52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)
2.17 52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (NOV 2020)
2.18 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—
CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (NOV 2022)
2.19 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) .. 54
2.20 VAAR 852.252-70 SOLICITATION PROVISIONS OR CLAUSES
INCORPORATED BY REFERENCE (JAN 2008)
Wilmington, DE VA Medical Center Wilmington, DE 19805
SCOPE OF WORK
For
Emergency Department Doorway
Period of Performance: 120 days after NTP
-- Services --
PROVIDE:
Professional construction services to include but not limited to: o Site investigation- Mechanical, electrical, plastering, painting and construction. o Construction period of services- Furnish and Install all items. o Infection Control Risk Assessment- Barriers above and below ceiling, tack mats and poly plastic covering.
GENERAL:
The Wilmington, Delaware VA Medical Center intends to issue a construction contract. The project consists of:
o Remove existing door and doorway material. o Supply and install new hollow metal door frame and door. o Supply and install stucco and wire mesh. o Connect PIV reader to door SPECIFICS:
1. The contractor shall furnish all materials, equipment, supervision, and personnel necessary to accomplish the project as indicated. Remove existing door and doorway material. Supply and install new hollow metal door frame and door. Supply and install stucco and wire mesh.
Address the stone walkway area directly infront of doorway.
2. Infection control and safety measures shall be provided per the contract specifications throughout the construction period to minimize risks. All work shall be completed in accordance with the latest ANSI, VA, UFAS, local, state and federal regulations.
3. All work to be performed on Monday through Friday from 8am till 430pm each evening.
4. All employees of the general contractor and subcontractors shall comply with the VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
5. Prior to commencing work, the general contractor shall provide proof that an OSHA certified “competent person” (CP)(29 CFR 1926.20(b)(2) shall maintain a presence at the work site whenever the general or subcontractors are present.
-- Project Scope - -
6. The general contractor shall implement the requirements of the VA Infection Control Risk Assessment (ICRA) team, including the establishment and maintenance of a dust control program. Prior to the start of work, the general contractor must prepare a plan detailing project-specific dust protection measure, including periodic status reports, and submit to the COR and Facility ICRA team for review.
-- Environmental/Occupational Safety and Health (EOSH) --
EXPECTATION: All projects and project designs shall contain language that addresses all applicable EOSH requirements.
Regulatory Compliance – EOSH requirements for work performed at the above location can be found in:
o Volume 29 of the Code of Federal Regulations, Part 1910 – Occupational Safety for General Industry o Volume 29 of the Code of Federal Regulations, Part 1926 – Occupational Safety for The Construction
Industry o Volume 40 of the Code of Federal Regulations – Protection of The Environment o Volume 49 of the Code of Federal Regulations, Part 397 – Transportation of Hazardous Materials o Title 7 of the Delaware Code – Conservation o Title 16 of the Delaware Code – Health and Safety
Specifications The VA Master Construction Specifications contain work procedures and material requirements designed to meet regulatory compliance requirements. Whenever possible, the Master Construction Specifications must be used as the basis for project designs.
SECTION 01 00 00 – General Requirement
01 00 00 -6
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work to as required by drawings, the scope of work, and/or specifications.
B. Visits to the site by Bidders may be made only by appointment with the
COR.
C. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: Perform all work required to enhance the physical security within the VBA suite in Building 13 located on the
Wilmington, DE VA Medical Center campus.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Applicable drawings or contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at
Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
01 00 00 -7
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Document Control:
1. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
2. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
3. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
4. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
5. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
01 00 00 -8
6. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
D. Motor Vehicle Restrictions
1. Contractor parking is prohibited on station at VAMC Wilmington, with the exception of active loading and unloading materials, tools, and equipment as coordinated with the COR.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
01 00 00 -9
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as determined by COR, though no space may be available on site.
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center Cemetery areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
G. Phasing:
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the
01 00 00 -10 work with milestone subtasks. The work to be outlined shall include, but not be limited to:
To insure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to insure accomplishment of this work in successive phases mutually agreeable to
COR and Contractor,
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of buildings.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government.
Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR
52.243-4 and VAAR 852.236-88).
01 00 00 -11
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workmen in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to
01 00 00 -12 be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the
Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
(FAR 52.236-9)
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is
01 00 00 -13 disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
1.11 AS-BUILT DRAWINGS (IF APPLICABLE)
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.12 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical
Center property.
01 00 00 -14
1.13 INSTRUCTIONS
A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.
C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned
Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed.
This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough coverage. The contractor shall submit a course outline with associated material to the COR for
01 00 00 -15 review and approval prior to scheduling training to ensure the subject matter covers the expectations of the VA and the contractual requirements. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the COR, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.
- - - E N D - - -
01 00 00 -16
A.3 PRICE/COST SCHEDULE
ITEM
NUMBER
DESCRIPTION OF
SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 Construction Services – Emergency Room Doorway
1.00 JB __________________ __________________
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE
AND BONDS
A. TRAINING:
Effective July 31, 2005, all employees of the general contractor and subcontractors shall have the 10-hour OSHA certified construction safety course. The General Contractor’s competent person shall have completed the 30-hour OSHA certified construction safety course. Documentation of training shall be submitted to the Contracting Officer for review and approval prior to any work being performed.
Failure to present the proper training documentation will result in the individual being removed from the job; the individual may only return after the proper documentation has been provided.
There shall be no exceptions to this requirement.
It is the responsibility of the Contractor to provide TB training annually and a PPD test annually for any employees providing services at the VA Medical Center, Wilmington, DE. The government reserves the right to review the contractor’s records. Failure to present the proper training documentation upon the Contracting Officer’s request will result in the individual being removed from the job; the individual may only return after the proper documentation has been provided. There shall be no exceptions to this requirement.
B. PRIVACY AND CONFIDENTIALITY:
Contractors to the Department of Veterans Affairs may be unintentionally exposed to sensitive information. Information maybe overheard, seen on documents or electronic devices, or observed that could potentially violate the privacy and confidentiality of our veterans, employees, volunteers, and their families. Regulations such as, but not limited to the Health Insurance Portability and Accountability Act of 1996 (HIPAA), Freedom of Information Act (FOIA) and Privacy Act of 1974 have been enacted to protect sensitive information from being improperly disclosed. Information should not be divulged or released to anyone unless specifically authorized in accordance with the contracted services. Failure to comply with applicable statutes and regulation can result in the termination of this contract and civil and criminal penalties, including fines and imprisonment. All suspected or actual breaches of the privacy and confidential should be reported immediately to the Contracting Officer, COR or the Facility Privacy Officer.
C. KEYS:
All keys provided the Contractor or any subcontractor for use during the project shall be returned to the COR at completion of the work or upon request. No keys shall be reproduced by the Contractor or any subcontractor. There shall be a charge for each key that is lost or not returned to the COR.
D. CONTRACTOR NORMAL WORK HOURS:
The contractor work hours are from 7:00AM to 4:30PM, Monday through Friday, excluding federal holidays. Federal holidays that fall on a non-workday –Saturday or Sunday—the holiday usually is observed on Monday if the holiday is on Sunday or on Friday if the holiday is on Saturday. The contractor may request authorization from the Contracting Officer to work an alternative schedule or on holidays. However, the Contracting Officer reserves the right to deny or authorize the contractor’s request at his or her discretion considering the best interests of the Government. All federal holidays are observed as non-workdays. Federal holidays can be found on the following web site:
http://www.opm.gov/policy-data-oversight/snow-dismissal-procedures/federal-holidays. These days will be identified during the pre-construction meeting. This contract may require work to be performed off-hours, and any increased costs related to this work will be the responsibility of the contractor.
E. SAFETY/ENVIRONMENTAL VIOLATIONS AND EXPERIENCE MODIFICATION RATE
All offerors shall submit information pertaining to their past safety and environmental record. The information shall contain, at a minimum, a certification that the offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any Environmental Protection Agency (EPA) violation(s) in the past three years. All offerors shall submit information regarding their current Experience Modification Rate (EMR) equal to or less than 1.0. This information shall be obtained from the offeror’s insurance company and be furnished on the insurance carrier’s letterhead.
Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR shall obtain their EMR rating from their state run worker’s compensation insurance rating bureau.
A determination of responsibility will be accomplished for the apparent awardee prior to processing the award. The above information, along with other information obtained from Government systems, such as the System for Award Management (SAM.gov), Veteran Small Business Certification (VetCert), DUN and Bradstreet, Federal Awardee Performance and Integrity Information System (FAPIIS) accessed through the Past Performance Information Retrieval System (PPIRS), Small Business Administration (SBA), Office of Inspector General-Health and Human Services (OIG-HHS), OSHA, Veterans’ Employment & Training Services (VETS 4214) reporting database, and EPA online inspection history databases will be used to make the Determination of Responsibility. Any information received by the Government that would cause for a negative Determination of Responsibility may make the offeror ineligible for award. This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.
As required by the statutory requirement pertaining to the Veterans Benefits Act of 2003 (15 U.S.C. 657f) and in accordance with FAR 6.206, this procurement will be set-aside for Service-Disabled Veteran Owned Small Business (SDVOSB) concerns. Only SDVOSB concerns who are verified in the Veteran Small Business Certification (VetCert) and registered in System for Award Management (SAM.gov) will be eligible to submit proposals.
F. CONTRACTING OFFICER’S REPRESENTATIVE (COR):
In accordance with VAAR 1.604 and 1.602-2 the COR assists in the technical monitoring or administration of a contract. Limited authority is given in writing by the Contracting Officer’s letter of http://www.opm.gov/policy-data-oversight/snow-dismissal-procedures/federal-holidays designation describing the COR’s duties and responsibilities. The COR has no authority to make any commitments or changes that affect price, quality, quantity, delivery, or other terms and conditions of the contract (or provisions of the solicitation). The COR’s authority is limited to contract administration functions delegated in writing by the Contracting Officer. In this solicitation and in the specifications, COR may be used interchangeably with Contracting Officer’s Technical Representative (COTR), Resident Engineer, Project Engineer and Engineer/Engineering.
G. POINT OF CONTACT:
All questions are to be directed to the Contract Specialist at the Wilmington VAMC. Do not contact any A/E firm that may be identified herein. The A/E firm does not have the authority to share information with others or bind the government.
H. WAGE AND HOUR LAWS:
The Contractor shall be responsible for the correct title classification of workers and compliance with all applicable wage and hour laws.
I. PUBLIC BID OPENING:
E-mail bids and bonds to Contract Specialist, Hanna Karmazyn at Hanna.Karmazyn@va.gov
Bids to be opened via MS Teams. Please save/ forward the invite link or dial in as desired.
Microsoft Teams meeting
Join: https://teams.microsoft.com/meet/226206085241206?p=iDaiJ2Mcc8yfEULLUc
Meeting ID: 226 206 085 241 206
Passcode: nn9He6GF
Need help? | System reference
Dial in by phone
+1 205-235-3524,,953872274# United States, Dora
Find a local number
Phone conference ID: 953 872 274#
For organizers: Meeting options | Reset dial-in PIN mailto:Hanna.Karmazyn@va.gov https://teams.microsoft.com/meet/226206085241206?p=iDaiJ2Mcc8yfEULLUc https://aka.ms/JoinTeamsMeeting?omkt=en-US https://teams.microsoft.com/l/meetup-join/19%3ameeting_ZWRkMjA2MmEtYzc1ZS00ZjRjLThjOWEtNWUwMzMxZGU1ZDJh%40thread.v2/0?context=%7b%22Tid%22%3a%22e95f1b23-abaf-45ee-821d-b7ab251ab3bf%22%2c%22Oid%22%3a%225a1f8d95-a89f-4d23-80e1-b83c40186720%22%7d tel:+12052353524,,953872274 https://dialin.teams.microsoft.com/14a86cbc-ba2a-4dde-a83a-5b9e20685e48?id=953872274 https://teams.microsoft.com/meetingOptions/?organizerId=5a1f8d95-a89f-4d23-80e1-b83c40186720&tenantId=e95f1b23-abaf-45ee-821d-b7ab251ab3bf&threadId=19_meeting_ZWRkMjA2MmEtYzc1ZS00ZjRjLThjOWEtNWUwMzMxZGU1ZDJh@thread.v2&messageId=0&language=en-US https://dialin.teams.microsoft.com/usp/pstnconferencing
System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations. Examples include 52.222-25, Affirmative Action Compliance, and paragraph (d) of 52.212- 3, Offeror Representations and Certifications—Commercial Products and Commercial Services.
Contracting officers will not consider these representations when making award decisions or enforce requirements. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO
BIDDERS/OFFERORS
2.3 52.216-1 TYPE OF CONTRACT (APR 1984) (DEVIATION) (NOV 2025)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
(End of Provision)
2.4 52.219-1 SMALL BUSINESS PROGRAM REPRESENTATIONS (NOV
2025) (DEVIATION) ALTERNATE II (NOV 2025)
(a) Definitions. As used in this provision—
Economically disadvantaged women-owned small business (EDWOSB) concern means a small business concern that is at least 51 percent directly and unconditionally owned by, and the management and daily business operations of which are controlled by, one or more women who are citizens of the United States and who are economically disadvantaged in accordance with 13 CFR part 127, and the concern is certified by SBA or an approved third-party certifier in accordance with 13 CFR 127.300. It automatically qualifies as a women-owned small business concern eligible under the WOSB Program.
HUBZone small business concern means a small business concern that meets the requirements described in 13 CFR 126.200, is certified by the Small Business Administration (SBA) and designated by SBA as a HUBZone small business concern in the Small Business Search (SBS) (13 CFR 126.103).
Service-disabled veteran-owned small business (SDVOSB) concern eligible under the SDVOSB Program means an SDVOSB concern that is designated in the System for Award Management (SAM) as certified by the Small Business Administration (SBA) in accordance with
13 CFR 128.300.
Small business concern—
(1) Means a concern, including its affiliates, that is independently owned and operated, not dominant in its field of operation, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (b) of this provision.
(2) Affiliates, as used in this definition, means business concerns, one of whom directly or indirectly controls or has the power to control the others, or a third party or parties control or have the power to control the others. In determining whether affiliation exists, consideration is given to all appropriate factors including common ownership, common management, and contractual relationships. SBA determines affiliation based on the factors set forth at 13 CFR 121.103.
Small disadvantaged business concern, consistent with 13 CFR 124.1001, means a small business concern under the size standard applicable to the acquisition, that-
(1) Is at least 51 percent unconditionally and directly owned (as defined at 13 CFR 124.105) by one or more socially disadvantaged (as defined at 13 CFR 124.103) and economically disadvantaged (as defined at 13 CFR 124.104) individuals who are citizens of the United States, and
(2) The management and daily business operations of which are controlled (as defined at 13 CFR 124.106) by individuals who meet the criteria in paragraph (1) of this definition.
Women-owned small business (WOSB) concern eligible under the WOSB Program (in accordance with 13 CFR part 127) means a small business concern that is at least 51 percent directly and unconditionally owned by, and the management and daily business operations of which are controlled by, one or more women who are citizens of the United States, and the concern is certified by SBA or an approved third-party certifier in accordance with 13 CFR 127.300.
(b)(1) The North American Industry Classification System (NAICS) codes and corresponding size standards for this acquisition are as follows; the categories or portions these NAICS codes are assigned to are specified elsewhere in the solicitation:
NAICS Code Size Standard
(2) The small business size standard for a concern that submits an offer, other than on a construction or service acquisition, but proposes to furnish an end item that it did not itself manufacture, process, or produce (i.e., nonmanufacturer), is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition—
(i) Is set aside for small business and has a value above the simplified acquisition threshold;
(ii) Uses the HUBZone price evaluation preference regardless of dollar value, unless the offeror waives the price evaluation preference; or
(iii) Is an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.
(c) Representations.
(1) The Offeror shall represent its small business size status for each one of the NAICS codes assigned to this acquisition under which it is submitting an offer.
NAICS Code Small Business Concern (yes/no)
(2) [Complete only if the offeror represented itself as a small business concern in paragraph (c)(1) of this provision.] The offeror represents that it [ ] is, [ ] is not a women-owned small disadvantage business concern.
(3) Women-owned small business (WOSB) joint venture eligible under the WOSB Program.
The offeror represents as part of its offer that it [ ] is, [ ] is not a joint venture that complies with the requirements of 13 CFR 127.506(a) through (c). [The offeror shall enter the name and unique entity identifier of each party to the joint venture: _________________.]
(4) Economically disadvantaged women-owned small business (EDWOSB) joint venture. The offeror represents as part of its offer that it [ ] is, [ ] is not a joint venture that complies with the requirements of 13 CFR 127.506(a) through (c). [The offeror shall enter the name and unique entity identifier of each party to the joint venture: _________________.]
(5) SDVOSB joint venture eligible under the SDVOSB Program. [Complete only if the offeror is certified as a SDVOSB concern]. The offeror represents as part of its offer that it [ ] is, [ ] is not a SDVOSB joint venture eligible under the SDVOSB Program that complies with the requirements of 13 CFR 128.402. [The offeror shall enter the name and unique entity identifier of each party to the joint venture: _________________.]
(6) HUBZone joint venture eligible under the HUBZone Program. [Complete only if the offeror is a HUBZone small business concern.] The offeror represents, as part of its offer, that it [ ] is, [ ] is not a HUBZone joint venture that complies with the requirements of 13 CFR 126.616(a) through (c). [The offeror shall enter the name and unique entity identifier of each party to the joint venture: _________________.] Each HUBZone small business concern participating in the HUBZone joint venture must be certified as a HUBZone concern.
(d) Notice.
Under 15 U.S.C. 645(d), any person who misrepresents a firm’s status as a business concern that is small, HUBZone small, small disadvantaged, service-disabled veteran-owned small, economically disadvantaged women-owned small, or women-owned small eligible under the WOSB Program in order to obtain a contract to be awarded under the preference programs established pursuant to section 8, 9, 15, 31, and 36 of the Small Business Act or any other provision of Federal law that specifically references section 8(d) for a definition of program eligibility, will be—
(1) Punished by imposition of fine, imprisonment, or both;
(2) Subject to administrative remedies, including suspension and debarment; and
(3) Ineligible for participation in programs conducted under the authority of the Act.
(End of Provision)
2.5 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM
REREPRESENTATION (FEB 2024)(DEVIATION NOV 2025)
(a) Definitions. As used in this clause—
Long-term contract means a contract of more than five years in duration, including options.
However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.
Small business concern—
(1) Means a concern, including its affiliates, that is independently owned and operated, not dominant in its field of operation, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause.
(2) Affiliates, as used in this definition, means business concerns, one of whom directly or indirectly controls or has the power to control the others, or a third party or parties control or have the power to control the others.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .