Questions from Industry - 36C24425Q0146.docx
DOCX document 16 KB Posted
- Solicitation number
- 36C24425Q0146
About this file
This is a Questions and Answers document related to solicitation 36C24425Q0146 for water treatment system services at the Erie VA Medical Center. The document contains three industry questions focused on chemical container specifications, injection points for the system, and alternate certifications for water treatment.
The related solicitation is for a five-year IDIQ fixed-price contract for water system testing, maintenance, and hyperchlorination services at the Wilmington VA Medical Center. This is a Veteran-Owned Small Business set-aside under NAICS 221310 with a $41M size standard. Quotes must include three sections: Administrative/Regulatory, Technical (10-page limit), and Price. Technical evaluation will be conducted on a Lowest Price Technically Acceptable (LPTA) basis. Questions are due by December 30, 2024, and must be submitted to Keri Lewis at the VA. The solicitation requires contractors to demonstrate experience with hyperchlorination programs and certified water treatment practices.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24425Q0146 0002.docx | DOCX document | |
| 36C24425Q0146 0001_1.docx | DOCX document | |
| 36C24425Q0146_1.docx | DOCX document | |
| 36C24425Q0146.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submitted Questions and Answers 01/07/2025 36C24425Q0146 | Water Treatment System | Erie
1) What is the chemical container size and quantity request?
Answer: The vendor determines the amount of chlorine to be used.
2) Injection points: where will they be, how many are going to be available, and is GC responsible for finding a contractor for the installation of said points? Or does the facility have the means to valve off each floor in order to disinfect specific areas?
Answer: We either have injection points already installed at the common problem areas or will have them installed prior to the contractor coming.
3) If the contractor does not have CWT or AWT certification. Is it possible to submit evidence that they can provide certifications that meet similar/greater compliance to said accreditations?
Answer: We will review additional or similar accreditation.