36C24425B0014 0001.docx
DOCX document 977 KB Posted
- Attached to
- Z1DA--562-25-207 Replace Boiler Safety Valves Fittings | NCO 4 Construction West (VA-25-00066884)
- Solicitation number
- 36C24425B0014
About this file
This document is an Amendment (A0001) to a solicitation for replacing boiler safety valves at the Veterans Administration Medical Center in Erie, Pennsylvania. The amendment provides responses to Request for Information (RFI) questions, clarifying technical details about the project. Key details include the roof being a 60 mil Thermoplastic Polyolfefin (TPO) by Versico Roofing Systems, confirmation that bid and performance bonds are required, and specific technical specifications for boiler safety valves for three boilers. The safety valves for each boiler have different capacities: Boiler #1 ranges from 4,438 to 4,487 pounds/hour, Boiler #2 and #3 both range from 10,818 to 11,928 pounds/hour. The amendment also specifies technical requirements for flanges, bolts, and nuts, and indicates that any catwalk modifications must use matching grating with fixed joints. Proposals are due electronically on June 25th, 2025 at 11:00 AM EST, with submissions to be sent to Christopher.McDevitt@va.gov and Keneisha.Coleman@va.gov.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
S06 Replace Boiler Safety Valves Fittings– Erie RFIs & Answers
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 562-25-207 00244 Department of Veterans Affairs Network Contracting Office 4
00244 Department of Veterans Affairs Network Contracting Office 4
To all Offerors/Bidders
36C24425B0014
X X X X The above numbered solicitation for "Replace Boiler Safety Valves Fittings" is amended as follows:
Amendment A0001 provides answers to submitted RFIs on pages 2-4.
Please see attachments.
Proposals must be submitted electronically to Christopher.McDevitt@va.gov and Keneisha.Coleman@va.gov.
The proposal due date remains the same on June 25th 2025 at11:00 AM EST.
Christopher McDevitt Contracting Officer
| # |
| Question |
| VA Answer |
| 1 |
| What type of roof is it? |
60 mil Thermoplastic Polyolfefin (TPO)
| 2 |
| Who is the manufacturer? |
Versico Roofing Systems
| 3 |
| Is it still under warranty? |
Yes
| 4 |
| Box 12.a is selected as “NO”. Please confirm that bid, performance and payment bonds are required for this project. |
The Contracting Officer has the ability to require Bonds below the statutory threshold established by the FAR, for this solicitation Bonds are required.
| 5 |
| This project will require an R-Stamp certification IAW the National Board of Boiler and Pressure Vessel Inspectors (NBBI). To document these repairs, we will need the NBBI Manufacturer’s Data Reports for each boiler. Can you please provide the NBBI Manufacturer’s Data Reports for each boiler? |
| 6 |
| Please provide the required capacities for each of the new boiler safety valves. |
0. Boiler #1
0. 1 ¼” Cast Steel Safety Valve set at 120 psi
0. Capacity = _______ pounds/hour
0. 1 ¼” Cast Steel Safety Valve set at 125 psi
1. Capacity = _______ pounds/hour
0. Boiler #2
1. 2” Cast Steel Safety Valve set at 120 psi
0. Capacity = _______ pounds/hour
1. 2” Cast Steel Safety Valve set at 125 psi
1. Capacity = _______ pounds/hour
0. Boiler #3
2. 2” Cast Steel Safety Valve set at 120 psi
0. Capacity = _______ pounds/hour
2. 2” Cast Steel Safety Valve set at 125 psi
1. Capacity = _______ pounds/hour
Boiler #1 i.8,048 pounds/hour ii.8,348 pounds/hour
Boiler #2 i.11,500 pounds/hour ii.11,928 pounds/hour
Boiler #3 i.11,500 pounds/hour ii.11,928 pounds/hour
Modifications to the existing catwalks may be required to achieve the required height of the new safety valves. If a section of the catwalk grating needs to be removed to accommodate this new height, would a sheet metal pan covering the opening be acceptable?
No, matching grating with fixed joints or fasteners must be used.
Please confirm the acceptable material composition of the new studs/nuts/bolts for the new flanged connections.
A. Flanges and Bolts: Forged steel weld neck, ASME B16.5, ASTM A105/A105M, 1034 kPa (150 psig) pressure class, except 2070 kPa (300 psig) class required adjacent to 1724 kPa (250 psig) and 2070 kPa (300 psig) class valves. Bolts shall be high strength steel ASTM A193/A193M, Class 2, Grade B7. Nuts shall be ASTM A194/A194M.
Reference: SECTION 23 21 11
BOILER PLANT PIPING SYSTEMS
See attached document: Boiler 1 NB 10592 Internal-External-Hydro Cert Signed.
See attached document: Boiler 1 NB 10592 Internal-External-Hydro Final Report Signed.
See attached document: Boiler 2 NB 10598 Internal and External rev 1 Signed.
See attached document: Boiler 2 NB 10598 Internal-External-Hydro Cert Signed.
See attached document: Boiler 3 NB 10589 Internal and External Final Report Signed.
See attached document: Boiler 3 NB 10589 Internal-External-Hydro Cert Signed.
End of Document image4.emf
Boiler #2 NB #10598 Internal-External-Hydro Cert Signed.pdf
VETERANS ADMINISTRATION MEDICAL
CENTER 135 E. 38th St
Erie, PA 16504
INSPECTION CERTIFICATE FOR: ___ BOILER ___ UNFIRED PRESSURE VESSEL
BUILDING # LOCATION SERIAL #
NATIONAL BOARD # & ASME STAMPING MANUFACTURE MAXIMUM ALLOWABLE PRESSURE
PSI
THIS CERTIFICATE EXPIRES ON:
3/27/2019
THIS BOILER HAS BEEN INSPECTED AND APPROVED, BY MAC
INSPECTION & WELDING AGENCY, LLC (MIWA), FOR IT'S INTERNAL,
EXTERNAL & HYDROSTATIC INTEGRITY. RESPONSIBILTY FOR
OPERATIONAL UNDER PRESSURE INSPECTIONS ARE TO BE PERFORMED
BY OTHERS.
TYPE OF INSPECTION: X EXTERNAL X INTERNAL X HYDROSTATIC N/A OPERATIONAL
INSPECTOR PRINT NAME & SIGNATURE DATE NATIONAL BOARD COMMISION #
THIS CERTIFICATE SHALL BE POSTED IN A PROCTIVE SLEEVE NEAR THE ABOVE OBJECT. THE FULL
INSPECTION REPORT SHALL BE MAINTAINED ON FILE
New Boiler Plant 10598
10598 & "S" William & Davis 200
12702A 3/27/2018Michael Coleman Michael Coleman image5.emf
Boiler #3 NB #10589 Internal and External Final Report Signed.pdf
MAC Inspection & Welding Agency (MIWA) National Board # 10589
MAC INSPECTION & WELDING AGENCY
BOILER INSPECTION CHECKLIST
Inspector: Michael Coleman Date: March 27, 2018 Page 1 of 2 Location Name / Building # VAMC Erie, PA
Nat’l Bd No /. Mfr’s Serial No 10589 / 10589
Boiler No.
Boiler Manufacturer and Year of Manufacture, ASME Stemp William & Davis, 2017, “S”
Current Certification Date Not Assigned
New Certificate Number N/A
New Certificate Expiration Date
Safety Valve Manufacture Kunkle Valve
TYPE OF TEST OR INSPECTION
External Visual Internal Visual Hydrostatic Test Other__________
Boiler Type (FT,WT, SM, HRT, etc.)
Horizontal Fire Tube
Method of Firing and Fuel Type
(1) Natural Gas (2) #2 Oil
MAWP (psig)
Test Pressure (psig)
SAFETY VALVE SETTINGS
Steam Drum # Set PSI - Size BTU/HR or LBS/HR
CHECKLIST OF ITEMS INSPECTED OR TESTED
Initial the Appropriate Box (Satisfactory, Unsatisfactory, or N/A) Corresponding to Each Step S U N/A
EXTERNAL INSPECTION
1.
Accessibility (Surrounding & Lighting) X
2.
Ladders, Stairs, and Handrails X
3.
Surfaces (Drums, Tubes, and Headers) X
4.
Check the Following for Cleanliness, Leaks, and Damage
a) Boiler Casing X
b) Control Equipment X
c) Fuel Burning Equipment X
d) Water Level Indicating & Control Equipment X
e) Blowdown Lines X
f) Valves X
g) Fittings X
h) Boiler Relief Valves X
i) Pressure Gauges X
j) Accessories X
5.
Appliance Connections X
INTERNAL INSPECTION
6.
Drums and Headers:
a) Valves (Closed, Tagged, and Padlocked) X
b) Electrical Accessories and Safety Lights Properly Used X
c) Internal Surfaces X
d) Stays and Braces
e) Presence of Sediment, Scale, and Debris
f) Presence & Extent of Corrosion (if any)
g) Scale Deposits on Tubes and Headers
Continued Next Page
2"
10818 LBS/HR
11477 LBS/HR
MAC Inspection & Welding Agency (MIWA) National Board # 10589
Page 2 of 2 BOILER INSPECTION CHECKLIST Initial the Appropriate Box (Satisfactory, Unsatisfactory, or N/A) Corresponding to Each Step S U N/A INTERNAL INSPECTION (Continued)
7.
Furnace: X
a) Scale/Slag on Upper Waterwall or Furnace Tube X
b) Refractory Condition X
c) Baffles and Dividers X
d) Distortion/Alignment of Tubes in Firebox X
e) Tube Walls X
f) Burners X
8.
Appurtenances:
a) Water Columns (and Gage Cocks when present) X
b) Pressure Gauge Tracking and Calibration X
HYDROSTATIC TEST (if applied) 9.
Safety Valves Gagged (when required) X
10.
Non-Pressure Devices Removed or Blocked X
11.
Boiler Temperature Between 70oΕ and 120oF X
12.
Boiler Pressurized (SHALL NOT Exceed 1.5 X MAWP) X
13.
Pressure Containing Parts X
14.
Verify Leak Tightness of Repairs X
15.
Safety Valve Gags Removed (if installed) X
OPERATIONAL TEST
16.
Functional Test of Safety Valve X
17.
Adjustments Require to Meet Tolerances X
18.
Operational Interlocks Meet CSD-1 Requirements X
19.
Combustion Fan Overspeed Trips X
POST INSPECTION
20.
Design Review and Acceptance (when applicable for Alteration) X
21.
Material Identification and Acceptance for Repair/Alteration (Repair or Replacement) X
24.
Verify Code Compliance (Welding, NDE, PWHT, etc.) X
25.
Complete and Certifiy NB Form Documenting Repair/Alteration X
CONDITION OF BOILER
No Deficiencies Noted Deficiencies Noted
REMARKS: (Mandatory for all items marked “U” above, attach additional sheet of necessary)
2. Recommend a catwalk be installed on the boiler.
4I - Boiler manifold piping to presssure gauge is designed as a wet system, protecting the gauge. No pig tail is required.
Tube and tube sheet surface coloration is normal considering lay up time. Condition will be treated upon final chemical treatment.
Safety Relief Valves were certified in 2017.
Operational testing & final gas & oil tuning responsible by others.
Inspector Signature/Commission Number/Date
Michael Coleman / 12702A / 3-27-2018
Accept Reject Not Insp Code “S” Scheduled Unscheduled Initial Installation image6.emf
Boiler #3 NB #10589 Internal-External-Hydro Cert Signed.pdf
New Boiler Plant 10589
10589 & "S" William & Davis 200 image1.emf
Boiler #1 NB #10592 Internal-External-Hydro Cert Signed.pdf
New Boiler Plant 10592
10592 & "S" William & Davis 200 image2.emf
Boiler #1 NB #10592 Internal-External-Hydro Final Report Signed.pdf
MAC Inspection & Welding Agency (MIWA) National Board # 10592
10592 / 10592
Initial the Appropriate Box (Satisfactory, Unsatisfactory, or N/A) Corresponding to Each Step S U N/A
a) Boiler Casing X
b) Control Equipment X
c) Fuel Burning Equipment X
d) Water Level Indicating & Control Equipment X
e) Blowdown Lines X
f) Valves X
g) Fittings X
h) Boiler Relief Valves X
b) Electrical Accessories and Safety Lights Properly Used X
1-1/4" 1-1/4"
4438 LBS/HR
4487 LBS/HR
MAC Inspection & Welding Agency (MIWA) National Board # 10592
Initial the Appropriate Box (Satisfactory, Unsatisfactory, or N/A) Corresponding to Each Step S U N/A
a) Scale/Slag on Upper Waterwall or Furnace Tube X
b) Refractory Condition X
c) Baffles and Dividers X
d) Distortion/Alignment of Tubes in Firebox X
4I - Boiler manifold piping to pressure gauge is designed as a wet system, protecting the gauge. No pig tail is required.
Operational testing and final gas & oil tuning responsible by others.
image3.emf
Boiler #2 NB #10598 Internal and External rev 1 Signed.pdf
MAC Inspection & Welding Agency (MIWA) National Board # 10598
10598 / 10598
Initial the Appropriate Box (Satisfactory, Unsatisfactory, or N/A) Corresponding to Each Step S U N/A
a) Boiler Casing X
b) Control Equipment X
c) Fuel Burning Equipment X
d) Water Level Indicating & Control Equipment X
e) Blowdown Lines X
f) Valves X
g) Fittings X
h) Boiler Relief Valves X
b) Electrical Accessories and Safety Lights Properly Used X
10818 LBS/HR
11477 LBS/HR
MAC Inspection & Welding Agency (MIWA) National Board # 10598
Initial the Appropriate Box (Satisfactory, Unsatisfactory, or N/A) Corresponding to Each Step S U N/A
a) Scale/Slag on Upper Waterwall or Furnace Tube X
b) Refractory Condition X
c) Baffles and Dividers X
d) Distortion/Alignment of Tubes in Firebox X
4I - Boiler manifold piping to pressure gauge is designed as a wet system, protecting the gauge. No pig tail is required.
Operational testing & final gas & oil tuning responsible by others.