Question and Answer - 36C24424Q0727.docx
DOCX document 13 KB Posted
- Solicitation number
- 36C24424Q0727
About this file
This document is a Question and Answer regarding Solicitation 36C24424Q0727, which is a Request for Quote (RFQ) for a five-year, firm-fixed price Indefinite Delivery - Indefinite Quantity (IDIQ) contract for water system testing and maintenance services.
The key details are:
- The solicitation is for an estimated total of 200 panels, 300 tests, and 360 tests over the 5-year period, to be ordered on an as-needed basis.
- The pricing schedule and Statement of Work (SOW) have been updated in an amendment and should be referenced using Version 2.
- The solicitation is a Small Business set-aside with a NAICS code of 541380 and a size standard of $16.5 million.
- The contracting agency is the Department of Veterans Affairs, Veterans Health Administration, Veterans Integrated Service Network 4.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment A - Statement of Work - Version 2.docx | DOCX document | |
| Attachment C - Price Schedule - Version 2.docx | DOCX document | |
| 36C24424Q0727 0001.docx | DOCX document | |
| Attachment B - Past Performance Questionnaire.docx | DOCX document | |
| Attachment C - Price Schedule.docx | DOCX document | |
| Attachment A - Statement of Work.docx | DOCX document | |
| 36C24424Q0727.docx | DOCX document | |
| Attachment D - Wage Determination.pdf | ||
| Combined Synopsis - 36C24424Q0727 - Water and Utility Testing - 646.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question and Answer
1. We are looking for some clarification on the pricing schedule for this sol attached.
For example, item 0001 reads 200 (estimated) panels. Does this mean that over the course of the 5 years you might order between 3-4 tests per month to be done? 200/60 = 3.33 Item 0002 Does this mean that over the course of the 5 years you might order around 15 tests per quarter? 300/20quarters Item 0003 Does this mean that over the course of the 5 years you might order around 18 tests per quarter? 360/20quarters Answer:
The total listed in the price schedule is the estimated total usage over five years. Year one estimate can be figured by dividing that total by 5. The price schedule and SOW have been updated in the amendment and should be referenced using Version 2.
File details come from the government source that posted it. Updated .