36C24423R0045.docx

DOCX document 152 KB Posted

Attached to
P400--Demolish Buildings Design-Build | 503-21-107
Solicitation number
36C24423R0045
Issued by

About this file

This solicitation requests proposals for a design-build project to demolish four buildings at a Veterans Affairs medical center. The project is set aside for a Service-Disabled Veteran-Owned Small Business and has an anticipated value between $1 million and $2 million.

The solicitation is conducted in two phases, with Phase I open to all qualified SDVOSB offerors. Phase II will be open only to the top-ranked offerors selected from Phase I evaluations. Phase I proposals are due by March 31, 2023 and should address the technical approach, qualifications, and past performance. Phase II proposals will be requested from finalists and must cover design concepts, management approach, schedule, and pricing. The award will be a fixed-price contract for design completion and demolition work within 420 days of notice to proceed.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C24423R0045

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5.

REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE

DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL

SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

1. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than ____ ___________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C24423R0045 X 02-27-2023 503-23-2-5071-0007 503-21-107 00244 Department of Veterans Affairs Network Contracting Office 4

See Instructions to Offerors

Melvin Moore

(814) 943-8164

Demolish Buildings 4, 5, 6, and 10 - Design Build

This is a design build solicitation under FAR Part

36.301. All qualified offerors may submit for Phase I.

After Phase I evaluation is completed, the Government will notify only the top offerors via email with instructions for Phase II submission; however, Phase II information is also included in this solicitation. Non- Selected Phase I offerors shall be notified that their offer was not selected for the Phase II of the solicitation.

This project is being solicited as a 100% Service Disable Veteran Owned Small Business (SDVOSB) set aside. The North American Industry Classification System (NAICS) code is 238910. The Size Standard is $19.0 Million.

The Disclosure of Magnitude of Construction Projects is between $1,000,000.00 and $2,000,000.00

Wage Determination PA 2023007 7 dated 01/13/2023 applies to this solicitation and any resultant contract.

The Contractor shall be responsible for the correct title and classification of workers and compliance with applicable wage and hour laws.

The attached Contract Language Doc shall be part of this solicitation and any resultant award.

VAAR Clause 852.219-75 is required to be signed and returned with submission package requirement s.

ALL PROPOSALS MUST BE RECEIVED NO LATER THAN 1:00 P.M. ON MARCH 31, 2023 by ELECTRONIC SUBMISSION (email) only.

ANY PROPOSALS RECEIVED AFTER THE TIME SPECIFIED WILL BE

CONSIDERED NONCOMPLIANT AND INVALID.

Design-Build Schedule, Reference Attachment SOW Design-Build Demo Project # 503-21-107 Design & Environmental Assessment - Phase 1, Multiple Timeline Milestones Construction - Phase II, 270 Days Overall Delivery Schedule 420 Days

X X 52.211-10 X 13:00

EDT

03-31-2023 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any req uired performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23.

ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT

WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise s pecified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

503-3630162-5071-854200-3220 503-23-2-5071-0007 00244 Department of Veterans Affairs Network Contracting Office 4

Austin Payment Center Department of Veterans Affairs PO Box 149971 Austin TX 78714-9971

(877) 353-9791

(512) 460-5429 Contracting Officer

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
SCHEDULE6
PRICE/COST SCHEDULE6
ITEM INFORMATION6
ACCOUNTING AND APPROPRIATION DATA6
DELIVERY SCHEDULE6
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS7
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS8
INSTRUCTIONS TO OFFERORS8
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)17
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)17
2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)17
2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)18
2.5 52.228-1 BID GUARANTEE (SEP 1996)19
2.6 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021)20
2.7 52.233-2 SERVICE OF PROTEST (SEP 2006)20
2.8 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)21
2.9 52.246-26 REPORTING NONCONFORMING ITEMS (NOV 2021)21
2.10 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)24
2.11 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)24
2.12 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)24
2.13 VAAR 852.252-70 SOLICITATION PROVISIONS OR CLAUSES INCORPORATED BY REFERENCE (JAN 2008)25
2.14 PARTNERING25
REPRESENTATIONS AND CERTIFICATIONS26
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (DEC 2022)26
3.2 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)30
3.3 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021)31
GENERAL CONDITIONS34
4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014)34
4.2 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (NOV 2021)34
4.3 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)35
4.4 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984)36
4.5 52.211-12 LIQUIDATED DAMAGES—CONSTRUCTION (INCLUDES TABLE FOR SEPARATE PARTS OR STAGES) (SEPT 2000)37
4.6 52.219-14 LIMITATIONS ON SUBCONTRACTING (OCT 2022)37
4.7 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (OCT 2022)39
4.8 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020)42
4.9 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020)42
4.10 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010)43
4.11 52.223-20 AEROSOLS (JUN 2016)44
4.12 52.223-21 FOAMS (JUN 2016)45
4.13 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)46
4.14 SUPPLEMENTAL INSURANCE REQUIREMENTS51
4.15 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)52
4.16 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022)55
4.17 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018)55
4.18 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)61
4.19 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)62
4.20 VAAR 852.236-72 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 2019)63
4.21 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)64
4.22 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)64
4.23 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020)64
4.24 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)66
4.25 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)66
DESIGN BUILD SPECIFICATIONS68
4.26 CONTRACTOR'S COST BREAKDOWN68
4.27 SCHEDULE OF PAYMENTS FOR DESIGN SERVICES68
4.28 OWNERSHIP OF ORIGINAL DOCUMENTS68
4.29 RETENTION OF REVIEW DOCUMENTS68
4.30 CONTRACT DRAWINGS AND SPECIFICATIONS GOVERNMENT FURNISHED PLANNING INFORMATION68
4.31 COORDINATION WITH MEDICAL CENTER69
4.32 RESPONSIBILITY OF THE DESIGN-BUILD CONTRACTOR69
ATTACHMENTS70
ATTACHMENT 1 - RELEASE OF CLAIMS70

SCHEDULE

PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
0001
Demo Buildings 4, 5, 6, & 10 (Design Build) per all requirements in SOW, Design Specifications, Design Drawings, Federal, State, Local Codes, and VA Policy / Standards.
1.00
JB
$0.00
$0.00
GRAND TOTAL
$0.00

ACCOUNTING AND APPROPRIATION DATA

ACRN
APPROPRIATION
REQUISITION NUMBER
AMOUNT
1
503-3630162-5071-854200-3220
503-23-2-5071-0007
$0.00

DELIVERY SCHEDULE

ITEM NUMBER
QUANTITY
DELIVERY DATE
001
Demo Buildings 4, 5, 6, & 10 (Design Build)
1
420 Days after NTP

Page 1 of Page 1 of

INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS

(a) Phase I Proposal information and contract forms may be obtained by general (prime) contractors interested in submitting a proposal direct to the Department of Veterans Affairs and by suppliers and subcontractors for their use in preparing sub-bids for general (prime) contractors from the System for Award Management (SAM) Contract Opportunities website at https://sam.gov under solicitation number 36C24423R0045. By registering at SAM, prime contractors, suppliers, and subcontractors will have access to download Scope of Work, solicitation, and amendments.

(b) PHASE II ONLY, an Offer Guarantee is required for this solicitation. An offer guarantee is required for the Phase II part of solicitation, in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000.00. The Offer Guarantee is to be executed on a SF 24. Failure to furnish the required offer guarantee on the proper form and amount, by the time set for the proposal due date, will require rejection of the offer in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then.

(c) The offeror to whom award is made will be required to furnish two (2) bonds, a Payment Bond to be executed on the SF 25A and a Performance Bond to be executed on the proper SF 25, each in the penal sum as noted in the General Conditions of the Specification. Copies of the SF 25 and SF 25A can be obtained upon application to the issuing office.

(d) Disclosure of the magnitude of construction: Between $1,000,000 and $2,000,000

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

POSTING - Solicitation AND ATTACHMENTS for PHASE I The Veterans Integrated Service Network #04 (VISN 04) Contracting Office / James E Van Zandt (Altoona) Veteran Administration Medical Center is issuing the attached solicitation with attachments and subsequently the VA intends on awarding a single, Firm-Fixed-Price contract that will be the “Best Value” to the Government based on evaluation factors and price. The project will be for the selection of a prime contractor NAICS code 238910, with a size standard of $19.0 million. The prime contractor to contract/partner with an architect/engineering firm to provide design-build services necessary for completion of designs and the objective – Demolish Buildings 4, 5, 6, & 10 (This is a Design-Build project).

Note: This notice is for Phase I submittals Only at this time. ALL Qualified PHASE I Offerors that are 100% SDVOSB may submit for Phase I. After Phase I evaluation is complete, ONLY Offerors that are selected for Phase II will be notified with instructions for Phase II proposal submission

Project Scope Summary The Design-Build team shall provide all, labor, materials, tools and equipment, and design-build services necessary for design and demolition of a project described here along with other specified tasks as further defined in a request for proposal (RFP) for Demolish Buildings 4, 5, 6, & 10 Project No. 503-21-107. The project shall be designed and completed in accordance with current VA guidelines, EPA requirements, VA Specifications and developed specifically to meet local requirements for the James E Van Zandt VA Medical Center in Altoona PA. The resultant contract of this procurement is to provide required design completion of the referenced project and perform construction / demolition of completed design work.

Selection/Administration:

This project is a “Best Value” two-phase design-build solicitation. The Phase I offers will be evaluated to determine which of the offerors will be selected to make an offer in Phase II of the solicitation. The Request for Proposal shall set forth the requirements for responding to Phase I of the solicitation as well as all evaluation factors for both Phases I and Phase II.

Phase II solicitation will be issued in an amendment as a Request for Proposal (RFP) conducted in accordance with Federal Acquisition Regulations (FAR) Parts 36.3 and 15 and will be evaluated in accordance with the evaluation factors therein.

Total project anticipated between $1,000,000 and $2,000,000.

INSTRUCTIONS TO OFFERORS

PROCEDURES FOR SUBMITTAL OF OFFERS AND PROPOSAL EVALUATION CRITERIA

1. Overview.

1.1 The intent of this solicitation is to select one contractor to provide professional design and construction services in accordance with the Statement of Work (SOW) for the Demolish Buildings 4, 5, 6, & 10 – Design-Build Project, 36C24423R0045.

1.2 The Government intends to use the “Best Value” tradeoff process source selection approach in accordance with FAR 15.101-1. Award will be made to the responsive, responsible offeror whose offer in conformance with this solicitation, results in the best value to the Government, price plus other factors considered. The Contracting Officer will award a firm fixed price contract to the responsive responsible offeror whom the Source Selection Authority determines conforms to the solicitation, is fair and reasonable, and offers the best overall value to the Government, all factors considered. A single award shall be generated for the project. The Government reserves the right to accept other than the lowest priced offer or to reject all offers. Setting aside for an SDVOSB firm is in compliance with regulations to meet our goals and fulfill the VA’s mission to meet socioeconomic goals.

1.3 This Request for Proposal is issued as a Two-Phase Design-Build procurement (Reference Federal Acquisition Regulation Part 36.3). Proposals will be evaluated in Phase I to determine which offerors will submit proposals for Phase II. A maximum of three (3) offerors will proceed to Phase II unless the Contracting Officer determines that a number greater than three (3) is in the Government’s interest and is consistent with the purposes and objectives of this Two-Phase Design-Build project.

The Phase II Request for Proposal (RFP), in the form of an amendment to this original solicitation, shall be issued to only those successful offerors that were determined to be the most highly qualified from Phase I.

2. Submittal of offers.

2.1 Offerors submitting proposals for this project should limit submissions to data essential for evaluation of proposals, so that a minimum of time and monies will have been expended in preparing information required herein; however, in order to be effectively and equitably evaluated, the proposals must include information sufficiently detailed in Phase I to clearly describe the offeror's technical approach, technical qualifications and past performance to successfully complete the project. Proposals should follow in the order of sequence set forth in the Request for Proposal (RFP). Information provided out of sequence may not be evaluated and may result in the offeror's disqualification from award. Requirements stated in this RFP are minimums.

2.2 Offerors must comply with the detailed instructions for the format and content of the proposal; proposals that do not comply with the detailed instructions for the format and content of the proposal may be considered non-responsive and may render the Offeror ineligible for award.

PHASE I PROPOSAL SUBMITTAL – OPEN TO ALL OFFERORS

2.3 Phase I of the Request for Proposal is open to ALL Offerors. All proposals shall be submitted in PDF Format by EMAIL to melvin.moore2@va.gov. NOTICE: ELCTRONIC SUBMISSION IS NOW REQUIRED. Electronic submissions, MUST clearly follow the below requirements. The Phase I proposal shall address the evaluation factors listed below:

Factor 1 - Technical Approach (but not detailed design or technical information)
Factor 2 – Technical Qualifications
Subfactor 2A – Specialized Experience and Technical Competence
Subfactor 2B – Capability to Perform
Factor 3 – Past Performance

2.4 Phase I proposals shall be received by March 31, 2023, 1:00 pm Local Time. Proposals that are received after this time shall be late and will not be considered. There will be no public opening of the proposals.

2.5 All proposals must be submitted by Electronic Submission – VIA EMAIL, to:

melvin.moore2@va.gov emails must contain in the subject line “PROPOSAL No. 36C24423R0045 Demolish Buildings – Design Build” for Phase I submittal.

2.6. Phase I Proposal Evaluation Process.

2.6.1 A Source Selection Evaluation Board (SSEB) comprised of representatives of the Department of Veterans Affairs will evaluate the proposals. The identities of the SSEB personnel are confidential, and any attempt by the offerors to contact these individuals is prohibited. The evaluation will be based on the content of the proposal and any subsequent discussions, if necessary, as well as information obtained from other sources, e.g., past performance information. Offerors are advised that the evaluation and rating of proposals will be conducted in strict confidence. During deliberation, the number and identities of offerors are not revealed to anyone who is not involved in the evaluation and award process or to other offerors. Proposals will be evaluated based on the factors described below.

2.6.2 The evaluation process for Phase I consists of three (3) Factors and two (2) subfactors: Technical Approach, Technical Qualifications (Specialized Experience and Capability to Perform) and Past Performance. Proposals will be evaluated by the factor and criteria identified below.

2.6.2.1 The Technical Approach, Technical Qualifications, and Past Performance factors are all equal to each other.

2.6.2.2 As demonstrated in their proposals, Offerors shall be evaluated in terms of the Offeror’s ability to meet or exceed the project’s requirements as identified in the SOW, and those proposals demonstrating an ability to exceed specified requirements may be rated higher in those areas than proposals demonstrating only the ability to meet requirements.

2.6.2.3 Provide a clear and concise narrative for each of the factors below. The narrative shall address the information stated in the factors and subfactors. The Government will evaluate the offeror’s answers for information and completeness, and offerors not submitting required information may not be considered for evaluation.

2.6.3 Phase I Evaluation Factors

2.6.3.1 Evaluation Factor 1 – Technical Approach:

This factor evaluates how the individual offeror will approach the design and construction of this project. The firms shall provide detailed information addressing the organization and the roles and responsibilities of the various sub-contractors for both the design and construction. For Design Approach, Firms shall describe the techniques and methods for an efficient, effective design. For Construction approach, firms shall describe the techniques and methods for this construction project to include coordination with the design packages, projected project timelines and coordination of work. The firm should also include considerations of “Fast Track” construction whereby preliminary site construction activities can begin prior to the completion of the accepted 100% design documents.

2.6.3.2 Evaluation Factor 2 – Technical Qualifications:

The offeror shall provide a minimum of one (1) and a maximum of two (2) projects using Exhibit A. The SSEB will evaluate this factor using the information provided by the offeror from Exhibit A along with the information requested in the subfactors below. The offeror shall demonstrate their experience on relevant Design/Build and project(s) that are similar in size, scope, and complexity to the RFP. Indicate the number of design/build projects construction contractor and AE have completed together.

2.6.3.2A Subfactor: Specialized Experience and Technical Competence

This factor evaluates the experience of the construction firm and design team in completing projects requiring skills similar to those anticipated for this contract. Evaluators will use the information provide in Exhibit A, the information from the organizational chart provide in subfactor 2.6.3.2B below, and the resumes of the Architect Firm. This may include general renovation of medical center space to include architectural changes of walls, ceiling, floors, finishes, masonry, doorways including hardware, plumbing including storm sewer, sanitary, hot and cold water, heating, ventilation, air conditioning (HVAC), primary and secondary electrical circuits, digital controls, fire protection to include sprinkler system, central fire and security alarms, audio paging systems, asbestos abatement and all work to return space to finished, functioning condition. Experience providing drawing in 3D.

2.6.3.2B Subfactor: Capability to Perform The Government will evaluate the offeror’s information concerning overall organization, organizational chart with brief relevant details of individual experiences/qualifications, as well as number of personnel and the duties of proposed technical staff to determine if offeror has the ability to manage multi-discipline projects within the areas of consideration chosen without significant difficulty. Offeror shall provide, as an attachment, an Organizational Chart listing company personnel and their roles. Provide names, duties, and levels of responsibility of key personnel to include the Project Manager, Site Superintendent(s), Quality Control Manager, Safety Manager, and Infection Control Manager. Indicate to whom the Quality Control, Safety, and Infection Control Managers report. In addition, contractor shall provide a list of the in-house trades that contractor employs. The offeror shall provide the names, disciplines, and resume of the key personnel of the Architectural Firm that will be used on this project. Offeror should detail its capability in managing projects for the similar size and scope and disciplines needed to accomplish this project. The specific criteria proposed (skill levels and background) for personnel, if adequate, is an indicator of an acceptable organization.

The proposed subcontractors, applicable for multi-discipline consideration, are verifiable, and information provided indicates a good professional relationship, electricians, HVAC, carpenters, plumbing, concrete, etc.

The offeror shall submit information concerning scheduling methodology, to determine if they have scheduling processes that ensure completion and control of the project from beginning to the end of the project. Adequate scheduling processes are necessary to ensure completion and control of the project from beginning to the end. Offeror must provide an organizational chart and tentative schedule, including a timeline for major features of work. In addition, please identify the person responsible for ensuring the schedule is met (ex. Project Manager).

This factor evaluates the ability of the Construction firm to perform given their current projected workload and the availability of their key personnel, to accomplish the project in the required time. Contractor to provide demonstrated compliance to performance schedules, adherence to timelines for deliverables, the ability to meet unusual time constraints and methods of project management

The offeror shall provide adequate detail on the offeror’s policy with regard to Quality Control (QC) and how the offeror intends to achieve this standard on the project. Offerors are also to discuss their ability to comply with the requirements of The Infection Control Manual of the Medical Center

Offeror to discuss their Safety Program in general, and provide, as a minimum, details on training, documentation, and your plan to ensure adherence to OSHA Standards. Offeror is to discuss the steps they took to promote safety during construction during the past five (5) years. Provide a certification that the offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years. If the number exceeds the criteria listed, explain why? Offerors shall submit their current EMR rating. EMR rating should be less than or equal to 1.0. If the number exceeds the criteria listed, explain why?

2.6.3.3 Evaluation Factor 3 – Past Performance:

The SSEB will evaluate past performance for the prime contractor past performance along with the designated team of subcontractors. Documentation of satisfactory performance of projects similar in size, scope, and dollar value will be considered to have met the minimum requirements of the RFP. The Government reserves the right to check any or all cited references to verify supplied information and to assess owner satisfaction as to quality, schedule, cost, and management. The Government may also use other tools such as CPARS, Vet Biz, Dunn & Bradstreet, Federal Awardee Performance, and Integrity Information System (FAPIIS), and Source Selection Evaluator personal knowledge of offeror to gather documentation on past performance. Past performance will be evaluated in accordance with FAR 15.305(a)(2). Evaluations may include past performance information regarding predecessor companies, key personnel who have relevant experience or subcontractors that will perform major or critical aspects of the requirement. Offerors without a record of relevant past performance or for whom information on past performance is not available may not be evaluated favorably or unfavorably on past performance and shall receive a neutral rating for Past Performance. Offerors may provide information on problems encountered on the identified contracts and the corrective action taken, if desired. This shall be rated based on the confidence portrayed for each of the projects submitted. Offeror’s can provide past performance on previous projects for the SSEB team which can be used during the past performance evaluation. A neutral rating is given when no current and/or relevant performance record is identifiable upon which to base a meaningful performance risk prediction. Government Personnel were unable to identify any relevant Past Performance information for the offeror or key team members/subcontractors or their key personnel. This is neither a negative or positive assessment and represents and unknown risk.

PHASE II PROPOSAL SUBMITTAL – This submittal is ONLY open to the offerors that the Government has issued an amendment for Design Concepts, Management Approach, Schedule, and Pricing information.

3.1 Part II of the Request for Proposal is open only to the offerors that the Government provides an amendment to. The top three or four offerors shall supply the information listed below. Proposals for Part II shall be electronically submitted in PDF Format to the Contracting Officer. The Phase II proposal shall address the evaluation factors listed below:

Factor 1 - Design Concepts
Factor 2 – Management Approach
Factor 3 - Schedule
Factor 4 - Price

Offerors shall submit by electronic submission in PDF Format, all the information for Phase II Factor 1, Factor 2, and Factor 3. All pages must be typed using 11- point Times New Roman font and include a table of contents. Failure to place the required submission information under the appropriate (factor or sub factor) and format may result in a lower rating if the evaluators cannot readily find the appropriate information.

In a separate file attachment in PDF Format, the offeror shall submit by electronic submission for Factor 4 – Price.

3.2 All proposals must be submitted in PDF Format by Electronic Submission – VIA EMAIL, to:

melvin.moore2@va.gov emails must contain in the subject line “PROPOSAL No. 36C24423R0045 Demolish Buildings – Design Build, Phase II” for Phase II.

3.3. Phase II Proposal Evaluation Process

3.3.1 The evaluation process for Phase II consists of three (3) non-priced Factors and one (1) priced Factor: Technical Approach, Technical Qualifications (Specialized Experience and Capability to Perform) and Past Performance. Proposals will be evaluated these factor and criteria identified below.

3.3.1.1 The Design Concepts, Management Approach and Schedule factors are all equal to each other and when combined are more important than Price.

3.3.1.2 As demonstrated in their proposals, Offerors shall be evaluated in terms of the Offeror’s ability to meet or exceed the project’s requirements as identified in the SOW, and those proposals demonstrating an ability to exceed specified requirements may be rated higher in those areas than proposals demonstrating only the ability to meet requirements.

3.3.1.3 Provide a clear and concise narrative for each of the factors below. The narrative shall address the information stated in the factors and subfactors. The Government will evaluate the offeror’s answers for information and completeness, and offerors not submitting required information may not be considered for evaluation.

3.3.2 Volume #1 - Phase II Evaluation Factors

3.3.2.1 Evaluation Factor 1 – Design Concepts:

This factor evaluates the offers schematic design based on functional layout of the Pharmacy Clean Room design. Offeror shall provide a schematic showing the overall layout making any potential layout changes to the current set-up and provide narrative to support the offeror’s design concept. Offeror shall address phasing to allow operations to continue during the construction and must work within budget to allow for the VA to continue operations at minimal interference.

3.3.2.2 Evaluation Factor 2 – Management Approach:

This factor evaluates the individual experience of persons that are to be assigned to this project. The offeror shall provide information (resume) for personnel in the following functions as a minimum (offeror to provide any additional discipline it feels appropriate) —Project Management, site superintendence, quality control manager, infection, and safety, as well as a list of major subcontractors. Offeror shall provide resumes of the individuals for the Design Engineering firm that offeror will be using that will be generating the design documents necessary for construction. The offeror shall provide a listing of projects, with a brief description of the projects, where the Offeror and the Design Engineering firm personnel worked together as a team on previous Design-Build projects.

3.3.2.3 Evaluation Factor 3 – Schedule:

This factor evaluates the Offeror’s methodology of the scheduling processes that ensure completion and control of the project from the beginning to the end of the project. The detailed schedule provides the SSEB the extent to which the offeror demonstrates a clear understanding of the architectural and engineering requirements for the construction period and general project delivery. Offeror’s Schedule shall indicate all elements of the design and construction timeline, from notice to proceed (NTP) (in order to establish a common baseline among all offerors) to contract completion, including but not limited to site investigation for design, design meetings, design submittals, preconstruction meetings, material submittals, mobilization, demolition, material lead times, utility installations, abatement (if required), testing, training, commissioning, construction and post-construction submittals, close-out.

3.4 Volume #2 - Price Information:

3.4.1 The offeror shall complete and submit Standard Form 1442. The offeror shall submit a price based on the line items. Note; If discussions or negotiations occur, the Government may require additional cost information. Offerors shall sign and submit all amendments to the solicitation. Please be advised that the Government intends award a contract from Phase II proposals without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a cost or price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary

3.4.2 The offeror shall complete and submit Exhibit B Calculation of Self-Performed Work.

3.4.3 Bid Bond – Phase II only. Offerors shall submit a Bid Guarantee. A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000.00 Bid Bond is to be executed on a SF 24. Failure to furnish the required bid guarantee on the proper form and amount, by the time set for the opening of bids, will require rejection of the bid in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then.

3.4.4 Annual Representation and Certifications shall be completed by offeror.

3.4.5 Discounts: Prompt payment discounts will not be considered in the evaluation of offers.

3.4.6 In the event a minor clerical error has occurred, then the offeror may be given an opportunity to correct the minor error within the constraints of the “clarifications” process or the Contracting Officer determines discussions are required.

4.0 Evaluation Criteria

The price will be evaluated by the Contracting Officer for reasonableness by using price analysis. The Contracting Officer shall perform the Best Value tradeoff using the evaluation factors along with price.

5.0 Discussions

Government intends to make award to a responsible Offeror submitting a conforming proposal without discussions if deemed to be in the best interest of the Government. The Government reserves the right to clarify certain aspects of proposals or conduct discussions providing an opportunity for the offeror to revise its proposal.

The Government reserves the right to reject any or all proposals at any time prior to award and to award the contract to other than the offeror submitting the lowest total price.

2.1 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision)

2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade
Goals for female participation for each trade
%
6.9 %

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is

(End of Provision)

2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

2.5 52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20% percent of the bid price or $3,000,000, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of Provision)

2.6 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021)

(a) Offerors shall obtain from each person acting as an individual surety on a bid guarantee—

(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203–1; and

(2) Standard Form 28, Affidavit of Individual Surety.

(b) The Offeror shall include with its offer the information required at paragraph (a) of this provision within the timeframe specified in the provision at FAR 52.228–1, Bid Guarantee, or as otherwise established by the Contracting Officer.

(c) The Contracting Officer may release the security interest on the individual surety’s assets in support of a bid guarantee based upon evidence that the offer supported by the individual surety will not result in contract award.

(End of Provision)

2.7 52.233-2 SERVICE OF PROTEST (SEP 2006)

Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:

Contracting Officer

Hand-Carried Address:

James E. Van Zandt VA Medical Center 2907 Pleasant Valley Blvd Altoona, PA 16602

Mailing Address:

James E. Van Zandt VA Medical Center 2907 Pleasant Valley Blvd Altoona, PA 16602

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

2.8 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for—

TBD

(c) Participants will meet at— Altoona VAMC (End of Provision)

2.9 52.246-26 REPORTING NONCONFORMING ITEMS (NOV 2021)

(a) Definitions. As used in this clause— Common item means an item that has multiple applications versus a single or peculiar application.

Counterfeit item means an unlawful or unauthorized reproduction, substitution, or alteration that has been knowingly mismarked, misidentified, or otherwise misrepresented to be an authentic, unmodified item from the original manufacturer, or a source with the express written authority of the original manufacturer or current design activity, including an authorized aftermarket manufacturer. Unlawful or unauthorized substitution includes used items represented as new, or the false identification of grade, serial number, lot number, date code, or performance characteristics.

Critical item means an item, the failure of which is likely to result in hazardous or unsafe conditions for individuals using, maintaining, or depending upon the item; or is likely to prevent performance of a vital agency mission.

Critical nonconformance means a nonconformance that is likely to result in hazardous or unsafe conditions for individuals using, maintaining, or depending upon the supplies or services; or is likely to prevent performance of a vital agency mission.

Design activity means an organization, Government or contractor, that has responsibility for the design and configuration of an item, including the preparation or maintenance of design documents. Design activity could be the original organization, or an organization to which design responsibility has been transferred.

Major nonconformance means a nonconformance, other than critical, that is likely to result in failure of the supplies or services, or to materially reduce the usability of the supplies or services for their intended purpose.

Suspect counterfeit item means an item for which credible evidence (including but not limited to, visual inspection or testing) provides reasonable doubt that the item is authentic.

(b) The Contractor shall—

(1) Screen Government-Industry Data Exchange Program (GIDEP) reports, available at www.gidep.org, as a part of the Contractor’s inspection system or program for the control of quality, to avoid the use and delivery of counterfeit or suspect counterfeit items or delivery of items that contain a major or critical nonconformance. This requirement does not apply if the Contractor is a foreign corporation or partnership that does not have an office, place of business, or fiscal paying agent in the United States;

(2) Provide written notification to the Contracting Officer within 60 days of becoming aware or having reason to suspect, such as through inspection, testing, record review, or notification from…